Exam - Genta's Questions Flashcards

1
Q

According to Document Six, what is the standard protocol for issuing notices; for example, a request by the architect to the contractor to fix any deficiencies or to issue a notice of payment (an invoice)?

A

Document Six, Agreement, A17
Notices in writing between the parties are to be delivered by hand or by registered post; or if sent by regular post, to have been delivered within five working days of the date of mailing. Notices sent electronically, by email or facsimile are not considered to be reliable for the purpose of official notice.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

According to the Schedule of Client Responsibilities for Document Six, how is the client to communicate information or instructions to the contractor during the construction phase?

A

Document Six, Schedule of Client Responsibilities, Phase 5.2
The client is to issue all instructions to the contractor via the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

After bidding has taken place and the successful bidder has been awarded the contract, who is responsible for preparing the construction contract? What contract is recommended?

A

CHOP 2.3.9, Contract Award - Preparation of the Construction Contract
The architect usually prepares the construction contract. It is recommended that the standard Canadian Construction Documents Committee (CCDC) forms of construction contract be used. These documents have widespread acceptance in the construction industry, and have been tested and endorsed by all CCDC constituent members.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Are architects required to have a written agreement with their clients before they begin providing services?

A

It is strongly recommended but not mandated in (most)? provinces. It is, however, a requirement in BC.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Arrange the four soil types from high to low bearing strength - silt, sand, clay, gravel

A

Gravel, Sand, Silt, Clay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

As a rule of thumb, what is the cost to an architect for coordinating engineering consultants?

A

CHOP 2.1.10 - The Architect’s Fee
25% - 35% of the engineering consultant’s fee.
In provincial or territorial fee guidelines, percentage fees usually include the fees of structural, mechanical, and electrical engineers - the three common engineering disciplines. For example, the AIBC Tarrif of Fees uses percentages that factor in the three basic engineering fees plus the architect’s fee for coordinating their work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Assuming the construction contract between client and contractor include provisions for dispute resolution by arbitration, what is the client obligated to do under one of the general conditions of Document Six if a dispute arises?

A

Document Six, GC 1.3.1
The client must notify the architect in writing 10 working days in advance of any arbitration and of any matters in dispute and the extent to which they affect the architect and, if the client has a claim against the architect that arises from the dispute, bring that claim against the architect at the time of the arbitration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

At what angle is a roof considered a wall?

A

NBC 3.2.1.3.(1)
Any part of a roof that is pitched at an angle of 60 degrees or more to the horizontal and is adjacent to a space intended for occupancy within a building shall be considered as part of an exterior wall of a building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Besides hiring a contractor to perform the work, what is the purpose of the bidding process?

A

Based on the “Lowest Bid Method”, the bidding process replaces negotiation between owner and contractor (CCDC 23)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Can an architect trump the Authority Having Jurisdiction when interpreting the Building Code?

A

CHOP 1.2.4, Relationships with Authorities
No, but if there is a disagreement they may submit an alternate solution for review by the AHJ. Regardless, the architect should always strive to develop professional relationships with building officials and deal with any conflicts in code interpretation tactfully.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Define ‘Construction Cost’ as defined in the Definitions of Document Six.

A

CHOP 2.1.10 - Definitions
Construction Cost is the contract price(s) of all Project elements designed or specified by, or on behalf of, or as a result of, the coordination by the Architect, including cash allowances, building permit fees, changes, construction management fees or other fees for the coordination and procurement of construction services, and all applicable taxes, including the full amount of value-added taxes, whether recoverable or not.
Where there is no contract price for all or part of the Project, the Construction Cost shall be the estimate of probable cost of construction as determined by the Architect, or as agreed by the Architect if a Cost Consultant is engaged, at market rates at the anticipated time of construction. Construction Cost excludes the following:
* the compensation of the Architect and the Consultants,
* other professional fees which are the responsibility of the Client, * the land cost, and land development charges.
In the event that the Client furnishes labour or material below market cost, or recycled materials are used, the Construction Cost for purposes of establishing the Architect’s and Consultants’ fees includes the cost of all materials and labour necessary to complete the Work as if all materials had been new and as if all labour had been paid for at market prices at the time of construction or, in the event that the construction does not proceed, at existing market prices at the anticipated time of construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Define access to exit

