Florida Wastewater Treatment Plant Operator Practice FDEP Rule Questions Flashcards

1
Q
  1. According to FDEP chapter 62-600.440 (4) (b) FAC, basic level disinfection is
    described as:
A

A chlorine residual of 0.5 mg/L for 15 minutes at peak hourly flow

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  1. FDEP chapter 62-604.550 (a) FAC, requires a wastewater spill shall be verbally
    reported to the state warning point no later than:
A

24 hours from discovery

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q
  1. According to FDEP chapter 62-601, FAC, a composite sample shall be used for
    which test?
A

Effluent CBOD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  1. According to FDEP Chapter 62-602 FAC, an operator could have his/her license
    permanently revoked for
A

Falsified or misrepresented reports, logs or lab sheets

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  1. According to Chapter 62-620 FAC, Wastewater Permitting, plant records must be
    maintained on-site for how many years?
A

Three years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q
  1. According to FDEP chapter 62-600.440 (4)(c) 4, basic level disinfection, any
    ONE sample may not exceed how many colonies per 100 ml sample?
A

800

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q
  1. Which FDEP rule describes requirements for high level disinfection?
A

Chapter 62-600 FAC, Domestic Wastewater Facilities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

8: According to Chapter 62-600.440 (5) (f) FAC, regarding high level disinfection,
any one sample shall not exceed how many fecal coliform values over a 30 day
period?

A

25 fecal coliform values per 100 ml sample

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  1. Chapter 62-601, Domestic Wastewater Treatment Plant Monitoring, states that
    on-site tests for total residual chlorine, pH and_______________can be
    performed under the direction of a certified operator:
A

Dissolved Oxygen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  1. These types of samples may be used for BODS and nutrients at flows less than
    100,000 GPD, according to Chapter 62-601.
A

Grab samples

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  1. According to FDEP Chapter 62-602, Drinking Water and Wastewater Treatment
    Plant Operators, duties of operators includes reporting to the permittee and the Department, as soon as possible, but within 24 hours:
A

Any major interruption of service

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q
  1. According to Chapter 62-610.421 FAC, reuse of reclaimed water, the minimum
    setback distance for a slow-rate, land application systems shall be ______________
    feet from the edge of wetted areas to buildings that are not part of
    the treatment system, or to the property line?
A

100 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  1. How many days, from the last day of application of reclaimed water, land
    application areas shall not be used for grazing of cattle whose milk is intended for human consumption? (DEP Ch 62-610.425 FAC)
A

30 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  1. If this kind of disinfection is provided, the above rule does not apply: (FDEP Ch
    62-610.425 FAC)
A

High level disinfection

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  1. According to Chapter 62-640, Domestic Wastewater Residuals, the definition of a
    pathogen includes viruses, bacteria, protozoa and ____________________
A

Viable helminth ova

Living nematode eggs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  1. According to FDEP Chapter 62-610 FAC, the definition: “Water that has received at least secondary treatment and basic disinfection and is reused after flowing out of a domestic wastewater treatment facility” describes what?
A

Reclaimed water

17
Q
  1. DEP Chapter 62-620 FAC, Wastewater Facility Permitting, requires applications
    for permit renewal be submitted to the department _____________ days
    before the expiration of existing permit?
A

180 days

18
Q
  1. According to FDEP Chapter 62-601 FAC, Domestic Wastewater Treatment Plant Monitoring, discharge monitoring reports (DMRs) for the previous month must be
    submitted to the department by the _____________
    day of the current month?
A

28th

19
Q
  1. FDEP Chapter 62-600 FAC, Domestic Wastewater Facilities, states that all
    treatment plants shall be _____________
    ?
A

Fenced

20
Q
  1. Chapter 62-601 FAC, Domestic Wastewater Treatment Plant Monitoring, states: “For systems involving high-level disinfection, compliance with the TSS
    limitation shall be achieved, and sampled for..”
A

After the filter, and before application of the disinfectant