EXAM2 (Develop the TEMP and Test Planning, Best Manufacturing Practices, Scheduling, Request for Proposal, Work Breakdown Structure, Leadership and Ethics, Systems Engineering in Acquisition, Systems Engineering Process Model, Technical Management Processes, Risk Management) Flashcards

1
Q

Understand the purpose of T&E and why we test

A

The purpose of test and evaluation (T&E) in a development and acquisition program is to help reduce or manage risks in:
Development
Acquisition
Utilization

We test to measure specific individual performance factors.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Recognize the customers of T&E

A

Developers / Acquisition Managers
Designers and Engineers
End-Users

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Recognize the various test agencies

A

Director, Operational Test and Evaluation (DOT&E)
Army Test and Evaluation Command (ATEC)
Army Evaluation Center (AEC)
Operational Test Command (OTC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Recognize the types of DT&E and OT&E

A

Types of OT&E (Operational Testing)
Early Operational Assessment (EOA)
Operational Assessment (OA)
Initial Operational Test and Evaluation (IOT&E)
Follow-on Operational Test and Evaluation (FOT&E)

Types of DT&E (Developmental Test and Evaluation)
Research Effort/Test
Technical Feasibility Test (TFT)
Engineering Development Test (EDT)
Production Qualification Test (PQT)
Production Verification Test (PVT)
First Article Test (FAT)
Production Acceptance Test and Evaluation (PAT&E)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Define test and evaluation

A

Test: Program, procedure or process to obtain, verify, or provide data to determine the degree to which a system or systems meet, exceed or fail to meet stated objectives
Obtains raw data (1’s and 0’s)
Measures specific, individual performance factors
Is resource intensive

Evaluation: Independent process to review, analyze, and assess data obtained from testing or other sources
Produces analyzed information from test data, modeling and simulation, or other sources
Draws conclusions by looking at how the factors interact
Is intellectually intensive

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Define operational effectiveness and operational suitability

A

Operational Effectiveness: How well it does the job?
Operational Suitability: How well it can be supported?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Understand the purpose of Live Fire Testing and when it applies

A

Purpose of Live Fire Testing:
Determines crew survivability and/or system vulnerability
Confirms lethality of munitions/missiles against intended target set
Mandated by FY87 Defense Authorization Bill

Applies to:
ACAT I and II major vehicles and weapons platforms
Conventional weapons that provide some degree of protection
Major munitions greater than 1M rounds

Note - Can be waived - LFT can be waived with justification
Prior to program initiation
Impractical or too expense
Must still accomplish an alternative
To determine vulnerability
Survivability, and lethality

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Define Interoperability and JITC’s (Joint Interoperability Test Command) role

A

Interoperability - The ability of systems, units, or forces to provide data, information, materiel, and services to and accept the same from other systems, units, or forces and to use the data, information, materiel, and services so exchanged to enable them to operate effectively together.

JITC issues a Interoperability Test Certification indicating: System has successfully passed interoperability testing and has met the NR-KPP

Testing is performed on Low Rate Initial Production (LRIP) production representative systems

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Recognize the importance of T&E to milestone decisions

A

Before Milestone A: Approved T&E Strategy

Before Milestone B: Approved TEMP; Identification of LRIP quantities – Only 10% max without waiver; DT&E Report

Before Milestone C: Updated TEMP; Final DT&E Report; Operational Assessment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Define Verification and Validation

A

Verification that the system meets the performance specifications accomplished through Developmental Testing. (Did you build it right?)

Validation that the system fulfills the user’s required capabilities accomplished through Operational Testing. (Did you build the right thing?)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define concurrent testing, combined testing, and integrated testing

A

Concurrent Testing- Circumstances in which developmental testing and operational testing take place at the same time as two parallel, but separate and distinct, activities.

Combined Testing- Single test program conducted to support developmental test and operational test objectives.

Integrated Testing- The collaborative planning and collaborative execution of test phases and events to provide shared data in support of independent analysis, evaluation, and reporting by all stakeholders, particularly the development (both contractor and government) and operational test and evaluation communities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Identify the forum in which the operational tester brings together all the representatives of agencies involved in the Operational or Force Development Test to determine overall readiness for test

A

T&E WIPT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Understand the purpose of the T&E WIPT and when it is formed

A

The T&E WIPT is a defined forum serving the PM, and PMO, as the test and evaluation subject matter experts responsible for supporting the PM, and other program WIPTs, on all aspects of a program’s test and evaluation effort. This effort includes T&E program strategy, design, development, oversight, and the analysis, assessment and reporting of test results.

