Formulas Flashcards

1
Q

Planned Value

A

The percent complete based on where the project should be

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the formula to calculate the Earned Value

A

EV = percent complete * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the formula for calculating Cost Variance?

A

CV = EV - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the formula for calculating Schedule Variance? Note that schedule variance can be calculated in time or dollars.

A

SV = EV - PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How do you calculate the Cost Performance Index

A

CPI = EV / AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index

A

SPI = EV / PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion (typical variance)

A

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate to Complete

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

To-Complete Performance Index

A

TCPI = (BAC - EV) / (BAC - AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Variance at Completion

A

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is it that the VAC tells you?

A

The variance at completion tells the amount that a project will be under or over budget at the time of completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the BAC?

A

BAC is the Budget at completion. It is the amount that was originally budgeted for a project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What does the CPI tell you?

A

The CPI is the cost performance index. It provides the rate of spending by looking at the Earned Value and dividing it by the Actual Cost. If the CPI is under “0” then the project is over budget (i.e., 0.792 means that a project is 20.8% over budget). Over “1” means that project is under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does the schedule variance formula tell you?

A

The schedule variance lets you know if you are ahead of or behind the planned schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What information do we receive from the Earned Value?

A

The earned value is the value of work completed to the indicated point. It includes the value of all work completed regardless of what was planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which formula allows you to understand the rate of performance against the schedule?

A

The schedule variance index.