Q

what is an opportunity for a GCO (government contracting officer) to explain to an offeror why their proposal was or was not selected?

A

debriefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

who can request a debriefing?

A

both the successful and unsuccesful offeror

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

what are the three reasons for doing a debriefing?

A
  • agencies enhance relationships with industry
    -offerors gain better understanding how to improve future proposals and be more competitive
    -offerors feel confident that they’ve been treated fairly in the acquisition process
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What type of debriefing takes place prior to a contract award?

A

preaward debriefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What type of debriefing takes place after the contract award is announced?

A

post-award debriefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Can offerors request both types of debriefings?

A

No! They can only request one!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What section of the FAR discusses what is permissible or not during a debriefing?

A

FAR part 15.5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What three things are included in a pre-award debriefing?

A

evaluation of significant proposal elements, rationale for elimination, reasonable responses to questions if source selection procedures were followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What can be discussed in a post-award debriefing?

A

significant weaknesses or deficiences, overall evaluated cost price and technical ratings, past performance information, rankings of all offerors, summary of award rationale, make/model of item to be delivered, reasonable responses to questions about if source selection procedures were followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

what are these?
-number of offerors
-identity of offerors
-content of prposals
-ranking
-evaluation of others
-point by point comparison
-any prohibited or exempt from FIOA information

A

Things which cannot be discussed in a pre-award debriefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

what are these?
- a point by point comparison of proposals
- any information prohibited or exempt from release under FIOA acts

A

what cannot be discussed in a post-award debriefing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is this?
If a supplier requests information on an award that was based on factors other than price alone, a brief explanation of the basis for the contract award decision shall be provided

A

FAR part 13 simplified acquisitions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

If you are using FAR part 12 (commercial items), what do you need to remember?

A

You need to provide a debriefing if requested. It would address the same elements in Far Part 15.506

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What does GSA FSS in Far Part 8 state?

A

does not use the term “debriefing” instead states there is a brief explanation to unsuccessful offerors on awards based on factors other than price

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What happens with debriefings in a Multiple Award IDIQ Contract (indefinite delivery/quantity)

A

post award debriefing is provided if requested

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What happens to debriefings in a two-step sealed bid?

A

Far part 15 is still relevant

17
Q

What happens to debriefings in R & D contracts?

A

FAR part 15 is still followed

18
Q

What happens with Architecture-Engineering Services?

A

You need to provide postaward debriefings in accordan with FAR part 15, with some exceptions

19
Q

What is the time length of how long an offeror has to request a debriefing?

A

3 days

20
Q

What is the time length the government has to conduct a debriefing upon receiving a written request for one?

A

5 days

21
Q

What is special about the DOD?

A

the CO will include in the debriefing info to unsuccessful offerors an opportunity to submit additional questions. These questions must be submitted back to the DOD within 2 days. The agency must respond back within 5 days

22
Q
A