Final Flashcards
Ron Weasley has been appointed the new Project Manager for a project which will be building an Innovative Electronics product. Earlier to this this job he has worked as a Chief Innovative Officer in a start-up company named Harry Towers Corp., where he earned much appreciation. He helped the start-up to develop many innovative products. Harry Towers Corp. was acquired by the company where Ron is currently appointed. During the planning phase, Ron gave numerous advice to the team and also shared his experiences when he was the Chief Innovative Officer at the Harry Towers Corp. This helped the team gain insights on knowledge areas such as scope, schedule, cost and risk. Even when Ron was new to the team, what form of power was he using?
Expert
Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?
- activity delays
- project delays
- difficulty in taking quick corrective action
- increase costs
- scope creep
Scope Creep
All of the following are types of resource constraints except
- materials
- people
- equipment
- information
- human
Information
All resource leveling techniques involve
Delaying noncritical activities
Resource Leveling or smoothing can have all the following results on a project except
- lower peak resource demand
- reduced resource need over the life of the project
- reduced fluctuations in resource demand
- a longer project duration
- a more sensitive network
A longer project duration
When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?
- physical
- technical
- time
- resource
Time
In resource constrained projects, resources are limited in quantity or availability. Which of the following is the second step in scheduling activities using heuristics (rule of thumb)?
- minimum slack
- maximum slack
- least duration
- lowest activity identifying number
Least Duration
Wilson has realized that two activities in his project cannot be done at the same time because not enough resources are available. Activity 3 is critical and has a duration of 5 days. Activity 4 has 2 days of slack and a duration of 2 days. How will he decide which activity should be scheduled first?
The activity with the least slack
How many processes are there in the Close Project process group?
One
When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is
Time-Constrained
Delaying non critical activities to lower peak demand and, thus, increase resource utilization is called resource
leveling or smoothing
Intense global competition and rapid technological advances create pressure to develop projects rapidly. This is an example of reducing project duration caused by
Time to Market
A contractor finished a bridge across a lake 18 months early and received more than $6 million for the early completion. This is an example of reducing project duration caused by
Incentive contracts
The less steep the cost slope of an activity, the
less it costs to shorten one time period
Emily has recently learned that she needs to reduce the duration of her project to meet an imposed deadline. She has calculated the crash cost per unit and know the maximum units each activity can be reduced. What is the next step?
Identify the critical path
An activity’s normal time and cost are 10 and $150, respectively. Its estimated crash time and cost are 5 and $200. What is this activity’s crash cost per time unit?
10
Adverse weather, design flaws, and equipment breakdown can create negative slack. This is an example of reducing project duration caused by
Unforeseen project delays
Sometimes very high ______ costs are recognized before a project begins and reducing these costs through shorter project durations becomes a high priority
Overhead
According to ________law, adding more manpower to a late software project makes it later
Brooks’
One difference between project management and project leadership is that project management includes
monitoring results against plans
Which group of stakeholders defines the scope of the project and ultimately determines whether or not the project is successful?
Customers
In terms of commonly traded organizational currencies, being involved in a task that has a large significance and having a change to do something important and do it well are examples of _______-related currencies
Inspiration
In terms of commonly traded organizational currencies, sharing personnel, undertaking unwanted tasks, and providing technical knowledge are examples of _______-related currencies
Task
Which of the following is used when the PM walks around, in an unstructured manner, through the workplace, at random to check with employees, equipment, or on the status of ongoing work. The PM walks in an unplanned manner within a workplace, rather than plan where employees expect a visit from managers at more systematic, pre-approved or scheduled times?
This is great for building relationships with key players that will determine a project’s success?
management by wandering around
Which of the following is NOT one of the aspects of leading by example?
Power
Networks among stakeholders are mutually beneficial alliances that are generally governed by the law of
reciprocity
Which of the following is commonly associated with high-performing project teams?
Mistakes are viewed as opportunities for learning
During which stage of team development do members accept that they are part of a project group but resist the constraints that the project and group put on their individuality?
Storming
During which stage of team development is high performance not a top priority and attention is devoted to wrapping up the project?
Adjourning
When a project manager has situations where it is difficult to determine whether conduct is right or wrong, what should she do?
Follow Professional standards and personal integrity
When the team realizes time is limited and focuses more on getting work completed, they are in a way facing a “mid-life crises” in the project. In which group development model has this been emphasized?
Punctuated Equilibrium Model
When is typical for a Large Project to have the kick-off meeting when all the stakeholders are present and discuss on the Project Plan?
After the Planning and beginning of the Executing Phase
Symptoms of groupthink include
Negative stereotypes of outsiders
When a project manager has command of her emotions and respond constructively to others of things get out of control, which of the following traits is she exhibiting?
High Emotional Intelligence