Exam questions Flashcards

1
Q

Which of the following represents a knowledge area typically not done in the Executing Process Group?

A. Integration
B. Risk Management
C. Quality Management
D. Human Resources Management

A

B
The processes found in the Risk Management Knowledge Area are typically not done in the executing process. They are typically only done in Planning and Monitoring & Controlling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

All the following will update the Risk Register from Perform Qualitative Risk Analysis process except:

a) List of potential risk responses
b) Causes of risk
c) Priority list of risks
d) Trends in qualitative risk analysis

A

A.

The list of potential responses is identified in the Identify Risk process. The risk register contains this update already before starting qualitative risk analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How many processes are included in Project Communications Management?

A. 3
B.4
C.5
D.6

A

C.

  • Identify Stakeholders;
  • Plan Communications;
  • Distribute Information;
  • Manage Stakeholder Expectations;
  • Report Performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Using the following information, determine the total price to be paid by the customer. This is a cost-plus incentive fee contract. The share ratio is 80/20, THE TARGET COST IS 150,000 the price ceiling is 180,000. The target profit is 10,000. The actual cost of the project was 140,000

A. 140,000
B. 150,000
C. 180,000
D. 152,000

A

D.

TC=150,000 TP=10,000 AC=140,000 Savings 10,000. Contractor share of saving is 20%x10,000= 2,000
TP= TP+Incentive =12,000

TOTAL PRICE PAID= 12,000+140000=152,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
You are working on a project when the customer demands an early release of the project deliverable ahead of schedule which may be a risk to the project. To meet this demand, you need to start using the most talented resources in the organization. Which risk response are you dealing with?
A. Accept
B.Mitigate
C. Aviod
D. Exploit
A

D. Exploit

An exploit is a positive risk strategy where the organization wishes to ensure the opportunity is realized. If you meet customer demand, the chances of getting more business are higher.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

A key responsibility of the project manager is to ensure the proper adaptation of the project management processes and coordinate the process phases through the project life cycle. This involves balancing the basic aspects of scope, cost, and schedule in addition to managing quality, communication, and customer satisfaction. How can the role of the project manager be best described in a single word?

A. Integrator
B.Leader
C. Communicator
D. DIfferentiator

A

A. Integrator.

The role of a project manager is a combination of all the above options, but the one that is most critical to the project’s success is that of an integrator. As described in the question, a project manager is expected to integrate the project management processes and coordinate the process phases throughout the project management life cycle to ensure all areas of the project come together to successfully deliver the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

The ability of an organization to invite or take the risk to make it an opportunity is called ______.

A. Risk seeker
B. Utility function
C. Risk averse
D. Risk neutreal

A

The ability of an organization to invite or handle risk is called a utility function. It uses the principle of utility theory.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

As a project manager, you need to determine the expected value of the decision to build a new plant. The cost of building the plant is $120 million. There are two probable outcomes. A 60% chance of a strong market, which will result in a $200 million reward, and a 40% chance that there will be weak demand, resulting in a $90 million reward. What is the expected monetary value of this decision?

A.36
B.48
C.12
D.60

A

The decision to build a new plant would cost $120 million. There are two possible outcomes associated with it. There is a 60% chance that there will be a strong demand for your product, which will result in a 200 million dollar reward or payout. The net path value for that scenario is $200-$120 million, or $80 million. There is a 60% probability that strong demand will occur. 60% of $80 million equals $48 million in expected value. There is a 40% chance that there will be weak demand for your product, which would result in a $90 million reward or payout. $90 million minus $120,000 equals $30 million. The net path value is -$30,000. 40% * 30 million =-$12 million. The expected value of this decision is -$12 million. Adding the $48 million and the -$12 million will result in an expected monetary value of the decision of $36 million.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the three elements that characterize Project risk?
A.Severity of impact, duration of impact, and cost of impact

B.Identification, type of risk category, and probability of impact

C.Risk, probability, and impact

D.Occurrence, frequency, and cost

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

As the project manager of a critical project, you need to manage project risk intentionally and methodically, so you have assembled only the project team. Using a risk rating matrix, they identified 32 potential project risks, determined what would trigger these risks, and rated and ranked each risk. In addition, you have reviewed and verified all documented assumptions from the project team, and you have verified the sources of data used to identify and rate risks. You are continuing to move through the risk management process. What have you forgotten to do?