A

NBC Div A, Part 1, 1.4.1.2
Access to exit means that part of a means of egress within a floor area that provides access to an exit serving the floor area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Define exit

A

NBC Div A, Part 1, 1.4.1.2
Exit means that part of a means of egress, including doorways, that leads from the floor area it serves to a separate building, an open public thoroughfare, or an exterior open space protected from fire exposure from the building and having access to an open public thoroughfare.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Define means of egress

A

NBC Div A, Part 1, 1.4.1.2.
Means of egress means a continuous path of travel provided for the escape of persons from any point in a building or contained open space to a separate building, an open public thoroughfare, or an exterior open space protected from fire exposure from the building and having access to an open public thoroughfare. Means of egress includes exits and access to exits.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Define the five main components of The National Council of Architectural Registration Boards’ (NCARB’s), Code of Ethics and Professional Conduct

A

CHOP 1.1.3, Code of Ethics and Professional Conduct NCARB’s model code which had also been adapted for use by the AIBC contains the following:
* competence
* conflict of interest
* full disclosure
* compliance with laws * professional conduct

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Define the term holdback and how it relates to lien legislation. How is the holdback amount determined? What is the minimum size of project that a holdback can be used?

A

BC Builders Lien Act
A holdback is a percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period of time in a separate savings account. The percentage and period of time are based on the provincial lien legislation (CHOP 2.3.10, Definitions)
The holdback amount is determined by the provincial or territorial lien legislation, typically 10% of the greater of the value of the work or material provided, or 10% of any payment made on account (BC Lien Act, Holdback, 4.1)
The minimum size is also determined by the provincial or territorial lien legislation. In BC it is $100,000 (BC Lien Act, Holdback Account, 5.8b)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Describe how the “real world” practice of architecture can differ from architecture as a profession and the regulations governing it.

A

CHOP 1.1.2, Architecture as a Profession
The practice of architecture is usually broader than the regulation governing the profession (i.e. in practice it can include urban design, interior design, landscape design, planning, etc.) The jurisdiction or professional association of a province or territory regulates only a certain portion of architecture which it deems to be the “profession of architecture” under its legislative authority. This typically includes life safety and building envelope among others.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Describe the difference between Intent Statements and Application Statements. Where can these be found?

A

NBC Volume 1, Preface, ix
Intent Statements explain, in plain language, the basic thinking behind each Code provision contained in Division B. They explain how requirement help to achieve their attributed objectives and functional statements. Intent Statements can be found throughout all the Parts of Division B.
Application Statements summarize what each Code provision does and does not apply to. They provide greater detail than the application information found in the body of the Code. The application statements serve explanatory purposes only and do not form an integral part of the Code provisions: as such, they are similar in function to appendix notes. Application Statements can be found in Part 1 of each Division (A,B, & C).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Describe the firestopping meaures required for a wall with a fire resistance rating of 1h that has the following penetrations:
Air duct
Sprinkler pipe Combustible piping Door
Expansion joint

A

NBC 3.1.9.1.
Air duct - fire stop flap (fire damper) with 45 min rating
Sprinkler pipe - cover with metal escutcheon plate in accordance with NFPA 13
Combustible piping - fire stop not less than rating of assembly (1h) Door - fire stop with 45 min rating
Expansion joint - fire stop not less than rating of assembly (1h)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Describe the fundamental difference between the National Building Code and the Fire Code.

A

NBC Volume 1 Preface, p.vi
The NBC generally applies at the time of construction and reconstruction while the NFC applies to the operation and maintenance of the fire-related features of building in use.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Describe the organizational hierarchy of the National Building Code (eg. Divisions, Parts, Articles, etc.)

