Experience E: Administration and Observation of Contract Works Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What situations may warrant an Extension of Time?

A
  • Unforeseen physical conditions
  • Weather
  • Delays with Principal/separate contractors
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

How long does the EtC have to respond to an EoT request from the Contractor?

A

10 working days from time of claim.
- A granted claim extends the date of practical completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How are RFI’s responded to in NZIA SCC ?

A

Architects directions.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How are RFI’s responded to in NZS3910?

A

Responses via CAN’s and instructions via Contract Instructions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a variation claim? Give an example

A

An alteration to the scope of works in a construction contract.
- Change of scope in the relocation of the GF swimming pool from SW corner to northern edge.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a payment claim? How must they be issued?

A

A demand for payment made by the Contractor to the Principal which sets out their claim to be paid for construction work carried out to date under the construction contract (CLAIMED AMOUNT).
- Can be issued alongside or be incorporated into an invoice.
- Can be claimed once per month.
A payment claim must:
- Be in writing
- Contain sufficient details to identify the contract to which it relates.
- Identify the work and relevant period for which the Payment Claim relates.
- State the claimed amount and due date
- Indicate how the claimed amount was calculated
- State that it is a payment claim made under the Construction Contracts Act.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is an Offsite payment

A
  • Payments to be made for the storage of equipment and building materials during the construction process. This is usually included as a provisional within the construction contract. Both the SCC and NZIA3910 convey a transfer of title from the Contractor to the Principal
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a payment schedule?

A

A schedule issued by a building client after having received a payment claim, if they dispute part or all of the claimed amount.
A payment schedule must:
- Be in writing
- Identify the payment claim to which it relates
- State an amount of the payment claim (if any) which is not disputed and which it proposed to pay.a

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are Liquidated Damages?

A

LD’s is a predetermined compensation established by parties during contract formation. They ensure that each party upholds their obligations.
A Liquidated Damage is a pre-determined figure that will be paid to one party following a contract breach.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What are the 3 stages of the Payment Regime in the Construction Contracts Act 2002 - Payment Claims and Payment Schedules?

A
  1. A payment claim is issued by the Contractor (PAYMENT CLAIM)
  2. If the amount owing under a Payment Claim is disputed, a payment schedule is issued by the Principal (PAYMENT SCHEDULE).
  3. Adjudication where a dispute is not resolved between parties.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is a contractors bond?

A

A contractors bond is a predetermined amount set out in the construction contract and is a guarantee from a third party that if the Contractor fails to deliver on its contractual obligations the bond provider (called a guarantor or surety) will pay instead.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a Producer Statement 1? (PS1)

A
  • Design
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is a Producer Statement 2? (PS2)

A
  • Design review
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is a Producer Statement 3? (PS3)

A
  • Construction (often used by the installers of a proprietary system).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Producer Statement 4? (PS4)

A
  • Construction review - Intended for use by a suitably qualified independent engineering construction monitoring professional who either undertakes or supervises construction monitoring of the building works where the BCA requests a Producer statement prior to issuing a Code Compliance Certificate.W
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are Retention monies

A

Retention money is an amount held back from a payment made under a construction contract. It is usually a percentage of the amount payable of each instalment.

17
Q

What must be done/supplied by the contractor to the Principal/EtC prior to site possession?

A
  • Ensure insurance certificates are signed + schedules to architect
  • Organise bond + signed Schedule
  • have Health and Safety plan
  • 1 copy of contract documents must be kept on site.
18
Q

What happens at an initial site / Pre construction meeting agenda?

A
  • Discuss health and safety plan
  • Discuss contractors program
  • Have evidence of insurances in place
  • Building consent documents to be kept on site at all times.
  • Evidence of Bond.
19
Q

What are unforeseeable physical conditions on site?

A

Conditions on site that could not have reasonable be foreseen and accounted for during the tender stage.

20
Q

What are the stages of disputes?

A

Mediation: Information, confidential negotiation with a mediator. 50-50 split cost between Principal and Contractor.

Adjudication: More formal, confidential negotiation with an adjudicator specifically in relation to the Construction Contracts Act.

Arbitration: Private, judicial determination of a dispute by an independent third party. Final and binding decision.

Litigation: Public civil court case.

21
Q

What is a Certificate of Practical Completion? (CPC)

A

Issued by the architect or contract administrator to the Principal to certify that the building works are completed and meet all the conditions states in the Construction Contract.

22
Q

What is a Certificate of Code Compliance? (CCC)

A

A requirement of the Building Act. A CC is issued when Council is satisfied the completed building works comply with the Building Consent documentation and any items or conditions to the Building Consent are met or provided, including Producer Statements, completed inspections, and warranties. The CC acknowledges the building is safe and fit for occupation.

23
Q

Under the Standard Conditions of Contract SCC, who is allowed to administer the contract?

A

The Architect, or their representative.

24
Q

Under the NZ3910 Construction Contract, who is allowed to administer the contract?

A

The Engineer is required to be ‘an expert advisor to and representative of the Principal (e.g. Project Manager, QS) in administering a contract under 3910.

25
Q

What is the NZS 3910 contract for?

A

Build only contract - Construction

26
Q

What is the NZS 3916 contract for?

A

Design and construct.

27
Q

What is the NZS3917 contract for?

A

Fixed term

28
Q
A