A.Conduct a Monte Carlo simulation

B.Determine which risks are transferable

C.Determine the overall riskiness of the project

D.Involve other stakeholders

A

The risk management process requires input from all key stakeholders, including the project team. The use of a stakeholder register provides the proper identification of stakeholders and their input.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Which of the following contract types does not encourage the seller to control costs and, as a result, places the greater risk on the buyer?

A.Cost exclusive

B.Cost Plus Fixed Fee

C.Cost Plus Incentive Fee

D.Cost Plus Percentage of Cost

A

D.
The cost-plus-percentage-of-cost or CPPC contract transfers all costs to the buyer, and any increase in costs results in an increase in the fee to the seller. It also incentivizes the seller to be inefficient. This places a significant risk on the buyer and requires close cost management.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

You are managing an information technology project. A technical specialist on your team, after an informal meeting with a low-ranking customer representative working on the project, determines that a simple alteration would be a great addition to the project. The scope has already been approved by you and the sponsor, and a change control process is in place. The technical specialist installs the change with no negative effect on the project schedule and at no additional cost. What management action should be taken?

A.The technical specialist should be recognized for exceeding customer expectations without affecting project cost or schedule

B.The project manager should add a task to the project plan with no additional scheduled time and note that there was no increased budget

C.The technical specialist should be informed their actions were not authorized and was inconsistent with the change management plan

D.The project manager should create a change control form, and have the customer sign-off, since the change has already been made

A

C

The change control process should be followed by everyone on the project team. Failure to manage change effectively can result in significant scope creep and serious implications, additional risk, and liability.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A project team with a CPI of 0.78 is looking for options to reduce cost. Choose the best option from the following.

A.Reduce a test cycle, in the System Testing phase

B.Reduce scope by cutting down non- essential features

C.Add more resources to expedite the schedule

D.Revisit estimates and eliminate risks; re- estimate

A

D

Option (c) wouldn’t reduce cost. Option (a) and (b) would always have a negative effect as they compromise on quality or scope. Of all the available options, (d) is the one with the minimum negative effect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

For your project, you are working on a procurement-related area to outsource some work packages. While doing so, you decide to go for a fixed-price contract. What is the disadvantage of a fixed-price contract?

A.Less work for buyer to manage

B.Seller has a strong incentive to control costs

C.Buyer knows the total price at project starts

D.Final cost may be more than a cost reimbursable contract because contractors have to inflate the price to cover their risk

A

D

All options are advantages of a fixed price contract except D.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Which of the following options comes under the project management risk category?

A.Regulatory

B.Funding

C.Requirements

D.Estimating

A

Estimating comes under project management, Regulatory comes under external, funding comes under internal, and requirements comes under technical

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Which of the following statements about the relationship between the product life cycle and the project life cycle is correct?

A.Project lifecycle and product life cycle are same

B.Product life cycle is initiating, planning, executing, monitoring, control, and closing

C.Product life cycle consists of multiple project life cycle

D.Project life cycle consists of multiple product life cycle

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Which statement regarding the RACI model is true?

A.We can have multiple accountable people for a single activity.

B.We can only have one accountable person for a single activity.

C.We can only have one responsible person for a single activity.

D.We can have multiple people in charge, multiple people accountable, multiple consultants, and multiple people informed about a single activity.

A

B.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

The process of reviewing all change requests, approving changes, and managing changes to deliverables, organizational process assets, project documents, and project management plans and communicating their disposition is called ________.

A.Change control system

B.Perform integrated change control

C.Work authorization system

D.Risk management

A

Integrated change control through CCB takes care of all these activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

As a project manager, you have been asked by the customer to give an overview of the project status using milestone charts. Which of the following statement about milestone charts is NOT true?

A.Milestones usually have zero duration.

B.Milestone charts are similar to bar charts but only show major points or events.

C.Milestone charts can be used to capture the status of a project schedule.

D.Milestones are used to define the phases of a project.

A

D.

Milestone charts capture the major milestones in the project, which represent the beginning or completion of a deliverable, work package, phase, or project. A milestone is a zero-duration activity, and these charts are commonly used to present project status to senior management or a customer. Milestones do not define the phases of a project-this is defined by the project lifecycle.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Which of the following statement is true regarding the role of the risk owner and the risk action owner?

A.Both are the same.

B.The person responsible for ensuring that an appropriate response is selected and implemented is the risk owner, whereas the risk action owner is responsible for carrying out approved risk actions.