The T&E WIPT should be established and chartered as early as possible during the Material Solutions Analysis phase so that it is involved in program strategy discussions and plans.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Recognize why independent agencies conduct and oversee OT&E

A

Recognize why independent agencies conduct and oversee OT&E

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Recognize T&E planning and its function

A

As the essential feedback mechanism for the Systems Engineering Process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Understand that the Test and Evaluation Master Plan (TEMP)

A

Must be updated periodically to ensure that it stays current and integrates the various disciplines as the program evolves through its life cycle

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Understand that Developmental Test and Evaluation (DT&E) is

A

Essential in determining a system’s readiness for Initial Operational Test and Evaluation (IOT&E)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Understand that Operational Test and Evaluation (OT&E)

A

Helps determine system operational suitability and effectiveness, and it addresses Critical Operational Issues (COIs) that are defined by the User

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The Logistics Demonstration is normally conducted

A

On those tasks performed at field level and some sustainment level by User representatives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Understand that the Test and Evaluation Master Plan (TEMP)

A

Is prepared by the Program Manager (PM) in conjunction with principal Test Integration Working Group (TIWG) members

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

NDIs (Non-developmental item) are

A

Any previously developed items regardless of the source of development-used exclusively for governmental purposes by federal, state, local, or allied governments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

The DoD Acquisition Guidebook states that

A

Producibility is the design effort priority.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Manufacturing integrated into the design process results in

A

Reduced program risk

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Factors leading to increased cost and production delays

A

Changing design requirements
Late design releases
Lack of production planning
Unstable funding

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

!The three steps in Production and Manufacturing Integration include!

A

!Influence the Design Process
Prepare for Production
Execute the Manufacturing Plan!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

A priority for manufacturing is

A

To develop a stable production process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Process Proofing involves

A

Proving that the design can actually produce a product that meets customer functional requirements in a realistic, “factory floor” type situation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

!The 5 Ms of Manufacturing!

A

!Material
Method
Machinery
Manpower
Measurement!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

!Five top-level design goals for producible products!

A

!Design for Ease of Fabrication
Design for Ease of Assemble
Design for Multiuse
Minimize Number of Parts
Maximize Number of Common Parts!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

!The cost of quality can be broken down into three separate areas!

A

!Prevention
Appraisal
Correcting Failures!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Contractor must have

A

A quality management process, but the contractor defines the process (must meet Government objectives)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Learning curve theory states

A

That as the production of an item doubles, the man-hours needed to produce that item decrease at a fixed rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

!Two main principles of Lean Manufacturing!

A

!Minimization of Waste
Responsive to Change!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

The five major causes of production problems

A

Unstable Rates and Quantities
Design Instability
Undue emphasis on Schedule
Inadequate Configuration Management System
Inattention to Environmental Impacts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

The Integrated Master Plan (IMP) is

A

An event-based plan that identifies the work that must be accomplished to complete the key program activities and events.

An effective schedule correctly balances the tradeoffs between cost, schedule and performance while taking into account risk and program impact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

The 5 step scheduling process includes:

A

Identify the tasks
Sequence the tasks
Estimate the task duration
Construct the schedule
Implement the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

Scheduling is

A

A listing of activities and events organized by time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

Milestones

A

Points in time where decision makers evaluate the status of the program and determine if the program should proceed to the next phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

What phases are?

A

Phases: logical means of translating broad capability needs into well defined system specific requirement ultimately into operationally effective, suitable, and survivable systems.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

Types of Schedules

A

Gantt
Milestone
Network
Production

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

Milestone Charts

A

Depicts information about significant project events, focusing on specific points in time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

The critical path is

A

The longest path through the network (the path with the greatest sum of task time duration). Any delay in tasks along the critical path will result in a delay in the overall project time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

Time constraints are

A

Limitations imposed by the length of time, or dates, associated with the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

Lead is

A

Allows an activity to start before the predecessor activity is complete.

