final exam pom Flashcards

1
Q

efficiency means doing the right things to create the most value for the company

A

False

efficiency means doing something at the lowest possible cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

An example of an operation that does not add value is making a wedding cake

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

central to the concept of operations strategy are the notions of operations focus and trade offs

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

the closer the customer is to the customer order decoupling point the longer it takes the customer to receive the product

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

the central problem in virtually every waiting line situation is a trade off decision balancing the costs of adding services with the costs of waiting.

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

the admissions system in a hospital for patients is an example of a single channel, single phase queuing system

A

false

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the three main inputs to an MRP system are the bill of materials, the master schedule and the inventory records file

A

true

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When implemented correctly, MRP links all areas of the business

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Lot for lot is the most common lot sizing technique

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Conformance quality is a strategic decision for a firm

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

The capability index (Cpk) calculates the percentage of items being produced within specifications

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Total, one hundred percent, inspection can never be cost justified

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If the cost to change from producing one product to producing another were zero the lot size would be very small

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Lean production makes implementing green strategies in manufacturing processes more difficult

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Group technology cells help to eliminate movement and queue time between operations

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In the textbook the expression “quality at the source” means that we need to purchase the best quality a supplier or vendor can provide.

A

false

17
Q

Efficiency means doing the right things to create the most value for the company

A

false

18
Q

The capacity focus concept can be put into practice through a mechanism called which of the following?
best operating level (BOL)
B. Plant within a plant (PWP)
C. total quality management (TQM)
D. Capacity utilization rate (CUR)
E. Zero-changeover- time (ZXT)

A

B. Plant within a plant (PWP)

19
Q

Which of the following models uses a schematic model of the sequence of steps in a problem and the conditions and consequences of each step?
A. Probability indexing
B. Johnson’s sequencing rule
C. Decision trees
D. Activity System Maps
E. Decision mapping

A

C. Decision trees

20
Q

Which of the following is not a lot sizing technique used in MRP systems?
A. Lot-for-lot (L4L)
B. Economic order quantity (EOQ)
C. Least total cost (LTC)
D. Least unit cost (LUC)
E. Warehouse loading factor (WLF)

A

E. Warehouse loading factor (WLF)

21
Q

Which of the following is a dynamic lot-sizing technique that calculates the order quantity by comparing the carrying cost and the setup (or ordering) costs for various lot sizes and then selects the lot in which these are most nearly equal?

A. Economic Order Quantity
B. Lot for lot
C.Least total cost
D.Least unit cost
E.ABC analysis

A

C.Least total cost

22
Q

A cost of quality classification is which of the following?

A.Material costs
B.Prevention costs
C.Variable overhead
D.Direct labor
E.Inventory costs

A

B.Prevention costs

23
Q

What is a capacity cushion and why would a firm have one?

A

the capacity cushion is an amount of excess capacity over expected demand maintained by a firm. A firm will typically hold capacity cushions when demand is more rapidly variable than capacity adjustments can be

24
Q

What is the criterion for determining whether a project activity is on the “critical path”

A

the critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete. The simplest answer would be that perhaps their is a delay in completing the activity will result in a delay in completing the entire project

25
Q

Define yield management. How does it differ from the pure strategies in production planning?

A

With yield management, we allocate capacity to customers at the right price and time to maximize revenue. Rather than trying to match demand by adjusting our workforce, inventory or production we adjust demand so that it better matches our production capability. The two approaches compliment one another

26
Q

What does it mean when we say that a process is capable?

A

We say the a process is capable when the mean and standard deviation of the process are operating such that the upper and lower control limits are acceptable relative to the upper and lower specification limits

27
Q

What is sustainability? What can we do at our personal level to promote sustainability?

A

The ability to meet current resource needs without compromising the ability of future generations to meet their needs. In other words, it is a way of life where our resources are managed well and the big and obvious risks are avoided and a way of life that can continue for generations. At personal level we all can
, Walk more and drive (car) less Fly less (by airplanes) Reduce/ reuse/recycle as much as possible

28
Q

A project may be defined as a series of related jobs directed toward some major output and requiring a significant period of time to perform

A

True

29
Q

One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.

A

true

30
Q

.The term “assembly line” refers to progressive assembly linked by some material handling device

A

true

31
Q

What is a work breakdown structure?
A. A list of the activities making up the higher levels of the project
B. A definition of the hierarchy of project tasks, subtasks, and work packages
C. A depiction of the activities making up a project
D. A Gantt chart
E. A structure that is incompatible with the Critical Path Method

A

a definition of the hierarchy of project tasks, subtasks, and work packages

32
Q

Which of the following are the three major components of a queuing system?
A. The source population, how customers exit the system and the queuing discipline
B. The number of servers, the service speed and the waiting line
C. The source population, how the customer exits the system and the servicing system.
D. The source population and the way customers arrive at the system, the servicing systems, and how customers exit the system.
E. The service speed, the queue discipline and the waiting line

A

the service speed, the queue discipline and the waiting line

33
Q

The main purpose of aggregate operations planning is to specify the optimal combination of which of the following

A. Workforce levels and inventory on hand
B. Inventory on hand and financing costs for that inventory
C. The strategic plan and the products available for sale
D. The workforce level and the degree of automation
E. Operational costs and the cash flow to support operations

A

workforce level and inventory on hand