Focus Area Test: PMP Diagram Questions Flashcards
- A project team is currently developing the schedule network for a construction project. Following is how the network is looking after completing the forwardpass (all durations in months). There is a risk that the activity G might take 6 more months to complete. If that happens, what will happen to the critical path?
The critical path will remain unchanged.
Explanation: If activity G takes 6 more months, the total activity duration will become 13 months and the early finish will become the 27th month. This will delay the activity K by a month which will then finish by the end of the 29th month. But this will not delay the activity M which is scheduled to start at the start of the 35th month. [PMBOK® Guide, 6th edition, Page 210]
- You are managing a house construction. The following table gives you a high-level status summary of the work packages on the project. What’s the CPI?
0.91
Explanation: The total cost incurred to date is provided; AC = $89,500 (total of Actual Costs column). However, we need to determine the total Earned Value for this project. Individual activity earned values can be calculated by the formula [Activity EV = Activity % Complete x Planned Value]. Calculating EVs for all activities and adding them up we get $81,250. Plugging these in the CPI formula (CPI = EV/AC) we get 0.91. [PMBOK® Guide 6th edition, page 263]
- A project team is currently developing the schedule network for a construction project. Following is how the network is looking after completing the forward pass (all durations in months). There is a risk that the activity G might incur some delays. What is the maximum amount of delay that can be absorbed by the activity without impacting the network’s critical path?
11 months
Explanation:
To determine this, you need to do a backward pass of the network and determine total floats for all activities including the activity G. Activity G has a total float of 11 months and this is the maximum amount of delay that can be absorbed without impacting the project’s critical path. [PMBOK® Guide, 6th edition, Page 210]
- What is the least amount of time required to complete all of the following activities?
15 days
Explanation: The critical path on the diagram is A->C->D. Adding their durations we get 15 days. [PMBOK® Guide 6th edition, page 190]
- A project team is currently assessing whether it is in the best interest of the company to enhance the current model of a product or design a new product from scratch. The following illustration shows the available options and their impact in case of strong and weak market demands. Which diagramming tool is this?
Decision Tree
Explanation: This is an example of a Decision Tree. A decision tree is a decision support tool that uses a tree-like graph or model of decisions and their possible consequences, including chance event outcomes, costs, and benefits. [PMBOK® Guide, 6th edition, Page 435]
- You are currently auditing a project and asked the project coordinator to supply the latest project’s performance report. The following report was shared with you. What do you think about how the project is performing?
The project cost performance is only 89% in terms of the cost baseline.
Explanation: The project cost performance is not on target. The current CPI of 0.89 indicates that the project is only performing at 89% in terms of the cost baseline. The rest of the statements might be correct but we don’t have enough information to conclude any of these are correct. [PMBOK® Guide, 6th edition, Page 261-263]
- Your organization has been awarded a project to lay a segment of railway track. You have recently analyzed the project’s scope and identified the following high-level activities. The given cost estimates include both direct and indirect costs to complete these activities. If you want to include 15% contingency reserves, 20% management reserves, and hope to make a 25% overall profit, what project budget will you offer to the client if you are negotiating a cost-plus contract?
$21.6 million
Since you are negotiating a cost-plus contract, you need to present the true project costs to the client and must not inflate these with the desired profit margin. The total cost estimate for the project is $16 million. However, you need to add the 15% contingency and 20% management reserves ($2,400,000 and $3,200,000 respectively) to complete the project budget. The total comes out to be $21.6 million. [PMBOK® Guide, 6th edition, Pages 252, 472]
- You are developing a software tool for your organization. The following chart gives the summary status of the project. What do you think about the cost performance of this project?
The project is earning 88 cents per dollar spent.
The project CPI = EV / AC = $25,000 / $28,500 = 0.88. This means that the project is earning 88 cents per dollar spent which doesn’t indicate good cost performance. [PMBOK® Guide 6th edition, page 263]
- A project team is currently assessing whether it is in the best interest of the company to enhance the current model of a product or design a new product from scratch. The following illustration shows the available options and their impact in case of strong and weak market demands. Which decision should you take if the management’s risk tolerance is low?
