FAR-Long Term Contracts Flashcards

1
Q

What kind of an asset is the CIP (Construction In Progress) Account?

A

Current Asset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is created when CIP is greater than Billings?

A

A current asset

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is created when CIP is less than billings?

A

A current liability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

When are anticipated losses recognized?

A

Under either method, anticipated Losses are always recognized immediately.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What method recognizes income throughout the life of the project?

A

Percentage of Completion Method. The Completed Contract Method does not recognize income until the contract has been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How is profit calculated under the Percentage of Completion Method?

A

Costs Incurred to Date/Total Construction Costs = Percentage of Completion

Percentage of Completion*Total Profit = Profit Recognized to Date

Profit Recognized to Date - Profit Recognized in previous years = Profit to recognize this year

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What makes up Total Construction Costs?

A

Actual Costs + Costs estimated to Complete

Note: This is not an error

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the difference between ‘estimated to complete’ and ‘estimated at complete’?

A

‘At Complete’ is total costs

‘To Complete’ are costs from today till complete. Is separate from ‘Actual Costs’ and is added to ‘Actual Costs’ to get ‘Total Construction Costs’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Which criteria must be met to use the percentage of completion method?

A
  • Dependable estimates can be made of contract revenues, costs, and progress toward completion
  • The contract clearly specifies the enforceable rights
  • The buyer can be expected to satisfy obligations
  • The contract can be expected to perform their obligations
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What two items are included in the Construction in Progress (CIP Account)?

A

Costs, and profits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When is profit recognized under the Completed Contract Method?

A

All income from the contract is related to the year of completion, even though only a small part of the earnings may be attributable to effort in that period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the Cost Recovery Method?

A

Profit is not recognized until all costs have been covered through cash receipts. After all costs have been recovered, future cash receipts can be applied towards revenue.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If a receivable is subject to subordination, what method is used to recognize revenue?

A

The cost recovery method

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

When is an asset created under the Percentage of Completion method?

A

When CIP>Billings

Costs + Profit in excess of billings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

When is a liability created under the Percentage of Completion Method?

A

When Billings>CIP

Billings + in excess of costs + profits

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the purpose of the Percentage of Completion Method?

A

Revenues earning and expenses are realized based on the percentage of the construction job completed. This creates better matching.

17
Q

What are the two criteria when the Completed Contract Method be used?

A

Two criteria:

  • Percentage-of-completion cannot be determined
  • Total costs cannot be estimated