A

NBC, Preface xi
Numbering System: B Divisions
3 Part
3.5. Section
3.5.2. Subsection
3.5.2.1. Article
3.5.2.1.(2) Sentence 3.5.2.1.(2)(a) Clause 3.5.2.1.(2)(a)(i) Subclause
Has three Divisions - A, B, and C
Division A: Compliance, Objective and Functional Statements Part 1 - General, definitions and references
Part 2 - Objectives
Part 3 - Functional Statements
Division B: Acceptable Solutions
Part 1 - General
Part 2 - Reserved
Part 3 to 9 - Accepted measures (prescriptive requirements)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Describe the process to issuing a Change Order.

A

CHOP 2.3.10, p.6
The change order process is usually started by the issuance of a form known as a Proposed Change (or “Contemplated Change”). The purpose of this form is to alert the contractor to the proposed change and to provide the contractor an opportunity to submit a quotation for additional cost (or credit) or a change in time (if any) for the proposed change. The Change Order is the final form which indicates the agreement between the client/owner and the contractor on specific additions, deletions or revisions to the contract documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Describe the purpose of drawings, schedules and specifications and how they differ.

A

CHOP 2.3.8, Specifications and Drawings
Drawings
* Illustrate extent, location, and quantity;
* Are graphic or pictorial descriptions;
* Identify a material or product only by a generic name.
Schedules
* State the configuration and dimension of each assembly, component or accessory; * Identification of pre-fabricated or pre-assembled components or equipment.
Specifications
* Reduce the need for notes on the drawings;
* Are the only location where brand names of products should appear;
* Describe workmanship and installation;
* Complement and permit simplification of the drawings;
* Describe requirements for quality and workmanship which the drawings may not be able to address.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Describe the relationship between Objectives and Functional Statements in the National Building Code.

A

NBC Volume 1, Preface, vii and Division A, 2.2. & 3.2.
Objectives state the goals that the code is trying to achieve. Functional Statements support and further articulate the objectives.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Describe the three general divisions of bylaws or regulations mandated by provincial or territorial architectural associations.

A

CHOP 1.1.3, Regulations
Ethical Regulations or Codes of Ethics - assist in maintaining the public trust in the integrity of the profession.
Regulations regarding Competency - ensure the proper provision of architectural services to the public.
Administrative Rules and Regulations - assist in the efficient operation of the provincial or territorial association.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Describe the three methods for architectural competitions and identify which one is not endorsed by the RAIC or provincial associations of architects?

A

RAIC Architectural Competitions, Competition Methods
The three methods are open, limited, and invited. Invited competitions are not endorsed.
Open - international competition; falls under the rules and regulations of the International Union of Architects (UIA); open to any architect recognized by the UIA; can be one or two stages. Two Stage Process:
1. Architects submit limited designs such as conceptual designs. Sponsor chooses architects who can compete in stage 2.
2. Competition includes more developed designs such as schematic design.
Limited - restricts the number of licensed architects who can compete by a geographic area or location (eg. BC architects only, Canadian architects only, etc.)
Invited - architect eligibility is on an invitation-only basis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
27
Q

Do shop drawings supersede the contract documents?

A

CHOP 2.3.10, p. 5
Shop drawings do not supersede the contract documents but supplement them to assist in the construction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
28
Q

Explain ‘progressive release of holdback.’

A

BC Builders Lien Act & Builders Lien Guide
Progressive release of holdback is possible if there is a multiple holdback system in place throughout the construction chain. This system allows for all persons who make payments under a contract or subcontract in a construction chain to retain a 10% holdback. Some former Lien Acts only required a single holdback between the owner and its general contractor. A progressive release of holdback allows for the release of holdbacks retained to sub-contractors when their contracts are completed before the construction project itself is complete. This benefits subcontractors who are involved earlier on in the project, as well as benefiting the owner, as it will reduce the body of potential lien claimants as the construction project progresses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
29
Q

Explain the difference between a fire block and a fire stop?