Enhance the current model
Explanation:
The EMV of designing a new model = 60% * (120 - 80) + 40% * (70 - 80) = $20 million; The EMV of enhancing the current model = 60% * (80 – 40) + 40% * (50 - 40) = $28 million. The management should decide to enhance the current model instead of designing a new model as the EMV of enhancing the current model is higher. Further, there is no loss situation when deciding to enhance the current model regardless of the market condition; hence this option should be selected if the risk tolerance is low. [PMBOK® Guide, 6th edition, Page 435]
- The following is an extract of the project schedule you are currently working on. This is a major project for your organization with a total budget of $21.6 million dollars. You are currently developing a cost performance report for this project. What is the current CPI?
0.89
Explanation:
In order to determine the current CPI, you need to first determine the total project EV to date. The EV of a project activity can be computed by multiplying the activity’s PV with its percentage complete. Calculating individual activity EVs and adding them together you get the total project EV of $4,000,000. The total actual cost is $4,500,000. CPI = EV/AC = 0.89. [PMBOK® Guide, 6th edition, Pages 261-263]
- You are managing a house construction. The following table gives you a high-level status summary of the work packages on the project. You are a bit concerned regarding the final total costs of the project if the cost performance continues at the current rate. What will the project EAC be if the cost overruns continue at the current rate?
$170,330
Explanation: ince you expect the current cost performance to continue, you need to calculate the project’s EAC based on current CPI by the formula EAC = BAC / CPI. The total budget of the project is the sum of individual project activity planned values; BAC = $155,000. The total cost incurred to date is provided; AC = $89,500 (total of Actual Costs column). However, we need to determine the total Earned Value for this project. Individual activity earned values can be calculated by the formula [Activity EV = Activity % Complete x Planned Value]. Calculating EVs for all activities and adding them up we get the total project EV = $81,250. Plugging these in the CPI formula (CPI = EV/AC) we get CPI = 0.91. Plugging these values in the EAC formula we get $155,000 / 0.91 = $170,330. [PMBOK® Guide 6th edition, page 265]
- The following is an extract of the project schedule you are currently working on. This is a major project for your organization with a total budget of $21.6 million dollars. You are currently developing a cost performance report for this project. What is the project’s total EV?
$4,000,000
Explanation:
The EV of a project activity can be computed by multiplying the activity’s PV with its percentage complete. Calculating individual activity EVs and adding them together you get the total project EV of $4,000,000. [PMBOK® Guide, 6th edition, Pages 261-263]
- You are leading a construction project that requires building ten nearly identical buildings. Although you can start the construction of all the buildings at the same time, some constraints such as site access, geographical terrain and construction feasibility, limit you to construct these in a specific order. The schedule of construction is shown below (all durations are in weeks). If due to some reason the completion of building C gets delayed by 10 weeks, how would this impact building H and the project?
The float for building H will reduce to 4 weeks and there will be no delay on the project.
Explanation: Building H is the successor of building C with a total float of 14 weeks. If the completion of building C is delayed by 10 weeks, it will reduce the total float of building H by 10 weeks and it will get reduced to 4 weeks. Since none of the building on the critical path has been impacted, the project completion time will not be impacted. [PMBOK® Guide 6th edition, page 210]
- A project team is currently assessing whether it is in the best interest of the company to enhance the current model of a product or design a new product from scratch. The following illustration shows the available options and their impact in case of strong and weak market demands. According to the given decision tree, what is the EMV of the designing a new model?
$20 million
Explanation: The EMV of designing a new model = 60% * (120 - 80) + 40% * (70 - 80) = $20 million. [PMBOK® Guide, 6th edition, Page 435]
- You are managing a construction project. The following network shows the involved activities and their durations (in months). If the shown dependencies cannot be changed and none of the activities can be completed any earlier, how many months do you need to complete this project?
41 months
Explanation:
In order to solve this network, you need to complete the forward pass. You will find out that the critical path of the network is A -> E -> I -> L -> M and the duration of this critical path is 41 months. [PMBOK® Guide, 6th edition, Page 210]