C.The person responsible for ensuring that an appropriate response is selected and implemented is the risk action owner, whereas the risk owner is responsible for carrying out approved risk actions.

D.A risk owner is called a risk actionee.

A

B.

The risk owner ensures the risk is implemented. The risk action owner executes or implements the decided action. A risk action owner is called a risk actionee.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which option is true regarding sigma values?

A.1 sigma is 68.2%, 2 sigma is 95.4%, 3 sigma is 99.7%, and 6 sigma is 99.99%.

B.2 sigma is 68.2%, 2 sigma is 90.4%, 3 sigma is 99.7%, and 6 sigma is 99.99%.

C.3 sigma is 68.2%, 2 sigma is 95.4%, 3 sigma is 97.7%, and 6 sigma is 99.99%.

D.4 sigma is 60.2%, 2 sigma is 95.4%, 3 sigma is 99.7%, and 6 sigma is 99.99%.

A

A.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

A project manager would like to inform everyone in a distributed team to update their time cards every Monday evening. What is the best way to communicate this expectation?

A.Formal written

B.Informal written

C.Formal verbal

D.Informal verbal

A

B.

Informal written communication: the project manager will likely send an email reminder to everybody, which represents informal written communication.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

You have just been informed that a preferred vendor will be utilized on an upcoming project. There had been concern over the type of contract to be used and the risk involved. Which one of the following contracts would be preferred by the vendor?

A.Time and materials contract

B.Fixed price incentive fee contract

C.Lump sum contract

D.Cost plus fixed fee contract

A

A
A time and material contract is a risk to the buyer because the seller may not do the work in a reasonable time or try to control the cost of material. It is normally used for small projects.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

There are many types of project documents created during the project life cycle. Many of them contain information concerning project-related risks. Which of the following would most likely NOT be one of them?

A.Resource Breakdown Structure

B.Source selection criteria

C.Project charter

D.Risk register

A

C.

The Resource Breakdown Structure displays the necessary activity resources by category and type. It does not display risk information. Source selection criteria can contain risks assigned to the seller. Project charter can contain high level risks, and Risk register is a primary risk document.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

While preparing the identify risks, you decide to review the risk plan one final time to see if it is well prepared. Which of the following would NOT be helpful if found in the risk plan while preparing to identify risks?

A.Risk urgency information

B,Revised stakeholder tolerances

C.Predetermined PIM

D.Risk definitions

A

A. Risk urgency

Risk urgency information would be updated to the risk register after qualitative risk analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Which of the following would be a true statement regarding the use of checklists for risk identification?

A.Previous experience will not contribute to the checklist development

B.An exhaustive checklist can be practical

C.Regular maintenance is a consideration

D.Check lists provide a more generalized list of risks

A

C

Regular maintenance is required for a checklist to be accurate and tailored to each project. The other choices are false statements.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

While working with the project team during risk identification, you instruct one of the team members to use force field analysis on the next set of risks. Which one of the following is the best description of force field analysis?

A.This tool analyzes the elements of a system that cause it to fail by themselves or in combination with other

B.This tool determines what a project areas might be most sensitive to a risk’s impact

C.This tool compares the variables for change and the variables against change

D.This tool helps determine if your process is in control

A

C

This is the best description of force field analysis. Option A is FMEA, Option B is sensitivity analysis, and Option D is a reference to a control chart.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

The project team is reviewing the risks in the risk register. They find a risk that may require more time to complete due to resource constraints. So, they calculate the time necessary to complete this scheduled activity and network path with reserve analysis. Which of the following is a likely outcome?

A.An assumption

B.A contingency budget

C.A project buffer

D.A negative schedule variance

A

C

A project buffer is used to protect a resource constraint critical chain within the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

The project team is reviewing sources of potential risks for a project in the planning phase. They are reviewing the cost and quality management plans to spot potential sources of risk. Which of the following might be a source of quality risk that is related to cost?