A lead allows an acceleration of a successor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

Lag is

A

A lag directs a delay in a successor activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Intermediate schedules tie (or roll up)

A

Is the detailed schedules to the key events and milestones in the master schedule(s), and provide traceability between the two levels

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

Given task durations, minimum durations, and cost to reduce the duration, be able to evaluate which tasks should be reduced in order to crash the schedule

A

Given task durations, minimum durations, and cost to reduce the duration, be able to evaluate which tasks should be reduced in order to crash the schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

Recognize the roles of the Program Manager and the Contracting Officer

A

Program Manager: Responsible for bringing the program in on time and within budget

Contracting Officer: Responsible for advising the PM and ensuring that all acquisition laws and regulations are followed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

Understand the difference between fixed-price and cost-reimbursement contracts

A

Fixed-Price: Contractor promises to deliver on time and to meet contract specifications for a negotiated price

Cost-Reimbursement: Contractor promises to put forth their best effort

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

!Understand that contracts greater than…!

A

!$3,000 but less than or equal to $150,000 are set-aside exclusively for small businesses, if at least two capable small businesses can be expected to submit offers!

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

Understand that DoD guidance allows contractors to..

A

Use the quality assurance process of their choice, as long as it meets program objectives

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

Identify the three generic classifications of DoD software-intensive systems

A

Weapons Systems

Command, Control, Communications, Computers and Intelligence, Surveillance and Reconnaissance (C4ISR)

Defense Business Systems (DBS)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

Recognize software intensive system acquisition best practices

A

Identify and manage risk continuously throughout the life of the system
Estimate cost and schedule empirically
Use metrics to monitor risk, identify problems, and base decisions
Track earned value
Establish quality targets and track defects against those targets
Treat people as your most important resource
Implement a sound configuration management process
Manage and trace requirements to lowest level
Use system-based software design to document/evaluate process
Ensure data and database interoperability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

Identify the four categories of data rights

A

Unlimited Rights
Limited Rights
Government Purposed Rights
Restricted Rights

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

Define Work Breakdown Structure

A

Product-oriented family tree
Composed of hardware, software, services, data, and facilities
Created from systems engineering process throughout the R&D efforts
Allows acquisition personnel to manage risk at levels lower than system level

Displays and defines the product to be developed and produced

The WBS is an output of the Systems Engineering Process

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

Understand that there are 11 WBS categories and 10 common elements (Level 2)

A

WBS Categories:
Aircraft
Electronic/Automated Software
Missile
Ordnance
Ship
Space
Surface Vehicle
Unmanned Air Vehicle
Unmanned Maritime Systems
Launch Vehicle Systems
Automated Information Systems

Common Elements:
Integration, assembly, test, and checkout efforts
Systems engineering/program management
System test and evaluation
Training
Data
Peculiar support equipment
Common support equipment
Operational/site activation
Industrial facilities (construction, conversion or expansion)
Initial spares and repair parts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

Understand that the WBS is used for

A

Planning logistics
Establishing schedules
Tracking cost
Predicting variations

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

A Functional WBS answers the question

A

What it must do?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

A Product WBS answers the question

A

What must it look like?

60
Q

Identify the two types of WBS

A

Functional WBS

Product WBS

61
Q

Identify the two types of Product WBS

A

Program WBS:
Developed by the Government (Program Management Office)
Entire WBS for the program - includes everything
Consists of first three levels

Contract WBS:
Developed by the Contractor (4th level – “n”)
Complete WBS for the contract
Contains lowest reporting level agreed upon in the contract

62
Q

Understand that the Requirements Analysis application of Systems Engineering includes:

A

Analyze functions

Decompose higher level functions to lower level functions

Allocate performance requirements to the functions

63
Q

Understand that the Overall System WBS Level is

A

Level 1

64
Q

Identify who is responsible for producing the Program and Contract WBS’s and the levels associated with each.

A

Program WBS:
Developed by the Government (Program Management Office)
Entire WBS for the program - includes everything
Consists of first three levels

Contract WBS:
Developed by the Contractor (4th level – “n”)
Complete WBS for the contract
Contains lowest reporting level agreed upon in the contract

65
Q

Understand that Level 2 of the WBS includes

A

Major Elements of the defense materiel item, such as hardware, software elements, program management, training, data, etc

66
Q

!Three types of leadership!

A

!Supervisory, participative, and team (Team is preferred)!

67
Q

!Ethics may be thought of as a set of behavioral standards for a group of people or society!

