Final Multiple Choice Flashcards
Examples of Projects
Project:
unique, one-time operational activity or effort
Examples:
Constructing: houses, factories, shopping malls, athletic stadiums, arenas
Developing military weapons systems, aircrafts, new ships
Launching satellite systems
Constructing oil pipelines, dams, bridges
Developing and implementing new computer systems
Planning concert, football games, or basketball tournaments
Introducing new products into market
Characteristics of Projects
non repetitive, one of a kind, subject to high uncertainty, etc.
Key person involved in PM
project mgr.
Project team characteristics
Cross functional with diff. skills (engg., mktg., HR, prodn., A/c)
What is Work Breakdown structure (WBS)
Breakdown project into modules, sub-components, tasks, activities for scheduling / planning; responsibility (job description) assignment - SOW)
• Gantt Chart
Graph with a bar representing time for each activity in the project
Provides visual display of project schedule
- When activities start, finish (activities ahead/ behind schedule)
- Where extra time is available and which activities can be delayed
Slack definition, Advantage of slack
allows resources to be temporarily diverted from activities with slack and used for other activities that might be delayed.
CPM/PERT
• Critical path – longest path in the N/W, project cannot be completed in less time than the time reqd. by the critical path, min. completion time of project)
EF=
LS=
EF=ES+t;
LS=LF-t
Forward pass
Backward pass
- Forward pass used to calculate earliest start and finish times
- Backward pass used to calculate latest start and finish times
ES=
LF=
- ES=max of EF of immediate predecessors
* LF=min of LS of immediate successor activities
• For activities on critical path ES=EF and LS=LF & slack = 0
o This implies
Activities on critical path cannot be delayed at all. If any activity on critical path delayed, overall project is delayed
Probabilistic activity times can be described by
beta distribution
Mean of beta distribution =
(a+4m+b)/6
Total project variance =
• sum of variances of activities on critical path
• Project crashing definition
o Indirect cost increases as project duration increases
o crashing cost increases as project duration is reduced
o optimal project time is the one at min. cost