The dollar amount of the proposal for supplying materials or labor for a specific job is called:
A bid price
The estimated number of brick per square foot is:
6.75 standard-size brick, 5.8 oversize brick, or 3 economy brick
The surface area of one standard-size CMU, including a head joint and bed joint, is:
0.88 square foot
A 1-cubic foot bag of masonry cement can be mixed for mortar to lay approximately:
125 brick or 40 block
The number of 1-cubic foot bags of masonry cement that can be mixed with 1 cubic yard of sand for making mortar is estimated to be:
8 bags
The number of cubic feet in 1 cubic yard is:
27 cubic feet
The amount of labor required to perform a specific amount of work is called the:
Labor constant
Name 3 factors that influence the cost of the labor required to complete a job:
Employee wages and benefits
Site Accessibility
Workers’ compensation and insurance premiums
The method for charging costs in which the owner is obligated to pay the contractor for furnishing the materials and labor at a mutually established and accepted rate or price is called:
Time and materials
The area of a triangular gable-end of a house is calculated using what formula:
1/2 (base x height)
The part of a building below the first floor framing is know as the:
Foundation
The concrete structure supporting the foundation walls and transmitting the structure’s weight to the soil is called the:
Footing
Name 3 things that determine the size of a footing:
The load-bearing capacity of the soil
The wall design
The number of stories
The minimum thickness of concrete for residential footings is:
8”
Name 3 things that help determine the compressive strength of the concrete chosen for the footings:
The type of construction
The location of the concrete
The weathering potential