FORMULAS Flashcards
EV
EV = % complete x BAC (or PV)
sum of the planned value of completed work
PV
Planned Value: The value of the work to be completed to a point in time.
The value of the work planned to be
completed to a point in time, usually
the data date, or project completion.
AC
The actual cost of all the work
completed to a point in time, usually
the data date.
BAC
The value of total planned work, the
project cost baseline.
CV
Cost Variance = EV - AC
Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
SV
Schedule Variance = EV - PV
Positive = Ahead of Schedule Neutral = On schedule Negative = Behind Schedule
VAC
Variance at Completion = BAC - EAC
Positive = Under planned cost Neutral = On planned cost Negative = Over planned cost
CPI
Cost Performance Index = EV/AC
Greater than 1.0 = Under planned cost
Exactly 1.0 = On planned cost
Less than 1.0 = Over planned cost
SPI
Schedule Performance Index = EV/PV
Greater than 1.0 = Ahead of schedule
Exactly 1.0 = On schedule
Less than 1.0 = Behind schedule
EAC (CPI remains)
EAC (at planned rate)
EAC (plan no longer valid)
EAC (CPI, SPI)
Estimate at Completion
EAC (CPI) = BAC/CPI
EAC(at planned rate) = AC + (BAC - EV)
EAC (plan no longer valid) = AC + Bottom-up ETC
EAC (CPI, SPI) = AC + (BAC - EV) / (CPI x SPI)
ETC
Estimate to Completion = EAC - AC
or
reestimate
TCPI (BAC)
TCPI (EAC)
To Complete Performance Index
TCPI (BAC) = (BAC - EV) / (BAC - AC)
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
TCPI (EAC) = (BAC - EV) / (EAC - AC)
Greater than 1.0 = Harder to complete
Exactly 1.0 = Same to complete
Less than 1.0 = Easier to complete
Total Float (formulas and definition)
TF = LS - ES
or
TF = LF - EF
Late Start - Early Start
Late Finish - Early Finish
the total float or schedule flexibility is measured by the amount of time that a schedule activity can be delayed or extended from its early start date without delaying the project finish date or violating a schedule constraint. A critical path is normally characterized by zero total float on the critical path.
Free Float (formula and definition)
FF = ESSuccesor - ESPresent - DurPresent
free float is the amount of time that a schedule
activity can be delayed without delaying the early start date of any successor or violating a schedule constraint
Communication Channels
Communication Channels = n x (n - 1) / 2