Excavation/Grading Flashcards

0
Q

Minimum overdig for crawl space foundation

A

2 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

Name three things considered when excavating a foundation with excess dirt?

A
  • keep trucks ready
  • haul to stockpiles
  • adjust house elevation to minimize hauling
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Protection for equipment of pavement/curbs

A
  • wood planks
  • tires
  • silt fence under 3/4” stone
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What should be accomplished by rough grading of a lot?

A
  • establishing Swales
  • drainage away from house
  • cut for lead walks and driveways
  • evaluate if need for dirt
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Tools needed to check excavation

A
  • lock level
  • 100’ tape
  • blueprints
  • phase specs
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

When is a driveway excavated for a house with integral garage?

A

During back fill

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are three solutions for rock problems?

A
  • hoe ram
  • blasting
  • raise house
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why should excess fill be removed during excavation?

A
  • room for dumpster/lumber

- appearance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What phases should be completed before backfilling for rough grade?

A
  • 8” minimum below top of foundation or slab
  • 6” minimum of fall in first 10’ away from foundation
  • no dirt piles left on lot
  • all debris moved
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What establishes final grade

A

8” minimum below framing member
-remove large debris from lot
Driveways and walks poured and complete

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

How far below the bottom of the lowest framing member should the final grade be held at a minimum and why.

A
  • 8”

- to keep water running away from house

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

When grading home, how far should equipment stay away from house.

A

2 feet

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is minimum overdig for full basement foundations.

A

3’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

What is the minimum overdig for knee wall foundation ?

A

2’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

What is the minimum overdig for crawl space?

A

2’

How well did you know this?
1
Not at all
2
3
4
5
Perfectly