final exam Flashcards

1
Q

write down Xij set variables format. transportation

A

Xij = number of units sent from “i” to destribution center “J”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

2 things to always remember on objective function for transportation

A
  1. put the costs of producing and the the costs of shipping for each variable. dont forget putting the cost!
  2. always put min or max Z
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

always say these 3 things for constraints in transportation

A
  1. Subject to:
  2. verbalize constraints

3, non negativity, binary or integer constraint

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

supply and demand. when one is bigger, another one is less and when they are equal to each other

A

When demand is greater : set supply constraints to =

when supply is greater: set demand constraints to =

when supply and demand are the same: demand and supply constraints set to =

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

LP relaxation BIP formulation

A

is when you relax the binary and integer constraints to obtain the relaxed (optimal) solution

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

a relax solution for BIP formulation will never be better solution than the actual binary or integer solution. true or false

A

false, relaxed solutions will be always optimal. making the the normal solution for BIP feasible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

how to activate the variables for fixed costs on BIP problems

A

supply/capacity constraints 400 is example:

x1-400y1<= 0 or
x2<=400y2
xn<=400yn

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

mutually exclusive constraint where we cannot have both: x1 and x3

A

x1 + x3 <= 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

x1 and x3 muttually exclusive constraint where we need 1 but not more

A

x1 + x3 = 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

if project 4 is selected then project 2 must also be selected

A

x4<= x2
or
x2>=x4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

project 1 must also be if 5 and vice versa.

A

x1=x5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

if project 1 is selected, then projects 2 and 3 must also be selected

A

2X1<= x2 + x3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

if project 1 is selected, then projects 2 or 3 must also be selected

A

X1<= x2 + x3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

project 1 cannot be selected if both projects 2 and 3 are selected

A

x1 + x2 + x3 <=2

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

if projects 2 and 3 are selected, then project 1 must also be selected

A

x2 + x3 <= X1 + 1

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

optimistic approach for decision analysis

A

maximax approach. best of best

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

conservative approach for decision analysis

A

maximin approach. best of worst

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

minimize regret approach

A

minimax. minimizes regret

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

how to calculate regret table

A

best pay off of state of nature - pay off chosen

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

steps for minimax regret approach

A

calculate regrets for each cell. get maximum regret per row. choose the one with least regret

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

decision making approach called laplace

A

equally likely approach

22
Q

decisi9on making approach called hurwicz

A

realism approach

23
Q

equally likely approach

A

maximizes the average payoff per row

24
Q

approach called realism hurwicz. Decision analysis

A

finds a compromise between the best and worst pay off

25
Q

steps for realism approach

A
  1. multiply the best pay off from the row by alpha
  2. (1-alpha)(worst payoff of the row)
  3. add both values
  4. choose the one with highest value
26
Q

expected value approach decision analysis

A

a weighted probability of the payoff*probability in a row. then choose the highest one

27
Q

expected value of perfect information

A

maximum payment for additional information

28
Q

formula for EVPI

A

EVPI = EVwPI - EVwoPI

29
Q

how to calculate EVwPI

A
  1. choose the best payoff from each state of nature.
  2. multiply those values by the probability
  3. add all values
30
Q

EOL approach

A

expected opportunity loss

31
Q

EOL approach steps

A
  1. start with regret table
    2.multiply by probability across SoN
  2. choose with the min regret average
32
Q

P(x | y). what is x and y for decision analysis 2

A

P(result of report | state of nature)

33
Q

draw tables for posterior probabilities

A

prior. conditional. joint ….. marginal. posterior

34
Q

how do you get marginal probabilities

A

add joint probabilities per table

35
Q

how do you get joint probabilities

A

prior * conditional

36
Q

how do you get posterior probabilities

A

joint probabilty / marginal probability

37
Q

decision tree with sample information steps

A

start with decision node.
dont get sample information, or get sample information

  1. if getting, then results of sample. positive or negative or so
  2. paste original tree for each result
  3. change probabilities for posterior probabilities
  4. solve nodes
  5. solve decision
38
Q

node for cpm showing ES EF LS LF

A

ES. # EF

LS. AT. LF

39
Q

earliest start formula

A

earliest time = MAX EF of all immediate predecessors

40
Q

earliest finish formula

A

Earliest finish = earliest start + activity time

41
Q

latest finish formula

A

Min LS of all immediate following

42
Q

latest start formula

A

=latest finish - activity time

or

=Lf - AT

43
Q

slack in terms of CPM

A

LS - ES

or

LF - EF

44
Q

how do you know if an activity is on the critical path

45
Q

In project scheduling. When calculating Total variance, which variances are included in total variance

A

the variances of the activities that lie on the critical path

46
Q

formula for expected time ET or TE (optimistic, most likely and pessimistic)

A

(O+4ML+P)/6

47
Q

variance formula CPM ba

A

Variance = [ (p - o) / 6 ] ^2

48
Q

formula for standard deviation

A

= Square root of total Variance

49
Q

how to get the variance of an activity using standard deviation

A

standard deviation ^2

50
Q

what is the definition of Z-score on project management/scheduling

A

how many standard deviations the project deadline is away from the mean (expected time of completion)

51
Q

100% rule

A

what if you change more than one parameter at the time. will that change the solution? it will not change the optimal solution if the result of this formula is under 1: sum of : change in coefficient/allowable increase/decrease