Final Flashcards
(T/F) TAR’s are inherently expensive, sometimes as much as half of the annual budget for the site
true
TAR’s are not frequent events. this results in __________ who will be involved in preparing for and managing the next TAR event
a fairly large turnover of personnel
this deliverable involves the gathering, evaluation, and archiving of key TAR data and sets the stage for the next TAR
TAR close out
data collection after execution for continuous improvement must be done in a timely manner while people are still accessible and data is fresh. names sometimes given to these process events are ______, _____, or _______.
critiques, look-backs, and continuous improvement sessions
(T/F) capturing data for continuous improvement not only includes the execution phase but the preparation and planning phase as well
true
once execution of the TAR plan has been completed, it is extremely important that time is taken to evaluate the effort and capture data around ______, ______, and ______.
success of achieving TAR goals or KPIs, areas of strength that need to be sustained, and areas of opportunity to improve
depending on the size of the outage, post TAR work can take as long as _______ post and as little as _______ post.
12 weeks, 3-4 weeks
(T/F) post TAR work starts directly after the TAR completion
false, after the unit has started up and is running
during execution, the key platers attend meetings from the TAR ______ team and TAR ______ team; adjustments are made basis the data being measured
management and planning
(T/F) during execution, update meetings are held bi-weekly to review safety stats, environmental compliance, progress, cost, and other key elements of the TAR.
false, daily
TAR execution is managed by setting up and maintaining proper _______.
project controls
what are the 4 phases of a TAR execution?
unit shutdown and equipment preparation, TAR maintenance window, equipment turnover and commissioning, and unit inventory and startup
the ability to achieve success in execution is directly proportional to several factors: ? (6)
size, adoption of TARPG, adherence to TARPG deliverable compliance, effective governance, clear goals and organizational alignment, and effective project controls
(T/F) some TAR’s may execute over 500,000 manhours in a 40-day window, with manhour levels peaking over 1500 craftspersons- they involve working long hours for many days straight
true
(T/F) by nature, TAR’s are very intense, high activity events that occur in a very compressed timeframe
true
being environmentally ______ is key to achieving a successful execution of a TAR
compliant
(T/F) conducing a TAR safely and without injuries is a big challenge but paramount
true
pre and post TAR work being included in the TAR plan and coded so the work can be segregated and scheduled separately allows for what?
quantifying the amount of resources and time it will take to complete preparations/post TAR activities
(T/F) pre and post TAR work is not included in the TAR plan and is coded so the work can be segregated and scheduled separately
false, is included
depending on the size of the outage, pre TAR activities can start as early as _______ out and as little as _______ out.
12 weeks, 3-4 weeks
(T/F) pre TAR work should start prior to the TAR with enough time to complete all preparatory activities prior to the unit shutdown
true
during the TAR plan alignment and agreement stage, contingency plans are also reviewed and discussed for clarity and agreement. the deliverable from this event is a _________ that has been agreed to by all players
final TAR plan and schedule
this is the stage for all elements of the TAR plan and schedule to be finalized
TAR plan alignment and agreement
this exercise consists of conducting a walk thru or simulation of the TAR plan and schedule. key players are assembled with each representing their area of responsibility for the TA- each walks through their respective section of the TAR plan and schedule, shift by shift to gain alignment and identify any last gaps.
TAR plan alignment and agreement
___________ are drafted and used to measure progress on addressing items by the TAR planning and management teams; a final book is assembled with the key threats and plans being published and communicated to the entire site
mitigation and contingency action plans
the design or intent of threat assessment is to assemble ______ to identify and risk-rank the threats that may occur during the outage and have a negative impact on the effort
key execution staff personnel
________ activities are optimally performed following development of the TAR plan and schedule and 2 months prior to the start of the outage.
threat assessment
if there is an overage on the final estimate, a business decision must be made to either obtain the funds to cover the difference, or reduce the amount of work scope to be performed. if funding is increased, impact is negligible to the TAR plan. however, if work scope reduction is chosen, potential impact to the TAR plan is directly proportional to the _________ and _________.