A

!Ethics may be thought of as a set of behavioral standards for a group of people or society!

68
Q

Ethics can also be defined as

A

Standards of conduct that shape one’s behavior with respect to moral duties and obligations

69
Q

Identify the two major aspects of our personal ethics, according to the Josephson Institute of Ethics

A

Our ability to distinguish right from wrong, good from evil and propriety from impropriety

Out level of commitment to doing what is good, right and proper

70
Q

Understand that although ethical norms vary from organization to organization, and culture to culture

A

There are some core values that have been identified by leaders in education, business, religion and government.

71
Q

Identify the six core ethical values, according to the Josephson Institute of Ethics

A

Trustworthiness
Respect
Responsibility
Fairness
Caring
Citizenship

72
Q

Identify simplest approach to ethical decision-making

A

The “hero test”
Ask yourself how someone you greatly admire would handle the situation
Ask yourself what you would do if your actions were going to appear on the front page of the newspaper

73
Q

Understand the three classical models for resolving dilemmas

A

Consequentialism / Utilitarianism – end justifies the means as long as the greater good is served
The Golden Rule – “Do unto others as you would have them do unto you”
Kant’s Absolute Moral Duties – “Higher truths” are not flexible and there are no exceptions

74
Q

Understand that the Principled Decision-Making model combines aspects of all three classical models, and

A

It calls for decisions to take into consideration the welfare of all stakeholders
It also expects ethical values, such as trustworthiness and fairness, to take precedence over other values, such as efficiency or self-interest
Finally, it offers help in prioritizing conflicting ethical values based on what will bring the most good and the least harm to others

75
Q

Understand that Integrated Product Teams (IPTs) are

A

An important part of the acquisition process, and effective leadership of those teams is essential to their success

76
Q

Recognize that your goal is to…

A

Create an atmosphere within your IPTs in which there is open, honest communication so that fear can be replaced with trust, and where the core ethical values are demonstrated consistently

77
Q

Define the three primary types of leadership styles found in today’s workplace.

A

Supervisory – tends to be directive. They do a lot of one-on-one training. Get personally involved in resolving conflicts. React to changes as they occur. This is natural for first line supervisors, but we want IPT leader to take a different approach.

Participative –
1. Interested in obtaining inputs from the team
2. Consider different points of view prior to decisions
3. Seeks to Develop team member performance
4. Ensures changes lead to improvement
5. Focus is more on participation and involvement of the team members

Team Leadership – ideal style for most IPT leaders
1. Inspires individuals as well as the entire team
2. Creates a team identity and finds ways to harness team member diversity
3. Foresees and influences changes
4. Output of this team is greater than the sum of its members

78
Q

Team Leadership is the ideal style for most IPT leaders

A

Team Leadership is the ideal style for most IPT leaders

79
Q

In the DoD, Systems Engineering is:

A

Typically implemented via Integrated Product and Process Development (IPPD). IPPD is performed by multidisciplinary teams, typically formally charted as Integrated Product Teams (IPTs).

80
Q

Both industry and the DoD have…

A

Similar goals in product development and share key Systems Engineering processes

81
Q

The three Technical Processes for Designing Systems are:

A

Stakeholder Requirements Definition

Requirements Analysis

Architecture Design

82
Q

The 8 Technical Management Processes are:

A

Technical Planning

Requirements Management

Interface Management

Risk Management

Configuration Management

Technical Data Management

Technical Assessment

Decision Analysis

83
Q

Technical Management Processes are….

A

Used to manage the development of system products, including supporting or enabling products.

84
Q

!MIL-STD 499A used to be…!

A

!The mandatory standard used for DoD Systems Engineering. It has be cancelled and replaced with EIA 632 and IEEE 1220!

85
Q

Standards provide….

A

A set of processes that, if performed by qualified persons using appropriate tools and methods, will provide a capability for effective and efficient engineering of systems, including their software components

86
Q

A System is…

A

An aggregation of end products and enabling products to achieve a given purpose.

87
Q

Every system consists of :

A

One or more End Products

A set of Enabling Products

88
Q

System Specifications:

A

This is a type of program-unique specification that describes the requirements and verification of the requirements for a combination of elements that must function together to produce the capabilities required to fulfill a mission need, including hardware, equipment and software.

