Formulas Flashcards

1
Q

Planned Value (PV)

A
  • PV = Planned % complete * BAC.
  • The authorized budget assigned to scheduled work.
  • Amount of money worth of work we that should have been done on the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value (EV)

A
  • EV = % of work completed * BAC.
  • The value of work actually performed.
  • Amount of money worth of work you actually did on the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Cost (AC)

A
  • AC = Total cost incurred for the actual work completed.
  • Amount of money you already spent on the project
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Cost Variance (CV)

A
  • CV = EV - AC.
  • Positive CV means under budget, negative means over budget.
  • The difference between the work done and money spent.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Variance (SV)

A
  • SV = EV - PV.
  • Positive SV means ahead of schedule, negative means behind schedule.
  • The difference between the amount of work we should have done vs. the amount actually done.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Cost Performance Index (CPI)

A
  • CPI = EV / AC.
  • If CPI > 1, the project is under budget; < 1, it’s over budget.
  • The rate of how we are spending to actually earning on the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion (EAC)

A
  • EAC = BAC / CPI
    (If current variances are expected to continue).
  • Forecasting the total cost of the project at the end based on the current spending rate of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Schedule Performance Index (SPI)

A
  • SPI = EV / PV.
  • If SPI > 1, the project is ahead of schedule; < 1, it’s behind schedule.
  • The rate of how we are meeting the project schedule.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Estimate to Complete (ETC)

A
  • ETC = EAC - AC.
  • The expected cost to finish all remaining work.
  • Forecasting the amount that will be needed to complete the current project based on the current performance.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Variance at Completion (VAC)

A
  • VAC = BAC - EAC.
  • Positive VAC means under budget, negative means over budget.
  • The difference between the original budget and new forecasted budget.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

To-Complete Performance Index (TCPI)

A
  • TCPI = (BAC - EV) / (BAC - AC)
  • The performance that needs to be met to finish the project within the budget.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Budget at Completion (BAC)

A
  • BAC = Total planned value of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Critical Path Method (CPM)

A
  • CPM is used to determine the longest path and the earliest completion of the project.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Float (or Slack)

A
  • Float = LS - ES or LF - EF.
  • The amount of time an activity can be delayed without affecting the project end date.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Expected Monetary Value (EMV)

A
  • EMV = Probability * Impact.
  • Used in risk management to calculate the expected risk outcome.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Standard Deviation (SD)

A
  • SD = (Pessimistic - Optimistic) / 6.
  • Measures the range of uncertainty for estimates.
17
Q

Variance (σ²)

A
  • Variance = SD^2.
  • It measures the spread between numbers in a data set.
18
Q

Three-Point Estimate (Triangular)

A
  • Triangular Estimate = (O + M + P) / 3.
  • A simple average of three-point estimates.
19
Q

Three-Point Estimate (PERT)

A
  • PERT Estimate = (O + 4M + P) / 6.
  • A weighted average giving more weight to the most likely estimate.
20
Q

Present Value (PV)

A
  • PV = FV / (1 + r)^n.
  • The current value of future cash flows.
21
Q

Future Value (FV)

A
  • FV = PV * (1 + r)^n.
  • The future value of current cash flows.
22
Q

Communication Channels

A
  • Communication Channels = n(n-1)/2
  • n is the number of stakeholders.
23
Q

Risk Probability and Impact

A
  • Risk = Probability * Impact.
  • Used to quantify risks during risk management.
24
Q

Point of Total Assumption (PTA)

A
  • PTA = (Ceiling Price - Target Price) / Buyer’s Share Ratio + Target Cost.
25
Q

Procurement - Cost Plus Fixed Fee (CPFF)

A
  • CPFF = Total Cost + Fixed Fee.
  • The contractor is reimbursed for costs and receives a fixed fee.