Finance Flashcards
What is EV?
EV is the value of work completed. It is the monetary value of the deliverables completed.
What does EV stand for?
Earned Value
What does SPI stand for?
Schedule Performance Index
What is SPI?
Schedule Performance Index is another Earned Value term to understand if the project is on schedule. SPI = EV / PV.
SPI reflects only the project-to-date performance for the rest of the project. It is expressed as a number or two-digit decimal such as
.85 or 1.01.
What does PC stand for?
Percent Complete
What does CPI stand for?
Cost Performance Index
What does SV stand for?
Schedule Variance
What is the formula for SV?
SV = EV - PV
Schedule Variance = Earned Value minus Planned Value (or budgeted amount)
What does CEAC stand for?
Calculated Estimate At Completion
What does EAC stand for?
Estimate At Completion
What does ETC stand for?
Estimate To Complete
What is an accrual?
If you book costs to the ledger, but there is no billing to match it, the amount is an accrual. Example: You had $28,040 in project costs that were booked to the current month, but the customer was not invoiced for it. This created a revenue accrual.
What is a revenue deferral?
A revenue deferral is the opposite of a revenue accrual. It is when revenue is billed but has not been earned. IBM: Cost deferrals must meet specific criteria and be approved.
What is the formula for CEAC?
CEAC = BAC / CPI BAC = Budget At Completion CPI = Cost Performance Index = Earned Value (EV) / Actual Cost (AC)
What is the formula for Gross Profit Margin
(1 - (cost / revenue)) x 100