89
Q

Item Specification:

A

This is a type of program-unique specification that describes the form, fit and function and method for acceptance of end products (e.g., parts, components and other items that are elements of a system model).

90
Q

A ‘program’ WBS displays and defines…

A

The product(s) to be developed and/ or produced by the program. It relates the elements of work to be accomplished to each other and to the End Product.

91
Q

In the DoD, the Program WBS is…

A

Extended to a Contract WBS that defines the relationships between the elements of the program and corresponding elements of the contract work statement.

92
Q

!An Engineering ‘V” Model!

A

!Is a system structure based on a hierarchy of system models and provides the basis for both Top-down System Design and Bottom-up product Realization!

93
Q

The typical sequence of the ‘Bottom-up/Realization’ Systems Engineering processes is:

A

Implementation or Integration

Verification

Validation

Transition

94
Q

Iteration

A

Is the re-application of processes already applied to a system model based on feedback indicating a problem that needs resolution before progress can continue.

95
Q

The System Requirements Review (SRR) is …

A

A multifunctional technical review to ensure that all system and performance requirements derived from the Capability Development Document are defined and consistent with cost (budget), schedule (program schedule), risk and system constraints.

96
Q

Detail Specifications…

A

These specify design requirements, such as materials to be used, how a requirement is to be achieved or how an item is to be fabricated or constructed.

97
Q

Program SEPs are…

A

Formally assessed during milestone reviews

98
Q

There are 8 System Engineering Technical Processes

A

Stakeholder Requirements Definition

Requirements Analysis

Architecture Design

Implementation

Integration

Verification

Validation

Transition

99
Q

An Engineering Work model consists of…

A

Top Down Design and Bottom Up Realization.

100
Q

In early stages of the acquisition life cycle many Systems Engineering technical processes are..

A

Performed by the government “Front-end” systems engineering-like activities include defining architectures and capabilities and conducting functional analyses, and planners usually complete these activities before a program is initiated.

101
Q

A stakeholder…

A

Is any party that has an interest in the outcome of the project

102
Q

The acquirer requirements come from…

A

The end users of the system

103
Q

The JCIDS process formally documents stakeholder needs in terms of capabilities via a series of progressively more detailed documents. JCIDS key documents include:

A

Initial Capability Document (ICD) at Milestone A

Capability Development Document (CDD) at Milestone B.
Capability Production Document (CPD) at Milestone C.

104
Q

The functional baseline is described by

A

The System Specification

105
Q

Logical Analysis enables…

A

A more detailed definition and understanding of the problem to be solved.

106
Q

A derived requirement is…

A

One that is not explicitly stated in a higher-level set of requirements yet required to be satisfied in order to provide a complete system solution

Two Broad Types of Derived Requirements:
- Derived Stakeholder Requirements
- Derived Technical Requirements

107
Q

Behavioral analysis involves…

A

The simulation or stimulation of functional architectures utilizing operational scenarios to expose the model to stressful situations that reflect anticipated usage and environments

108
Q

Interfaces, both for hardware and software, should be defined using…

A

Open System standards to the maximum extent possible wherever feasible and cost-effective

109
Q

Implementation:

A

Is where the lowest system element items are made, bought, or reused. (Involves hardware fabrication and software coding)

110
Q

Integration:

A

Is the Technical Process involved in realization of an End product when the assembled product consists of two or more end products from lower-layer system models. (Involves simulations, EDMs, LRIP models)

111
Q

Verification Process (developmental testing):

A

Confirms that the system element meets the design to or build-to specifications as defined in the functional, allocated, and product baselines.

112
Q

The four types of Verification are:

A

Analysis

Inspection

Demonstration

Test

113
Q

The Validation Process…

A

Tests the performance of systems within their intended operational environment, with anticipated operators and users.
-Most tests conducted by Operational Test and Evaluation (OT&E) are used for Systems Engineering validation events.

114
Q

VV&A stands for:

A

Verification, Validation, and Accreditation

115
Q

PHS&T stands for:

A

Packaging, Handling, Storage, and Transportation.

116
Q

Quality Function Deployment (QFD) starts with…

A

‘The voice of the customer.’ It uses a series of matrices to “flow down’ requirements to various levels.