A

NBC Division A, 1.2.1.2.
Fire block means a material, component or system that restricts the spread of fire within a concealed space or from a concealed space to an adjacent space.
Fire stop means a system consisting of a material, component and means of support used to fill gaps between fire separations or between fire separations and other assemblies, or used around items that wholly or partially penetrate a fire separation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
30
Q

Explain the difference between a Fire Separation and a Firewall

A

NBC Division A, 1.4.1.2.
Fire Separation - a construction assembly that acts as a barrier against the spread of fire; it may or may not have a required fire resistance rating.
Firewall - a type of fire separation of noncombustible construction that subdivides a building or separates adjoining buildings to resist the spread of fire and that has a fire-resistance rating as prescribed in this Code and has structural stability to remain intact under fire conditions for the required fire-rated time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
31
Q

Explain the difference between a Life Cycle Assessment (LCA) and Life Cycle Costing (LCC).

A

CHOP 2.3.4, p.10-11
LCA is a methodology for assessing the environmental performance of a product over its full life cycle, often referred to as cradle-to-grave or cradle-to-cradle analysis.
LCC focuses on the dollar costs of construction, operating and maintaining a structure over its life cycle, whereas LCA focuses on environmental performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
32
Q

Explain the difference between commissioning and take-over.

A

CHOP 2.3.12, Introduction - Commissioning
Commissioning is a separate and distinct service from take-over which may commence at the beginning of a project and may continue until occupancy by the owner. Commissioning is an additional service often provided by an independent third party - a commissioning agent.
Take-over, by contrast, starts when a project nears construction completion. The first step in the take-over process is certification of substantial performance of the work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
33
Q

Explain the difference between Major Occupancy, Subsidiary Occupancy and Multiple Major Occupancies.

A

NBC Division A, 1.4.1.2.
Major occupancy means the principal occupancy for which a building or part thereof is used or intended to be used, and shall be deemed to include the subsidiary occupancies that are an integral part of the principal occupancy.
Subsidiary occupancies are those that are not the principal occupancy of the building (eg. small retail shop or theatre space in an office building).
3.2.2.6. Multiple Major occupancies occur when you have more than one major occupancy. In a building containing more that one major occupancy, the requirements for the most restricted occupancy apply to the whole building.
3.2.2.8. To be considered a major occupancy, they must cover at least 10% of the floor area of a storey provided they are not classified as Group F, Division 1 or 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
34
Q

Explain the links between the MasterFormat and the National Master Specification (NMS)

A

CHOP 2.3.8 - Construction Documents - Specifications
The National Master Specification (NMS) is a comprehensive text base, containing descriptions of every procedure, product or method likely to be encountered. This collection of specifications can be used in developing a project specification by editing contents to suit the requirements of a project.
MasterFormatTM is a system of numbers and titles for organizing construction information into a standard order or sequence.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
35
Q

Explain what is meant by “professional standard of care.”

A

CHOP 2.1.9 - Risks Related to Management of the Practice
All architects are expected to perform their services to a “professional standard of care.” This means that architects are required to provide service with the degree of care and skill that would be rendered by reasonably competent architects under the same circumstances and in the same geographic location. An architect who does not meet this standard may be found to be negligent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
36
Q

For a building not provided with a fire department connection, what is the maximum distance of a hydrant to the building?

A

NBC 3.2.5.5.(2)(b) 90m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
37
Q

For a building provided with a fire department connection, what is the maximum unobstructed path of travel for the firefighter from the vehicle to the building?

A

NBC 3.2.5.5.(2)(c) 45m

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
38
Q

How is depth of frost penetration determined for a building’s foundation?

A

NBC Division B 1.1.3.2.
Depth of frost penetration shall be established on the basis of local experience. Typically the Authority Having Jurisdiction will have building bylaws that dictate the minimum depth of foundations to prevent frost penetration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
39
Q

How is the fire resistance rating of an assembly calculated?

