Exam - Genta's Questions Flashcards
According to Document Six, what is the standard protocol for issuing notices; for example, a request by the architect to the contractor to fix any deficiencies or to issue a notice of payment (an invoice)?
Document Six, Agreement, A17
Notices in writing between the parties are to be delivered by hand or by registered post; or if sent by regular post, to have been delivered within five working days of the date of mailing. Notices sent electronically, by email or facsimile are not considered to be reliable for the purpose of official notice.
According to the Schedule of Client Responsibilities for Document Six, how is the client to communicate information or instructions to the contractor during the construction phase?
Document Six, Schedule of Client Responsibilities, Phase 5.2
The client is to issue all instructions to the contractor via the architect.
After bidding has taken place and the successful bidder has been awarded the contract, who is responsible for preparing the construction contract? What contract is recommended?
CHOP 2.3.9, Contract Award - Preparation of the Construction Contract
The architect usually prepares the construction contract. It is recommended that the standard Canadian Construction Documents Committee (CCDC) forms of construction contract be used. These documents have widespread acceptance in the construction industry, and have been tested and endorsed by all CCDC constituent members.
Are architects required to have a written agreement with their clients before they begin providing services?
It is strongly recommended but not mandated in (most)? provinces. It is, however, a requirement in BC.
Arrange the four soil types from high to low bearing strength - silt, sand, clay, gravel
Gravel, Sand, Silt, Clay
As a rule of thumb, what is the cost to an architect for coordinating engineering consultants?
CHOP 2.1.10 - The Architect’s Fee
25% - 35% of the engineering consultant’s fee.
In provincial or territorial fee guidelines, percentage fees usually include the fees of structural, mechanical, and electrical engineers - the three common engineering disciplines. For example, the AIBC Tarrif of Fees uses percentages that factor in the three basic engineering fees plus the architect’s fee for coordinating their work.
Assuming the construction contract between client and contractor include provisions for dispute resolution by arbitration, what is the client obligated to do under one of the general conditions of Document Six if a dispute arises?
Document Six, GC 1.3.1
The client must notify the architect in writing 10 working days in advance of any arbitration and of any matters in dispute and the extent to which they affect the architect and, if the client has a claim against the architect that arises from the dispute, bring that claim against the architect at the time of the arbitration.
At what angle is a roof considered a wall?
NBC 3.2.1.3.(1)
Any part of a roof that is pitched at an angle of 60 degrees or more to the horizontal and is adjacent to a space intended for occupancy within a building shall be considered as part of an exterior wall of a building.
Besides hiring a contractor to perform the work, what is the purpose of the bidding process?
Based on the “Lowest Bid Method”, the bidding process replaces negotiation between owner and contractor (CCDC 23)
Can an architect trump the Authority Having Jurisdiction when interpreting the Building Code?
CHOP 1.2.4, Relationships with Authorities
No, but if there is a disagreement they may submit an alternate solution for review by the AHJ. Regardless, the architect should always strive to develop professional relationships with building officials and deal with any conflicts in code interpretation tactfully.
Define ‘Construction Cost’ as defined in the Definitions of Document Six.
CHOP 2.1.10 - Definitions
Construction Cost is the contract price(s) of all Project elements designed or specified by, or on behalf of, or as a result of, the coordination by the Architect, including cash allowances, building permit fees, changes, construction management fees or other fees for the coordination and procurement of construction services, and all applicable taxes, including the full amount of value-added taxes, whether recoverable or not.
Where there is no contract price for all or part of the Project, the Construction Cost shall be the estimate of probable cost of construction as determined by the Architect, or as agreed by the Architect if a Cost Consultant is engaged, at market rates at the anticipated time of construction. Construction Cost excludes the following:
* the compensation of the Architect and the Consultants,
* other professional fees which are the responsibility of the Client, * the land cost, and land development charges.
In the event that the Client furnishes labour or material below market cost, or recycled materials are used, the Construction Cost for purposes of establishing the Architect’s and Consultants’ fees includes the cost of all materials and labour necessary to complete the Work as if all materials had been new and as if all labour had been paid for at market prices at the time of construction or, in the event that the construction does not proceed, at existing market prices at the anticipated time of construction.
Define access to exit
NBC Div A, Part 1, 1.4.1.2
Access to exit means that part of a means of egress within a floor area that provides access to an exit serving the floor area.
Define exit
NBC Div A, Part 1, 1.4.1.2
Exit means that part of a means of egress, including doorways, that leads from the floor area it serves to a separate building, an open public thoroughfare, or an exterior open space protected from fire exposure from the building and having access to an open public thoroughfare.
Define means of egress
NBC Div A, Part 1, 1.4.1.2.
Means of egress means a continuous path of travel provided for the escape of persons from any point in a building or contained open space to a separate building, an open public thoroughfare, or an exterior open space protected from fire exposure from the building and having access to an open public thoroughfare. Means of egress includes exits and access to exits.