117
Q

There are 8 System Engineering Technical Management Processes:

A

Technical Planning

Requirements Management

Configuration Management

Technical Assessment

Decision Analysis

Risk Management

Interface Management

Technical Data Management

118
Q

Technical Management Processes:

A

Establish and evolve project plans

Assess progress against the plan

Evaluate and select alternatives.

Control technical project execution

119
Q

Technical Planning, as opposed to program planning addresses…

A

The scope of the overall technical effort needed to develop system products

120
Q

The Systems Engineering Plan (SEP) is…

A

The Government’s foundation plan for Systems Engineering activities planned for use on a project.

121
Q

Event-based schedules are based on…

A

Key events, related tasks and relevant completion criteria for the applicable engineering work model

122
Q

An Interface refers to…

A

The functional and physical characteristics required to exist at a common boundary between two or more systems, end products, enabling products or subsystems.

123
Q

The two types of interfaces are External and Internal:

A

–External Interfaces are the boundaries:
•between a system End Product and another external system End Product; or
•between a human and the environment in which the system End Products will be used or operated.

–Internal: those boundaries between products within a system model that are controlled by the developer or by the government acquirer’s technical effort.

124
Q

The government Program Office and the project IPT will…

A

Play key roles in the development of external interfaces because these may involve interfaces with systems outside the control of the contractor.

125
Q

!The three components of Risk are!:

A

!A future root cause

A probability or likelihood of that future root cause occurring

The consequences (or effect) of that future occurrence!

126
Q

Risk Management includes these key elements:

A

Risk Identification

Risk Analysis

Risk Mitigation Planning

Risk Mitigation Plan Implementation

Risk Tracking

127
Q

Configuration Management (CM) Establishes and maintains…

A

Consistency of a product’s attributes with its requirements and product configuration information

128
Q

Three formal technical baselines established for a system are:

A

Functional

Allocated

Product

129
Q

The product baseline is…

A

At the component level.

130
Q

Technical Performance Measurement (TPM) measures…

A

The current state of a given technical parameter and then estimates how it will evolve over a specific time period based on the planned technical development effort

131
Q

The Technical Authority should be…

A

Independent of the Program Manager in making assessments

132
Q

A Technical Data Package (TDP) provides…

A

A comprehensive description of a given product.

133
Q

Requirements change for a variety of reasons which can include:

A

Emerging technologies

Changing threats

New laws and policies

New missions

Evolving user needs

134
Q

Government program office’s responsibilities:

A

The program manager is responsible for long term storage and retrieval of technical data

135
Q

Risk is…

A

A measure of future uncertainties in achieving program technical performance goals within defined cost and schedule constraints.

136
Q

Aspects of Risk include:

A

Threat

Technology maturity

Supplier capability

Design maturation

Performance against plan

137
Q

Know the key elements of Risk management:

A

Risk Identification

Risk Analysis

Risk Mitigation Planning

Risk Mitigation Plan Implementation

Risk Tracking

138
Q

The Waterfall Effect:

A

As risk mitigation efforts are successfully implemented for an identified root cause, the amount of risk present for that root cause is reduced.

139
Q

Know what Risk is NOT

A

Risk is NOT an opportunity to exceed expectations

Risk is NOT a problem or an issue. These are previously known or unknown risks that have already occurred.

140
Q

Risk Tracking answers the question “How are things going?” by:

A

Communicating risk to all affected stakeholders

Monitoring risk mitigation plans

Reviewing regular status updates

141
Q

Risk identification is structured to help answer the question?

A

What can go wrong?

142
Q

Know who reviews and approves the final risk mitigation plan

A

The Program Manager and the Lead Systems Engineer should review and approve the final risk mitigation plan – PM has final approval

143
Q

Technical Performance Measures (TPM) measure?

A

Actual Results versus Expected Results

144
Q

3 Components of Risk are…

A

A future root cause,

A probability or likelihood of that future root cause occurring,

The consequences (or effect) of that future occurrence.

145
Q

Risk Management in a PM office may be centralized or decentralized

A

In a centralized risk management approach the program manager assigns a risk management coordinator or establishes a risk management board IPT to conduct most of the risk management efforts.
In the decentralized risk management approach, program personnel conduct risk management as part of their normally assigned duties within a program IPT. Since risks are present in every aspect/level of the program the decentralized approach is normally recommended.

146
Q

The 4 Risk mitigation options are:

A

Avoiding

Controlling

Transferring

Assuming