A

NBC Appendix D, D-2.3.4.
Add the fire resistant rating of the material on the fire-exposed side plus the time assigned for the framing members and additional protective measures such as insulation. For example, if you have a wood frame wall with studs spaced at 400mm o.c. (20 min) and a layer of 12.7mm Type X gypsum wallboard (25 min) on each side, the fire-resistance rating of that assembly is 45 minutes, not 70 minutes.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
40
Q

How is the profession of architecture regulated in Canada? What is the main document(s) that regulation is based upon?

A

CHOP 1.1.5, Self Regulation
The licensing and regulation of architects is carried out under provincial mandate. “Architect’s Acts” enable provincial associations to govern and regulate themselves separate from the provincial or territorial legislatures.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
41
Q

How is travel distance affected from a mezzanine when you have two exits to outside from the building vs. one exit?

A

NBC 3.4.2.2.(2)
One exit - measured from furthest point in mezzanine (longer distance)
Two exits - measured from the top of stairs exiting from mezzanine (shorter distance)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
42
Q

How long does copyright last?

A

CHOP 2.3.7, Appendix A - How long does Copyright Last?
Under a general rule, copyright subsists for the life of the author of the work, the remainder of the calendar year in which the author dies, plus an additional 50 years.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
43
Q

How long should an architect retain project files?

A

CHOP 2.1.5, Filing and Retrieval Systems - Retaining Files Records should be maintained well beyond completion of the project. Good records help to prepare a good defence against legal action. At a minimum, all project record should be retained until after expiry of the limitation period for pursuing a claim for professional negligence. In BC the limitation period is 2 years for damage or injury to property or person (see CH-30 in 2.1.9)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
44
Q

How many field reviews is an architect required to do?

A

CHOP 2.3.11, p. 4
There is no minimum or maximum legal requirement. The architect should schedule site visits at intervals appropriate to the construction. The frequency and timing is left to the judgement of the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
45
Q

How much liability insurance is an architect in Canada required to have?

A

AIBC Bulletin 66, AIBC Bylaw 16.3 & Architect’s Act
Depends on the province; in BC Architects are not required to have any liability insurance according to AIBC Bylaw 16.2d but Bulletin 66 requires that (before entering into an agreement to provide architectural services) a Certificate of Practice holder must notify the client in writing whether or not professional liability insurance is held and under what terms.
Section 24.2h in the Architect’s Act states that an institute’s bylaws may or may not include requirements for liability insurance; in BC, there is no requirement.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
46
Q

Identify some of the components in an architectural program or functional program.

A
  • the client’s philosophy, values, goals, and
    desired “image”;
  • determine the optimum size of a building;
  • the number of people or pieces of equipment that will occupy the spaces; * the nature of the activity in the space;
  • special furniture configurations;
  • environmental criteria;
  • security requirements;
  • site requirements, such as parking, circulation, orientation;
  • explicit space requirements for the future building, including: * definition of activities which will take place in each space;
  • the functional relationships of the spaces;
  • financial requirements and a preliminary budget; * scheduling and time frame for the project;
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
47
Q

If a client engages a consultant directly, such as a geotechnical engineer or a land surveyor, what should the architect do to minimize their liability?

A

Guide to Document Six, A18, Example 2 The architect should obtain from the client proof of professional liability insurance from all consultants that the client engages directly .

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
48
Q

If a project results in construction, the contract between arhcitect and client (Document 6) can be terminated in what 4 ways?

A

RAIC Document 6, GC8.7
1. Letter of termination from the client.
2. The contract can be terminated 7 days after the abandonment of the project.
3. 1 year passes from the date of certification of substantial performance of the work.
4. 1 year from the date of total completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
49
Q

If a sub-consultant (engineer) is hired by the architect instead of by the client, does this make the architect liable for that consultant’s work?