A.The cost of conformance

B.The cost of nonconformance

C.The cost of inspections

D.The cost of quality training

A

b

The cost of nonconformance is most closely associated with quality failures. It is the risk of additional time, money, and resources for failing to meet the quality standards. This is reflected in the quality plan during planning for a potential source of risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Your project team is currently performing a round of risk identification on a small project just before you begin execution. Which of the following is the best example of what will happen next?
A.PIM scores will be assigned, and risk responses will be developed

B.PIM scores will be assigned, and risk definitions will be determined

C.Risk impact values will be determined, and risk responses will be developed

D.Risk impact values will be determined, and risks will be controlled

A

A

After risk identification, each risk will be assessed in qualitative analysis and given a PIM score. With a small project, it is not required to conducted further analysis, and risk responses can be developed and assigned to each risk. Option B is incorrect as definitions should have been defined in the risk plan. Options C and D skipped qualitative analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

You have just finished updating the risk register with PIM scores. Which of the following statements is most TRUE at this point in your project?
A.The team performed a risk probability and impact assessment with the PMI to determine and identify the risk owner.

B.The team performed a risk probability and impact assessment with the PMI to determine the PMI scores

C.The team performed a risk probability and impact assessment along with risk categorization to determine the PMI scores

D.The team performed a risk probability and impact assessment along with a data quality assessment to determine the PMI scores

A

B

The probability and impact assessment attempt to determine the likelihood of a risk which will occur and its impact. The PMI is necessary to determine the PMI scores from this assessment.

32
Q

Which of the following is the best way to determine areas of the project with the highest concentrations of risk?
A.Risk categorization

B.Cause and effect diagrams

C.Pareto’s Law

D.Root cause analysis

A

A

Risk categorization is a tool that is used to determine where concentrations of risk might be in the project.

33
Q

You have identified the risk and carried out the risk analysis. What should be the next process from the risk management point of view?

A.Qualitative risk analysis

B.Control risk

C.Risk identification

D.Quantitative risk analysis

A

B

After a risk has been identified and a risk analysis has been carried out, control risk, which is monitoring and controlling process groups takes place.

34
Q

Sensitivity analysis is a technique for systematically changing parameters in a model to determine the effects of such changes and is useful for computer modelers for a range of purposes. Which of the following options will NOT be useful to meet the purpose of sensitivity analysis?

A.Increased understanding or quantification of the system

B.Estimating the average outcome

C.Model development

D.Decision-making or the development of recommendations for decision-makers

A

B

Average outcome is not a good technique. All remaining choices are good for sensitivity analysis.

35
Q

A project has a budget of $567,000 and is scheduled to last for three years. You want to examine the risk events to determine which of them might have the most impact on the project. Which modeling technique can help you accomplish this goal?

A.Expected monetary value

B.Sensitivity analysis

C.Quantitative risk analysis

D.Modeling and simulation

A

B

Sensitivity analysis determines the impact a risk might have on a project.

36
Q

One of the team members finds risk management quite difficult to manage. She asks you, a lead project manager, at what stage in the project will risk management become easier. Which of the following best answers that question?

A.Risk management only becomes easier with practice

B.Risk management only becomes easier when the project is in its closing stage

C.Risk management only becomes easier when the project moves into project execution

D.Risk management is an iterative process and never becomes easier

A

A

Practice makes a man perfect. The same principle applies to risk management.

37
Q

The risk monitoring and controlling process accomplishes four critical objectives for a project, in addition to monitoring and controlling project risks for their status and information. Which of the following is NOT a decision that the risk monitoring and controlling process makes?

A.Determining if the project assumptions are still valid

B.Determining if the risk management policies and procedures are being followed

C.Determining if the risk contingency reserves should be modified so that they are aligned with the current risk assessment

D.Determining if the project constraints are still valid

A

D

38
Q

Question: 13 You have identified risks for your project, qualified them and the risk response plan for these risks has been completed. Now you are going to update the risk register with these risks and their response plan. Which of the following statements is true about the level of detail you should put into the risk register?

(a) It should correspond with the priority ranking
(b) It should correspond with the risk response plan
(c) It should correspond with the risk impact
(d) It should be according to the risk management plan

A

A

39
Q

Question: 14 Your project is 70% complete and many of your identified risks did not occur, so much of your contingency reserve is left. A team member comes to you and informs you that an identified risks is about to occur which may affect your cost baseline, so you raise a change request to manage this risk. What is wrong here?

(a) Nothing is wrong; you can take preventive action through a change request.
(b) A risk is identified, and its contingency plan is ready so you should not take any action.
(c) You have enough contingency reserve so you should not take any action.
(d) It is your project so you can take any action you wish.

A

A

40
Q

Which procurement management process belongs to the execution process group?

