Excavators Flashcards
Elaborate on the 4 steps in site prep
a) Right of Way Felling – Cutting of standing and down trees (20 meters wide or +/- 3m)
b) Clearing – Stack timber out of immediate construction area
c) Grubbing – removal of stumps, roots, etc.
d) Stripping – removal of unsuitable materials organics, silt, clay
Elaborate on subgrade construction
- movement of rock and other material to create roadbed (unstabilized width), ditches, cut and fill slopes.
• Culverts are not usually installed yet (just some cross ditches)
Elaborate on ballasting (stabilization)
- Make a road surface suitable for traffic with a layer of well graded materials
- Try to use on site materials as much as possible (a lot cheaper)
- Borrow Pits may be needed to supply shortage of materials
- Usually need – rock drill, excavator, FEL, trucks, cat for spreading ballast
Elaborate on drainage installation
- Usually occurs as you ballast up to the culverts or bridges if you are using metal pipes
- Because you can drive them up to the site and deliver the culverts from the back of a truck
- For wooden culverts they can be built concurrent with subgrade
Elaborate on surfacing
This step is often skipped if ballast is suitable (
Shovel vs Excavator?
Shovels push to dig
Excavators pull to dig
Applications of digging bucket and typical size.
- All granular materials and fractured rock
- +/- 2 yards
- Most common general use
Cleanup bucket application
No teeth so harder to break out materials but good for leaving a smooth surface like ditching…
- Large capacity puts more stress on boom
- Good for loading trucks
- Good for stripping
Rock breaker attachment
- Break up to medium hard rock without using explosives
- Useful when working in residential areas
- Need special plumbed machine
What are excavators good at?
– Digging at a distance
– Separate materials
– Place and pile logs, rocks, stumps etc.
– Good on soft ground
– Split puncheon for culverts
Name some suitable applications of excavators
- Extensive cutting, sidehill
- Deep overburden, silt, clay to separate
- Wet conditions
- Deep ditches
- High cutbanks
- Placing and building culverts
What are some conditions that can effect excavator productivity.
• Type of material
– moist loam or sandy loam is good -100%
– Poorly blasted rock is bad – 40 to 50 %
- Angle of swing: A full 180 degree swing to load trucks is slow - 60 % reduction
- Bucket size and type: Use the proper bucket for the application
As conditions get more difficult, what happens to cycle time and bucket size?
Bucket size is reduced and cycle time increases, reducing production.
What is the standard utilization rate for excavators?
83%
What are the typical steps in road construction?
- Site Preparation
a) Right of Way Felling
b) Clearing
c) Grubbing
d) Stripping - Subgrade construction
- Ballasting (Stabilization)
- Surfacing / Drainage installation
Usually done in three passes