Formulas Flashcards

1
Q

Calculate Float/Slack

A

Float/Slack = (LS – ES = LF - EF)

LS = Late start ES = Early start LF = Late finish EF = Early finish =

0 On critical path

< 0 Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Actual Cost (AC)

A

AC = CV / (CPI - 1) CV = Cost Variance CPI = Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Budget At Completion (BAC)

A

BAC = Sum(PV) PV = Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Communication Channels

A

= N (N-1) / 2 N = # of people in project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Variance (CV)

A

CV = EV - AC (>0) EV = Earned Value AC = Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Performance Index (CPI)

A

CPI = EV / AC (>1) EV = Earned Value AC = Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Earned Value (EV)

A

EV = % Complete x BAC BAC = Budget At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate At Completion (EAC)

A

EAC = AC / % Complete EAC = BAC / CPI AC = Actual Cost BAC = Budget at Completion CPI = Cost Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Estimate To Completion (ETC)

A

ETC = EAC - AC EAC = Estimate At Completion AC = Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Expected Monetary Value (EMV)

A

EMV = Impact X Probability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Normal Distribution

A

1 sigma = 68.26% 2 sigma = 95.46% 3 sigma = 99.73% 6 sigma = 99.999%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Planned Value (PV)

A

PV = SV / (SPI - 1) SV = Schedule Variance SPI = Schedule Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Present Value (PV)

A

PV = FV / (1 + r)n FV = Future Value r = Rate of Interest n = Number of Years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Program Evaluation and Review Technique (PERT)

A

PERT = (O+4M+P) / 6

O = Optimistic P = Pessimistic M = Most Likely

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Schedule Performance Index (SPI)

A

SPI = EV / PV (>1) EV = Earned Value PV = Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Qualitative Risk Score

A

Qualitative Risk Score = Probability x (Scope + Time + Cost + Quality)

16
Q

Schedule Variance (SV)

A

SV = EV - PV (>0) EV = Earned Value PV = Planned Value

18
Q

Standard Deviation (SD) of Activity

A

SD = (P-O) / 6

O = Optimistic P = Pessimistic

19
Q

To Complete Performance Index (TCPI)

A

TCPI = Remaining Work / Remaining Budget TCPI = (BAC - EV) / (BAC - AC) TCPI = (BAC - EV) / (EAC - AC) BAC = Budget At Completion EAC = Estimate At Completion EV = Earned Value AC = Actual Cost

20
Q

Variance at Completion (VAC)

A

VAC = BAC - EAC BAC = Budget at Completion EAC = Estimate at Completion

21
Q

Variance of Activity

A

= (SD)2