(a) Control Procurement
(b) Execute Procurement
(c) Plan Procurement Management
(d) Conduct Procurement

A

d

41
Q

Which of the following is true about the decision tree analysis?

(a) It is an input to the Qualitative Risk Analysis process
(b) It is an Input to the Quantitative Risk Analysis process
(c) It is a tool & technique of the Perform Qualitative Risk Analysis process
(d) It is a tool & technique of the Perform Quantitative Risk Analysis process

A

D

42
Q

In the Perform Quantitative Risk Analysis process, which of the following tool do you not use?

(a) Monte Carlo Analysis
(b) Expected Monetary Value Analysis
(c) Decision Tree Analysis
(d) Earned Value Management

A

D

Earned value management is a tool for managing projects.

43
Q

In which process do you use root cause analysis?

(a) Identify Risks
(b) Plan Risk Management
(c) Perform Qualitative Risk Analysis
(d) Perform Quantitative Risk Analysis

A

A

44
Q

Question: 29 Your project is at the midway point and an important stakeholder comes to you and asks for some changes. He needs to add one extra big room to the building for himself and wants it to be different than other rooms. You agree to it and raise the change request to get it approved. What part of the change control system will review this request?

(a) Change control system
(b) Configuration management system
(c) Integrated change control system
(d) Control management system

A

B.

The C is the name of the process, but B is the name of the control system where the changes are approved or rejected

45
Q

Which of the following is an important aspect of risk management during project initiation?

A. the selection of the appropriate project life cycle
B. The selection of the overaal risk management approach
C. Creating the project business case.
D. Creating the porject risk management strategy

A

A

During project initiation, the selection of the appropriate project life cycle is one of the first decisions supported by risk management. Each of the known project life cycles has an impact on all areas of project management by helping to enhance and exploit opportunities or introducing a number of threats. The Standard for Risk Management in Portfolios, Programs and Projects, Page 62

46
Q

VUCA stands for:

A

A. Volatility, uncertainty, complexity, ambiguity.

47
Q

Your organization has a rule of accepting all risk costs for any new project till 50,000 $. Any project risk costs more than 50,000$, the project will be rejected. What does the 50,000$ represent?

A.Management Reserve
B. Cotigency Reserve.
C. Riks tolerance
D.Risk thershold

A

D.

Risk Threshold is the level of impact at which a stakeholder may have a specific interest. Below the risk threshold, the organization will accept the risk, and above the risk threshold, the organization will not tolerate the risk. The Standard for Risk Management in Portfolios, Programs and Projects, Page 10

48
Q

In which part of the project are opportunities greatest and require intense planning?

A. Initiating
B. Planning
C. Executing
D. Closing

A

A. Initiating

Risk and uncertainty are greatest at the start of the project and decrease over the life of the project . PMBOK 6th edition

49
Q

Which of the following evaluates risk across a related set of components?

A. Program Risk Management
B. Project Risk management
C. Portfolio Risk Management
D. Operation Risk management

A

A. Program Risk Management

Portfolio risk management tackles strategic, execution, and structural risks. Whereas program risk management evaluates risk across a related set of components, portfolio risk management is broad and considers risks that could impact unrelated components and operational activities within the portfolio. The Standard for Risk Management in Portfolios, Programs and Projects, Page 24

50
Q

During project initiating:

A. The level of project risk exposure is at its maximum but information on the project risk is at minimum
B. The level of risk exposure is at minimum but information on th eproject risk is at maximum
C.There is no relation between risk expousre and avaliability of risk related information
D.The level of risk exposure ismoderate but information on the project risk is moderate

A

A

.In the early stages of a project, the level of risk exposure is at its maximum but information on the project risks is at a minimum. PMBOK Guide 6th edition, Page 549

51
Q

Which of the following tackles strategic risks?

A. program risk management
B. Porject risk management
C. Portfolio risk management
D. Operation risk management

A

C.

Portfolio risk management tackles strategic, execution, and structural risks. Whereas program risk management evaluates risk across a related set of components, portfolio risk management is broad and considers risks that could impact unrelated components and operational activities within the portfolio. The Standard for Risk Management in Portfolios, Programs and Projects, Page 24

52
Q

You are planning to bid on a contract. You think that the value of this contract will be approximately 200,000 USD. Your organization has told you that, because of budgetary constraints, they cannot allow you to go beyond 220,000 USD. What does the extra 20,000 USD represent?