size of the reduction and remaining time to the outage
once the TAR plan has been scheduled with a resource loading control plan, a _______ can be generated by taking manhours from the manpower loading control plan and applying the corresponding hourly rates to each craft type
final estimate
once resources have been leveled, the CMMS can then be used to generate ________, which quantify the numbers of craft types by shift, by day for the entire job; this provides a control mechanism to be used in managing craft numbers each day of the TAR and will also be used to generate the final budget/estimate
manpower histograms
once the critical path has been determined, resources can then be “_______” on all non-critical path activities; this reduces the total number of craftspersons needed to a more manageable number to complete the work still inside the duration dictated by the critical path
leveled
an additional parallel path through the critical path network with the total durations shorter than the critical path is called ________
sub-critical (or non-critical)
(T/F) a project can have several, parallel, near critical paths
true
(T/F) there can be float on the critical path
false, there is no float on the critical path
any delay of an activity on the critical path directly impacts the _________.
planned project completion date
the critical path determines the ______ to complete the project
shortest time possible
the sequence of project network activities which add up to the longest overall duration
critical path
______ calculates the longest path of planned activities to logical end points or to the end of the project, and the earliest and latest that each activity can start and finish without making the project longer; it determines which activities are critical and which have total float
critical path method
when the TAR plan is ready to be scheduled (activity sequencing) and resource loaded (leveling) using the CMMS and EVM, a scheduling method called _______ is used; this was developed in the 1950s by James E. Kelley, Jr. of Remington Rand Company, and Morgan R. Walker of DuPont.
critical path method (CPM)
______ are an integral player in TARPG and their involvement early on and full time is essential to achieving success in safely executing the TAR
operations
failure to accurately align the timing of equipment availability with the mobilization of the workforce will result in many manhours being wasted with workers waiting on equipment to be turned over. this can result in ______ and _____.
budget overruns and schedule non-compliance
decommissioning and commissioning schedule
along with thorough procedures with sufficient detail, operations need to lay out an accurate _______ that will provide the necessary data to schedule the maintenance activities of the TAR plan
shut down and start up process
due to the infrequency, complexity, and level of responsibility TAR’s present to operations, it is imperative that they have ___________ to safely guide the operators step by step through the
thorough procedures with sufficient detail
(T/F) once the unit is secured and prepared, operations is responsible for permitting all of the work activities scheduled to take place in their unit
true
(T/F) most facilities run their units for several years between TAR’s
true
______ have the responsibility to ensure safe and reliable operation of each of the units; they have ultimate control over all activities within their respective unit areas.
operators
_______ is the discipline that operates each of the units or assets within a facility. they staff each of the units, round the clock with personnel- these workers are known as ________.
operations, operators
planning for materials (take offs) involve identifying the ______ to execute each job as well as the proper _________.
materials required, design specifications
entering WBS and coding at the task level of each job plan in the CMMS tool allows the scheduler to extract management reports; the TAR coordinator and manager use these reports to measure _______ and “drill down” to uncover root causes and contributing factors to non-
conformance
progress (earned value)
a “planning and scheduling” tool is normally used in EVM- this planning and scheduling tool is sometimes referred to as _______ and incorporates EVM.
computerized maintenance management system (CMMS)
earned value management provides ______ data for project decision making
quantitative
the _______ is an essential component of earned value management and serves as a reference point for all EVM related activities
project baseline
earned value management issued on the cost and schedule control and can be very useful in _________
project forecasting
most companies utilize a system called ________. it helps project managers to measure project performance; it is a systematic project management process used to find variances in projects based on the comparison of work performed and work planned
earned value management (EVM)
involved in executing the event, each TAR job has ben individual job plan built containing _______ and _______.
accounting for the thousands of sequenced activities
once the planning team receives ______, each project is planned and estimated
accurate identification of the work scope and individual job plans
issue for construction
in project engineering and detail design there must typically be approval upon the ______ from the project stakeholders
completion of each stage
the stage of project engineering and detail design where detail design is complete- planning scheduling, ordering materials commences
issue for construction (IFC)
the stage of project engineering and detail design where the detail design quantifies the project
cost for management approval
issue for approval (IFA)
the stage of project engineering and detail design where there is preliminary design funding and scope definition
concept approval
the stage of project engineering and detail design that provides initial funding for better definition on scope clarity
front end loading (FEL)
the stage of project engineering and detail design where there is the initial decision to pursue the project
project initiation
the deliverable of project engineering and detail design is typically called “_________” or “__________” drawings; they are then used by the planning team to estimate, plan, schedule, and order materials for the project
construction packages or issued for construction (IFC)