Examen 2 Flashcards

1
Q

Project Schedule

A

Describes the software development cycle for a particular project by enumerating the phases or stages of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Work Breakdown Structure

A

Depicts the project as a set of discrete pieces of work. Its the heart of a project plan,as most of other parts of a project are built from it

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Activity Graph

A

Depict the dependencies among activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Critical Path Method

A

Analyzing the paths among the milestones of a project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Real(Duration)

A

Estimated time required to complete the activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Available Time

A

Time available in the schedule for the activity’s completition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Slack

A

The difference between the available and real time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

More realism for CPM

A

We need the resources availability and it does not indicate weekends, holidays etc.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Analogy

A

If we already built a system much like the one proposed, then we can use this info for the estimates

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Delphi Technique

A

Experts are asked to make individual predictions secretly, based on their expertise and using whatever process they choose.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Watson and Felix Model

A

A productivity index is included in the equation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Gantt Charts

A

Invented during World War I to schedule the logistics of getting men and materials to the many ships the US coast for transport to Europe.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Earned Value Analysis

A

A way to measure the amount of work actually performed on a project and to forecast a project’s cost and date of completition

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Planned Value(BWCS)

A

“how much did we plan to spend as of this date?”, “how much work should have been completed by this date?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Actual Cost (ACWP)

A

“how much have we actually spent?”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Earned Value

A

“how much work has actually been completed” (%complete * planned value)

17
Q

Schedule Variance

A

SV = BCWP-BCWS

A negative variance mean the project is behind schedule

18
Q

Cost Variance

A

CV = BCWP-ACWP

A negative variance mean the project is over budget

19
Q

Schedule Performance Index

A

SPI = BCWP/BCWS

SPI <1 means project is behind schedule

20
Q

Cost Performance Index

A

CPI = BCWP/ACWP

CPI < 1 means project is over budget

21
Q

Estimation

A

During the contract process there is a need to estimate the size, effort, and cost of a software product that is yet to be developed.

22
Q

Measurement

A

With the exception of the contract phase and the time preceding the first milestone, measurement activities takes places in all other situations

23
Q

Function Point Analysis

A

Software us better measured in terms of the functionality that it performs.

24
Q

Internal Logical Files

A

Represent data that is stored and maintained within the boundary of the application you are counting

25
Q

Data Element Type

A

Unique user recognizable, non-recursive field

26
Q

Record Element Type

A

User recognizable sub-group of data elements within a ILF or EIF

27
Q

External Interface Files

A

Represent data that your application will use/reference but data that is not maintained by your application

28
Q

External Inputs

A

An elementary process in which data crosses the boundary from outside to inside.

29
Q

File Type Reference (FTR)

A

A file, internal or external, that has been accessed by the transaction

30
Q

External Outputs

A

An elementary process which derived data passes across the boundary from inside to outside

31
Q

External Inquiries

A

An elementary process with both input and output components that result in data retrieval from one or more ILFs and EIFs

32
Q

Risk

A

Uncertain event or condition that might affect your project

33
Q

Four Ways of handling Risk

A

Avoid
Mitigate
Transfer
Accept

34
Q

Risk Assesment phase Activities

A

Risk Identification
Risk Analysis
Risk Prioritization

35
Q

Risk Control Phase Activities

A

Risk management planning
Risk resolution
Risk Monitoring