A. Risk appetite
B. Cotingency reserve
C. Risk tolerance
D. Risk threshold

A

D.

Risk Threshold is the level of impact at which a stakeholder may have a specific interest. Below the risk threshold, the organization will accept the risk, and above the risk threshold, the organization will not tolerate the risk. The Standard for Risk Management in Portfolios, Programs and Projects, Page 10

53
Q

You have been assigned as a project manager for a new industrial project which is a part of a large program. A project charter has already been issued. You have been informed by the program manager that this program entails a high level of uncertainty. As a project manager, all of the following information in the project charter you will need in managing project risks, except:

A. What is the detailed product and project scope?
B. Are the objectives in the charter achivable?
C. What is the authority level of the project manager?
D. What is not included in the charter?

A

A.

Detailed product and project scope are not included in the project charter. PMBOK 6th edition, Page 81 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 103

54
Q

What is meant by cost risk?

A. The cost of all identified risk if they happend.
B. There is a risk that project sot could go higher than planned.
C. There are risk that will cost the project money.
D. The cosst of contingency reserve assigned for residual risks.

A

B.

The first thing to think of is :cost risks are risks or costs? Of course they are risks, so all answers saying it is cost should be eliminated. It is true that some risks cost the project money but this is not the right definition of cost risks. The right definition is that there is a risk that project costs could go higher than planned. PMBOK 6th edition, Page 433

55
Q

During project initiating, why do you need to identify high level risks, assumptions and constraints based on the current environment, organizational factors and historical data?

A. To determine risk that may affect the project and coumenting their characteristic
B. To increase project opportunities and decrease threats
C. To be able to tailor the porject managemnt plan to the size of the project
D. To propose an implementation strategy

A

D.

The project manager should identify high level risks, assumptions and constraints based on the current environment, organizational factors, historical data and expert judgment in order to propose an implementation strategy. Other choices don’t occur during project initiating. The Standard for Risk Management in Portfolios, Programs and Projects, Page 62

56
Q

All of the following statements are true about project risks except:

A. They can have a positive or negative effect on project objectives
B. They are uncertain events.
C. Positive risk which occur are called benefits.
D. Unknow risk are threat to the project objective

A

D.
Unknown risks maybe threats or opportunities. The Standard for Risk Management in Portfolios, Programs and Projects, Page 8

57
Q

Which of the following is a tactical risk?

A. A risk identified either by management process at the portfolio level or escalated from the portfolio components.
B. A risk identified directly at the portfolio level and triggered by portofolio actities.
C. A risk resulting from the strategic and organizational environment of the program.
D. A risk that is directly triggered by program activities.

A

A.

Tactical risks are risks identified either by management processes at the portfolio level or escalated from the portfolio’s components. The Standard for Risk Management in Portfolios, Programs and Projects, Page 42

58
Q

The lowest level of the risk breakdown structure can be used as a/an:

A. Prioritized list of project risk
B. individual project risk
C. Checklist
D. Risk register

A

C

The lowest level of a risk breakdown structure can also be used as a risk checklist.. The Standard for Risk Management in Portfolios, Programs and Projects, Page 131

59
Q

Why would the project manager need to know the assumptions made during the identify risks process?

A. To test assumptions stability.
B. To quantify these assumptions.
C.To remove risk which include assumptions
D. To evaluate the Identify Risks process.

A

A

The project manager should analyze the stability of assumptions to discover how realistic or valid they are and evaluate the impacts if these assumptions are false. The Standard for Risk Management in Portfolios, Programs and Projects, Page 130 and 151

60
Q

Diana is a project manager for a new IT project. She is working with project key stakeholders to analyze and prioritize requirements. She pays more attention to customer satisfaction because one of the project requirements is to achieve a high-level of customer satisfaction for the product of the project. What is the risk here in project requirements?

A. . Achieving high-level customer satisfaction is a is an assumption and it should be documented in the project assumptions log.
B.Achieving high-level customer satisfaction is a subjective requirement and entails a high level of risk
C. Achieving high-level customer satisfaction is a constraints and it must be balanced with other constraints like time,scope and cost
D. . Achieving high-level customer satisfaction is a top risk and it must be identified, analyzed and appropriate response should be planned for it.

