Experience E: Administration and Observation of Contract Works Flashcards
What situations may warrant an Extension of Time?
- Unforeseen physical conditions
- Weather
- Delays with Principal/separate contractors
How long does the EtC have to respond to an EoT request from the Contractor?
10 working days from time of claim.
- A granted claim extends the date of practical completion
How are RFI’s responded to in NZIA SCC ?
Architects directions.
How are RFI’s responded to in NZS3910?
Responses via CAN’s and instructions via Contract Instructions
What is a variation claim? Give an example
An alteration to the scope of works in a construction contract.
- Change of scope in the relocation of the GF swimming pool from SW corner to northern edge.
What is a payment claim? How must they be issued?
A demand for payment made by the Contractor to the Principal which sets out their claim to be paid for construction work carried out to date under the construction contract (CLAIMED AMOUNT).
- Can be issued alongside or be incorporated into an invoice.
- Can be claimed once per month.
A payment claim must:
- Be in writing
- Contain sufficient details to identify the contract to which it relates.
- Identify the work and relevant period for which the Payment Claim relates.
- State the claimed amount and due date
- Indicate how the claimed amount was calculated
- State that it is a payment claim made under the Construction Contracts Act.
What is an Offsite payment
- Payments to be made for the storage of equipment and building materials during the construction process. This is usually included as a provisional within the construction contract. Both the SCC and NZIA3910 convey a transfer of title from the Contractor to the Principal
What is a payment schedule?
A schedule issued by a building client after having received a payment claim, if they dispute part or all of the claimed amount.
A payment schedule must:
- Be in writing
- Identify the payment claim to which it relates
- State an amount of the payment claim (if any) which is not disputed and which it proposed to pay.a
What are Liquidated Damages?
LD’s is a predetermined compensation established by parties during contract formation. They ensure that each party upholds their obligations.
A Liquidated Damage is a pre-determined figure that will be paid to one party following a contract breach.
What are the 3 stages of the Payment Regime in the Construction Contracts Act 2002 - Payment Claims and Payment Schedules?
- A payment claim is issued by the Contractor (PAYMENT CLAIM)
- If the amount owing under a Payment Claim is disputed, a payment schedule is issued by the Principal (PAYMENT SCHEDULE).
- Adjudication where a dispute is not resolved between parties.
What is a contractors bond?
A contractors bond is a predetermined amount set out in the construction contract and is a guarantee from a third party that if the Contractor fails to deliver on its contractual obligations the bond provider (called a guarantor or surety) will pay instead.
What is a Producer Statement 1? (PS1)
- Design
What is a Producer Statement 2? (PS2)
- Design review
What is a Producer Statement 3? (PS3)
- Construction (often used by the installers of a proprietary system).
What is a Producer Statement 4? (PS4)
- Construction review - Intended for use by a suitably qualified independent engineering construction monitoring professional who either undertakes or supervises construction monitoring of the building works where the BCA requests a Producer statement prior to issuing a Code Compliance Certificate.W