Foundation Design Flashcards

1
Q

What would happen if we neglected soil information that we built our foundations on? (5)

A
  1. weight overloading from the structure to the soil, 2. Sub-stratum could be uneven and lead to unequal settlement, 3. Building surface might not be level, 4. As the structure transmits the load to the ground, stability compromised, 5. Potential lateral movements around the building
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Frost Heave

A

Lifting of the ground due to expansion caused by water freezing in the soil. To avoid, foundations should be at least 600mm below ground

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Swelling and shrinkage

A

Clay soils are subject to shrinking in summer and swelling in winter. Foundations should be 900mm below ground to account for this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the difference between shallow and deep foundations?

A

Shallow is between 0.2 and 2m, and deep is more than 2m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Four types of shallow foundations

A

Strip foundations, ground beams, pad, raft

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Strip foundations

A

II shaped, loads downwards are distributed at a 45 degree angle, creating a defined area of loading. If foundation is too wide, shear failure may result.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

How is shear failure avoided in strip foundations?

A

The foundation is designed so that it does not extend outside the zone of downward loading. As the width is increased, the depth is also increased to avoid shear failure.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Key facts Strip foundations

A

Most common type, weaker the soil/heavier the building, wider the strip. Designed to spread load from uniformally loaded bricks. Mainly used for 2-3 storeys, not suited for seasonal movement soil or poor GC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Advantages of strip foundations (3)

A
  1. Economical for the depth with limited excavation. 2. Simple, 3. Can support a two storey domestic structure
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Disadvantages of strip foundations (4)

A
  1. Wider strips required to support greater loads on poor ground, 2. Trench may require side supporting, 3. Requires backfilling, 4. Limited loading capacity
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the difference between DPM and DPC

A

DPM is horizontal, underneath the floor slab to prevent rising moisture. DPC are installed in the walls to prevent rising damp.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Stepped Strip Foundations

A

These are strip foundations but for sloping ground. Add steps into the foundation to account for the slope to distribute the load down

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Trench fill foundations

A

Where loading or ground conditions permit narrow trenches, trench fill is cost effective. This is just filling the trench with concrete basically

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Deep strip, or trench fill foundations?

A

Strip foundations require the bricks to go further down, so space for them to lay will also need to be dug/supported. Trench fill foundations means you dont need to make this space which is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Trench fill foundations advantages (4)

A
  1. Can cope with groundwater, displaced by poured concrete. 2. Fast method of construction, 3. No trench support required. 4. No backfilling required
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Trench fill foundations disadvantages (2)

A
  1. Higher cost associated with larger volumes of concrete. 2. Lower sustainability in terms of higher cement content
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Pad foundations

A

Spread concentrated loads (like steel beams). A resting point for ground beams. Foundation to brick piers, reinforced concrete columns, steel columns, ground piers. Area of pad is determined by load/soil strength

18
Q

Factors to consider with pad foundations (4)

A
  1. Thickness, 2.Depth (need to reach adequate bearing, avoid moisture movements, avoid frost heave). 3. Position of loading (needs to be centrally in both directions 4. steel reinforcement
19
Q

Pad foundations advantages (3)

A
  1. Economical foundations for steel columns, 2. Can be reinforced to withstand greater axial loads, 3. Can be linked with a continuous beam that provides external wall foundations
20
Q

Pad foundations disadvantages (2)

A
  1. Can use lots of concrete which is bad for cost/sustainability, 2. Large pads pay be required to resist uplifting forces from wind
21
Q

Raft foundation

A

Constructed in the form of a continuous slab extending beneath the whole building. Loadings from building are spread over a wide area. Think multiple pads, with a gigantic plate underneath all

22
Q

When are raft foundations used? (3)

A
  1. Poor soils, building load needs to be spread more, 2. Where soil is variable, 3. Where total area of pad foundation is greater than 75% of total building area
23
Q

What are the steps to construct a raft foundation?

A
  1. Identify the desired depth, 2. Excavate soil, 3. Pour 50mm weak contract as compaction, 4. Erect formwork, 5. Place reinforcement on spacers, 6. Pour concrete, 7. curing
24
Q

Raft foundation advantages (2)

A
  1. Economical solution with minimal excavation depth. 2. Floor and foundations are cast as one, saving time.
25
Q

Raft foundation disadvantages (2)

A

1.Requires formwork and steel reinforcement design, 2.edge of slab has to be protected from the elements

26
Q

Deep foundations

A

Generally referred to as deeper than 3m below ground level - unlikely to be affected by changing conditions at the surface of the ground

27
Q

Piles

A

Columns within the ground, transfer loads from superstructure to the ground.

28
Q

Displacement Piles

A

Driven into ground displacing the surrounding earth. Driven shell (casing) > place the reinforcement > pour concrete

29
Q

Replacement Piles

A

AKA Bored piles. Removing the volume of the soil. The holes are bored by a hollow weighted grab or by rotary borer or auger. Ground is removed by boring and replaced by pouring concrete into void and loweing reinforcmeent cage into the concrete

30
Q

Pile foundations advantages (3)

A
  1. Economical solution to reach greater bearing capacity soils. 2. Can be pre-fabricated off-site, maintaining quality. 3. Can cope with variable ground conditions
31
Q

Pile foundations disadvantages (1)

A

Noise during installation

32
Q

Basement foundation disadvantages (4)

A
  1. Problems with excavation, 2. Construction problems, 3. Achieving watertightness, 4. Leading to cost implications and risk
33
Q

When to use a basement? (4)

A
  1. Needing additional accommodation, 2. to meet planning reqs on building height, 3. to reach good bearing soil, 4. To make use of overburden removal
34
Q

4 Grades of basement

A
  1. Basic utility (car parks etc) 2. Better utility (Retail storage etc.) 3. Habitable (offices, residential) 4. Special (Archive storage etc)
35
Q

Basement walls reqs (4)

A
  1. Need durability (below ground is a hostile environment) 2. Cope with axial and lateral loads 3. Exclude moisture, 4. Design related to grade
36
Q

Tanked basement walls

A

Tanking involved applying a membrane to the inside or outside of the structure. This makes the basement watertight. Defined as ‘Type A’ waterproofing

37
Q

4 types of waterproofing basement strategies

A
  1. Lowering the water table 2. Drained cavity 3. Integral waterproofing 4. tanking
38
Q

Drained cavity

A

Water is collected through the walls in a cavity beneath the basement and pumped out. Need to be wary of possible silting in the pumps

39
Q

Integral waterproofing

A

The concrete keeps out the water. Achieved by optimising the concrete mix design with traditional additions of mineral and chemical admixtures

40
Q

Basement construction process (5)

A
  1. Excavate 2. Raft or slab 3. Structural walls 4. Floor and tanking 5. backfilling