A

A

B

Requirements need to be measurable and customer satisfaction is not measurable. PMBOK 6th edition, Page 147

61
Q

Mark is a project manager for a telecommunications project in his organization. Tom is his sponsor and he is working with David, the risk manager in the organization to determine the effectiveness of the risk responses. Tom and David are concerned that some of the risks assigned to Frederick, a project team member to implement the planned risk responses may not be addresses to the depth they would like. In this scenario, who is responsible for ensuring that this process is performed at an appropriate frequency?

A.Mark
B.David
C.Tom
D. Frederick

A

A
The project manager is responsible for ensuring that risk audits are performed at an appropriate frequency, as defined in the project’s risk management plan. PMBOK 6th edition, Page 456 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 39

62
Q

The project manager is responsible for ensuring that risk audits are performed at an appropriate frequency, as defined in the project’s risk management plan. PMBOK 6th edition, Page 456 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 39

A. Project managemet plan updates
B.Risk register pdates
C.Project document updates
D. Risk response plan updates

A

C
The outputs of the Perform Qualitative Risk Analysis process includes more than just risk register updates, because it may include updates to the assumptions log or issue log. PMBOK 6th edition, Page 427

63
Q

Which of the following is the best strategy to deal with unknown-unknowns?

A. Identify in advance and proactively manage.
B. Identify as part of the requirement and manage as part of the scope.
C.Accommodate them through management reserve.
D. Address trough progressive risk elaboration integrated with execution of the endeavor

A

C

Unknown-unknown risks may be emergent risks that are essentially unknowable within the context of portfolio, program, and project management. Management reserves are evaluated by the top management to accommodate for those unforeseen risks (unknown-unknowns). PMBOK 6th edition, Page 202 and 439 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 161

64
Q

Jim is managing a large industrial project. His project is halfway done, when he held a meeting with the project team and other stakeholders to identify new risks and reevaluate the current risks. This practice is known as:

A. Risk Audit
B. Riskreassessment
C. Risk identification
D. Developing risk responses

A

B

This means you are during the Monitor Risks process that often results in identification of new risks, reassessment of current risks, and the closing of risks that are outdated. PMBOK 6th edition, Page 457 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 39

65
Q

Joseph has managed many small IT projects before, and now he is managing his first large IT project. The project is not going well and it seems that the project will not achieve its objectives. So, he is seeking with the project key stakeholders about which objectives have higher priority in case they need to make trade-off between project objectives. Which tool can he use in this situation?

A. Probability and impacts matrix
B. Monte Carlo
C. Latin Hypercube
D. Analytical Hierarchy Process (AHP)

A

D.
Analytical Hierarchy Process (AHP) indicates the relative weighting of the project’s objectives in terms of their priority to the stakeholders or management. The results are weights (summing to 100%) that reflects the relative priority for each objective. This prioritization can be important in determining how trade-offs affect the project objectives. The Standard for Risk Management in Portfolios, Programs and Projects, Page 136

66
Q

What the tool used to prioritize the most significant item among many:

A. Pareto Technique.
B. Monte Carlo
C. Histogram
B. Run CHart

A

A.

67
Q

What of the following statement is FALSE regarding Sensitivity analysis?

A. Prioritizes risk based on their potential impact on the project
B.Tornado diagram is a graphical representation of Sensitivity analysis.
C. Are used to find correlation
D. can be done for different parameters like cost and schedule

A

C.

The C is a scatter diagram

68
Q

What of the following statements is FALSE about pareto chart?

A. Is used to identify areas to focus on first in process improvement.
B. Is used to find correlation between variables as cost and schedule
C. Is used to find root causes
D. Pareto charts show the ordered frequency counts of values for the different levels of a categorical or nominal variable.

A

B.

Sensitivity analysis is to find correlation.

69
Q

Which of the following is a tool used for qualitative analysis?

A. Monte Carlo
B. Pareto Chart
C. Sensitivity Analysis
D. Checklist

A

B.

Checklist are used to identify risk, not qualify them.

70
Q

Which of the following contract needs more audit?

A. Cost reimbursable
B. Cost fix fee
C. Cost reimbursable + fee
D. Time and material

A

C

71
Q

Robert is attending a risk management training session when the trainer displayed a template for a risk identification tool he has never seen before. This template is used in change management context and can be adapted for risk identification. It is categorized with two variables in contrast with one another. One is for change, and the other is against. Which risk tool does the trainer display?

