Excavation Flashcards

0
Q

List three types of protection commonly used and providing workers with safety in any trench that is more than 1.5m deep.

A

Shoring
trench boxes
cutbacks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
1
Q

An engineer must certify any shoring in trenches deeper then?

A

6 m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

hard and compact soil walls must be cut back to no less then?

A

30° from the vertical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Other soil types must be cut back?

A

At least 45° from the vertical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

List four things that must be taken into consideration for any excavation over 1.5 m in depth.

A
  1. soil structure
  2. weather in moisture conditions
  3. proximity of other structures and vibration
  4. placement of waste soil
How well did you know this?
1
Not at all
2
3
4
5
Perfectly