Define the five main components of The National Council of Architectural Registration Boards’ (NCARB’s), Code of Ethics and Professional Conduct
CHOP 1.1.3, Code of Ethics and Professional Conduct NCARB’s model code which had also been adapted for use by the AIBC contains the following:
* competence
* conflict of interest
* full disclosure
* compliance with laws * professional conduct
Define the term holdback and how it relates to lien legislation. How is the holdback amount determined? What is the minimum size of project that a holdback can be used?
BC Builders Lien Act
A holdback is a percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period of time in a separate savings account. The percentage and period of time are based on the provincial lien legislation (CHOP 2.3.10, Definitions)
The holdback amount is determined by the provincial or territorial lien legislation, typically 10% of the greater of the value of the work or material provided, or 10% of any payment made on account (BC Lien Act, Holdback, 4.1)
The minimum size is also determined by the provincial or territorial lien legislation. In BC it is $100,000 (BC Lien Act, Holdback Account, 5.8b)
Describe how the “real world” practice of architecture can differ from architecture as a profession and the regulations governing it.
CHOP 1.1.2, Architecture as a Profession
The practice of architecture is usually broader than the regulation governing the profession (i.e. in practice it can include urban design, interior design, landscape design, planning, etc.) The jurisdiction or professional association of a province or territory regulates only a certain portion of architecture which it deems to be the “profession of architecture” under its legislative authority. This typically includes life safety and building envelope among others.
Describe the difference between Intent Statements and Application Statements. Where can these be found?
NBC Volume 1, Preface, ix
Intent Statements explain, in plain language, the basic thinking behind each Code provision contained in Division B. They explain how requirement help to achieve their attributed objectives and functional statements. Intent Statements can be found throughout all the Parts of Division B.
Application Statements summarize what each Code provision does and does not apply to. They provide greater detail than the application information found in the body of the Code. The application statements serve explanatory purposes only and do not form an integral part of the Code provisions: as such, they are similar in function to appendix notes. Application Statements can be found in Part 1 of each Division (A,B, & C).
Describe the firestopping meaures required for a wall with a fire resistance rating of 1h that has the following penetrations:
Air duct
Sprinkler pipe Combustible piping Door
Expansion joint
NBC 3.1.9.1.
Air duct - fire stop flap (fire damper) with 45 min rating
Sprinkler pipe - cover with metal escutcheon plate in accordance with NFPA 13
Combustible piping - fire stop not less than rating of assembly (1h) Door - fire stop with 45 min rating
Expansion joint - fire stop not less than rating of assembly (1h)
Describe the fundamental difference between the National Building Code and the Fire Code.
NBC Volume 1 Preface, p.vi
The NBC generally applies at the time of construction and reconstruction while the NFC applies to the operation and maintenance of the fire-related features of building in use.
Describe the organizational hierarchy of the National Building Code (eg. Divisions, Parts, Articles, etc.)
NBC, Preface xi
Numbering System: B Divisions
3 Part
3.5. Section
3.5.2. Subsection
3.5.2.1. Article
3.5.2.1.(2) Sentence 3.5.2.1.(2)(a) Clause 3.5.2.1.(2)(a)(i) Subclause
Has three Divisions - A, B, and C
Division A: Compliance, Objective and Functional Statements Part 1 - General, definitions and references
Part 2 - Objectives
Part 3 - Functional Statements
Division B: Acceptable Solutions
Part 1 - General
Part 2 - Reserved
Part 3 to 9 - Accepted measures (prescriptive requirements)
Describe the process to issuing a Change Order.
CHOP 2.3.10, p.6
The change order process is usually started by the issuance of a form known as a Proposed Change (or “Contemplated Change”). The purpose of this form is to alert the contractor to the proposed change and to provide the contractor an opportunity to submit a quotation for additional cost (or credit) or a change in time (if any) for the proposed change. The Change Order is the final form which indicates the agreement between the client/owner and the contractor on specific additions, deletions or revisions to the contract documents.
Describe the purpose of drawings, schedules and specifications and how they differ.
CHOP 2.3.8, Specifications and Drawings
Drawings
* Illustrate extent, location, and quantity;
* Are graphic or pictorial descriptions;
* Identify a material or product only by a generic name.
Schedules
* State the configuration and dimension of each assembly, component or accessory; * Identification of pre-fabricated or pre-assembled components or equipment.
Specifications
* Reduce the need for notes on the drawings;
* Are the only location where brand names of products should appear;
* Describe workmanship and installation;
* Complement and permit simplification of the drawings;
* Describe requirements for quality and workmanship which the drawings may not be able to address.
Describe the relationship between Objectives and Functional Statements in the National Building Code.
NBC Volume 1, Preface, vii and Division A, 2.2. & 3.2.
Objectives state the goals that the code is trying to achieve. Functional Statements support and further articulate the objectives.