Flash Cards - CDS - Glossary by Definition
Statements or drawings that modify the basic contract documents after the latter have been issued to the bidders, but prior to taking of bids.
Addenda
An amount added to the contract sum either by an accepted additive alternate or by change order.
Addition (to the contract sum)
Published public notice soliciting proposals for a construction project.
Advertisement for Bids
One who acts on behalf of another.
Agent
Proposal by bidder for amount to be subtracted from or added to the base bid if the corresponding change in the work is accepted.
Alternate Bid
Federal civil rights legislation that establishes the right of persons with disabilities to equal access to sites and buildings and sets design guidelines for its implementation.
Americans with Disabilities Act (ADA)
Contractor’s written request for payment of amount due on account of work completed and or materials suitably stored on the site. Also called Payment Request.
Application for Payment
Material or method that is approved by the architect as being equivalent to what was originally specified.
Approved Equal
An alternative to litigating a dispute, in which one or more arbitrators hears the evidence and renders a decision.
Arbitration
See Record Drawings. (Drawings revised to show changes made during construction. Sometimes erroneously called As Built Drawings.)
As Built Drawings
Regulations that provide for accessibility to buildings and sites for persons with disabilities.
Barrier free Provisions
The sum of money stated in the bid for which the bidder offers to do the work, not including any alternate bids.
Base Bid
The architectural services normally required for a building project, usually consisting of schematic design, design development, construction documents, bidding or negotiation, and construction contract administration.
Basic Services
A proposal by a contractor to do the work required by the contract documents for a stipulated sum of money.
Bid
A surety bond guaranteeing that the bidder will sign a contract, if offered, in accordance with his or her proposal.
Bid Bond
The invitation to bid, instructions to bidders, bid form, and the contract documents.
Bidding Documents
See Surety Bond. (An agreement under which one party (the surety or bonding company) guarantees to make good to another party (the obligee or owner) the debt, default, or failure to perform of a third party (the principal or contractor). See Bid Bond, Labor and Material Payment Bond, and Performance Bond.)
Bond
A provision in the construction contract for payment of a bonus to the contractor for completing the project prior to a specific date, and for a charge (penalty) against the contractor for failing to complete the project by that date.
Bonus and Penalty Clause
An amount included in the contract sum to cover the cost of certain items not specified in detail. Hardware and other finish items are often handled in this manner.
Cash Allowance
A statement by the architect informing the owner of the amount due the contractor on account of work completed and or materials suitably stored.
Certificate for Payment
A document issued by the governing authority stating that a building complies with applicable laws and permitting occupancy for its designated use.
Certificate of Occupancy
A document prepared by the architect stating that the work is substantially complete, thereby establishing the date of substantial completion. It generally fixes the time within which the contractor must complete the unfinished work listed.
Certificate of Substantial Completion
Professional services rendered by the architect, upon the owner’s request, in addition to the basic services identified in the owner architect agreement. Also called Extra Services.
Change in Services (of the architect)
A written order to the contractor, prepared by the architect and signed by the owner, contractor, and architect, which authorizes a change in the work, the contract sum, or the contract time.
Change Order
The owner’s job site representative.
Clerk of the Works
A bond obtained by the contractor or owner, which guarantees that the project will be completed free of liens.
Completion Bond
The architect’s basic services expanded to include certain additional services, such as programming, land use studies, etc.
Comprehensive Services
The sum established by the owner as available for construction of the project. See Project Budget.
Construction Budget
A document, signed by the owner and the architect, which authorizes a change in the work, the contract sum, or the contract time. Used when there is not complete agreement on the terms of a change order. See Change Order.
Construction Change Directive
Working drawings and specifications.
Construction Documents
Management services performed by the architect or others, over and above normal architectural services, that contribute to the control of time and cost in the construction of a project.
Construction Management (CM)
An engineer or other specialist retained by the architect to provide specified professional services to the architect that the architect is required to provide to the owner under the owner architect agreement.
Consultant
An amount of money set aside in a budget to cover unanticipated expenses.
Contingency
Working drawings, specifications, addenda, general conditions of the contract, supplementary conditions, and the owner contractor agreement.
Contract Documents
The total amount payable by the owner to the contractor, as stated in the owner contractor agreement, for performing the work under the contract documents.
Contract Sum
The period of time within which the work must be completed, as established in the contract documents.
Contract Time
An agreement under which the contractor, or the architect, is reimbursed for his or her costs and, in addition, is paid a fee for his or her services.
Cost Plus Fee Contract
A project management procedure in which all events and operations are charted in a way that establishes the optimum sequence and duration of operations.
Critical Path Method (CPM)
A systematic listing of construction trades, materials, systems, and administrative requirements published by the Construction Specifications Institute (CSI) for the purpose of organizing construction specifications.
CSI MasterFormat
The date, certified by the architect, when the construction is sufficiently completed, in accordance with the contract documents, so that the owner can occupy the project or specified area of the project for the intended use.
Date of Substantial Completion
A federal law that requires the Department of Labor to set prevailing wages for government financed construction projects.
Davis Bacon Act
A deposit of money required of each bidder as security for the bidding documents, to ensure the return of the documents by unsuccessful bidders.
Deposit for Bidding Documents
Expense items directly incurred by or attributable to a specific project.
Direct Expense
Salaries and wages attributable to a specific project, plus benefits such as employment taxes, insurance, sick leave, holidays, vacations, pensions, and similar contributions and benefits.
Direct Personnel Expense (DPE)
The General Requirements Division of the specifications that establishes the administrative and procedural duties of the contractor, architect, and owner during construction.
Division One
The requirement that a professional exercise reasonable ability and judgment in a specific circumstance, the absence of which constitutes negligence. Also called Standard of Care.
Due Care
See Professional Liability Insurance. (Insurance that financially protects an architect against claims for damages resulting from professional negligence. Also called Errors and Omissions Insurance.)
Errors and Omissions Insurance
A forecast of probable costs, as opposed to a firm bid.
Estimate
A legally enforceable promise made by the warrantor.
Express Warranty