Executing A PI Flashcards
What are the events of a PI execution
PI Planning PO synch scrum of Scrums Preparing for Next PI planning System Demo Inspect and Adapt Innovate
What are PO synchs
The POs across ART and PM meet each week
This is to evaluate progress with respect to PI objectives
Adjust Scope if necessary
PI System Demos- characteristics
POs and PMs give system demos
Held as the last demo of the PI
Platform for SME / business user feedback
Timeboxed
Business value for the PI is reviews with Business Owner
Pillars of LeanAgile mindset
Respect for people and culture
flow
Innovation
Relentless Improvements
Where are Innovations done
Value stream
How to facilitate
Create time by adding Innovation Iteration
Enable edu and learning
Avoid Tyranny of Urgency
Innovation riptide
When during delivery a solution comes up an d flows back in as a feature
Inspect and Adopt aspects
PI system Demos
Quantitative Measurements
retrospective and problem solving
What is Program predictability measure
Shows of achievements fall into an acceptable control band
Rate each each of the objectives on - Time - quality - content Max being the business value of the objective
Avg of all Business values = Program percent achievement score
What is in Performance report
% Achievement = actual/ Planned ( does not have uncommitted)