A. Latin hypercube
C. Force field analysis
D. Analytical Hierarchy Process (AHP)
E. Influence diagram

A

B

Force field analysis compares the forces for change with the forces against change. The Standard for Risk Management in Portfolios, Programs and Projects, Page 144

72
Q

You are managing a mechanical project. The sponsor is worried about the status of the project. You provided him with the earned value calculations AC = $24,100, ETC = $44,600, VAC = -$1,600, BAC =$89,000, and EAC = $91,100. Your sponsor asks you to forecast how much money you expect to spend on the remainder of the project. Which is the best estimate to use for this forecast?

A=44.600
B=86,400
C. 89,000
D.91,100

A

A

Asking of the Estimate to completion.

73
Q

The project manager is holding a risk reassessment meeting with the project team and the project sponsor, the sponsor is looking at the latest list of top risks in the project report. A new risk has been identified and assessed. That risk ranking was lower than all of the previously identified risks. Three fallback plans have been adjusted based on the severity of previous risk impacts. Which of the following has the project manager forgotten to do?

A- Look at the impact of the new risk to the project as a whole
B- Provide the sponsor with the full list of non-critical risk.
C- Look for contingency risks from the fallback plan
D- Perform quantitative Risk Analysis for the new risk

A

A
It is not the responsibility of the project sponsor to review a full list of non-critical risks but he may review residual risks. There is nothing called contingency risks. Quantitative risk analysis is not performed to risks which rank lower than all of the previously identified risks. Quantitative risk analysis is performed for top risks only. The best answer here is to look at the impact of the new risk to the project as a whole as a part of the Identify Risks process. PMBOK 6th edition, Page 411 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 31

74
Q

The project sponsor has asked you to perform a risk audit and report back on the results. A project team member asked you what a risk audit is. What would you tell the team member?

A-A risk audit is the identification of new risk, reassessment of current risk, and the closing of risk that are outdated.
B- A risk audit examines and documents the effectiveness of risk responses in dealing with identified risk and their root causes, as well, as the effectiveness of the risk management process.
C-A risk audit is a review of the probability and impact of the risks, which are still present in the project but which have not yet occurred.
D-A risk audit is a review of the probability and impact for the risks, which have occurred in the project to determine if they were correctly evaluated.

A

B

Risk audits examine and document the effectiveness of risk responses in dealing with identified risks and their root causes, as well as the effectiveness of the risk management process. This is the correct definition of a risk audit. PMBOK 6th edition, Page 456 and The Standard for Risk Management in Portfolios, Programs and Projects, Page 39

75
Q

You are a project manager for a construction project. You are in planning process group and estimating with team members the costs needed to perform the project. The cost of the material pessimistically $120,000, most likely $110,000, and optimistically $100,000. The cost of labor is pessimistically $100,000, most likely $90,000, and optimistically $85,000. The cost of equipment is pessimistically $60,000, optimistically $40,000 and most likely $50,000. The cost for management fees is pessimistically $50,000, most likely $40,000, and optimistically $30,000. What is the probability of the project coming in under $280,000?

A-Exact 50%
B-Less than 50%
C- Over 50%
D- There is not enough inforation

A

B

“Average Expected Cost = (P+4M+O)/6. Average cost of material = 110,000, labor = 90,833, Equipments = 50,000, Management fees = 40,000. Average Total Cost = 110000+ 90833+50000+40000 = 290833. Average Total Cost = 110000+ 90833+50000+40000 = 290,833. Mean is at 290833 which means that the probability of total cost to be > 290833 = 50% and the probability of total cost to be < 290833 = 50%. So the probability of total cost to be < 280000$ is less than 50%. PMBOK 6th edition, Page 245”

76
Q

A go/no go decision can be taken during which risk management processes?

A. Plan risk management and plan risk responses
B.Perform Qualitative Risk Analysis and Plan Risk Responses
C.Identify Risks and Perform Qualitative Risk Analysis
D. Perform Quantitative Risk Analysis and Plan Risk Responses.

A

B

77
Q

Component risks at the portfolio level are:

A. Risk that the project/program/operational manager escalates to the portfolio level for information or action
B. Risk that the component manager escalates to portfolio level for information or action
C. Risk that consider the interdependecies between portfolio components
D. Risk that arises as a direct result of implementing aa risk response

A

A

Component risks at the portfolio level are risks that the component manager escalates to the portfolio level for information or action The Standard for Risk Management in Portfolios, Programs and Projects, Page 14