A

Document Six, GC 7.5
No. The client agrees that the architect shall not be liable to the client, in contract or in tort, for the acts, omissions or errors of such consultants whether retained by the architect or the client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
50
Q

If an architect hires an independent contractor (another architectural firm, etc.) to prepare documents (drawings, reports, etc.) and Document Nine is the contract used between the two parties, who owns the copyright on those materials?

A

Guide to Document Six, GC 5
The architect owns copyright. Document Nine binds the consultant (independent contractor) to all the terms and conditions of the lead contract (Document 6), including the statement that the work performed on the architect’s behalf is owned by the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
51
Q

If an architect is called upon to spend time preparing for a hearing, in which they have been summoned to testify on behalf of their client, how should they expect to be compensated for this extra work?

A

CHOP 2.1.10, Appendix A - The Architect as Expert Witness
An architect may be called upon to spend time preparing for the hearing, in consultation with the client, or with the client’s solicitor. This should be considered to be extra work, and fees should be discussed and agreed upon before the work is undertaken.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
52
Q

If an employee (an architect) of a firm
designs a building and then leaves the firm, who owns copyright of the design?

A

CHOP 2.3.7, Appendix A - Architects Own the Copyright in their Works
Under a general rule, the first owner of copy right in a work is its author. There are a number of special ownership rules, however, one of which provides that where an author is employed, and the work is made as part of that employment, the “employer” instead of the “author” is the first owner of the copyright. The rules on ownership can be changed by agreement, however. The copyright law requires that the agreement, or contract, be in writing.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
53
Q

If drawings and specifications disagree, which takes precedence?

A

CCDC 3, GC 1.1.7.1 & CHOP 2.3.8, Specifications and Drawings
In the event of conflict between the two, the specifications take precedence over the drawings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
54
Q

If owner and contractor agree that hazardous materials on site were not brought on to the place of work by the contractor, what measures should be taken?

A

Contract Price and Contract Time shall be increased an appropriate amount. (CCDC 2, GC 9.2.7.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
55
Q

If the client lacks the financial ability or authority to proceed, how much notice must be given to suspend the architect’s services?

A

The client must give seven (7) days written notice to the architect that the client elects to suspend the architect’s services. (RAIC Document 6, GC8)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
56
Q

If the contractor considers the work to be substantially performed and applies for payment, what does the architect do?

A

The architect looks at the work and decides if it is substantially performed. If it is substantially performed, a certificate of substantial performance is issued, as well as a list of things to be completed, and a timeline for completion. (CCDC 2, GC 5.4)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
57
Q

If the contractor encounters toxic or hazardous substances on site, what is the contractor obliged to do?

A

Take all reasonable steps, including stopping work to protect all people on site, then immediately report the circumstances to the consultant and owners. (CCDC 2, GC 9.2.5.)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
58
Q

If the scale of a client’s project requires the architect to increase their insurance coverage or obtain specialized insurance, who is responsible for paying?

A

RAIC Document Six, GC 7.2 The client.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
59
Q

If there is a conflict within the Contract Documents, what is the order of priority, from highest to lowest? (Hint - 8 items)

A

CCDC 2, GC 1.1.7.1
1. The agreement between the owner and contractor 2. The definitions
3. Supplemental conditions
4. General conditions
5. Division 1 of the specifications
6. Technical specifications
7. Material and finish schedules
8. Drawings

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
60
Q

In a bidding process, Contract B is formed when the owner accepts a bid in accordance with contract A. What is the primary legal obligation under Contract B, the Construction Contract?

A

To perform the work in accordance with the Contract Documents. (CCDC 23)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
61
Q

In the Construction Documents phase, which of the following services are considered basic, which are additional?
1. coordinate services of consultants as applicable,
2. construction documents consisting of drawings and specifications;
3. Application for Building Permit;
4. Building Code Equivalencies
5. advise the client of any adjustments to the statement of probable Construction Cost, including adjustments indicated by changes in requirements and general market conditions;
6. obtain instructions from and advise the client on the preparation of the necessary bidding information, bidding forms, conditions of the contract and the form of contract between the client and the contractor;
7. review statutes, regulations, codes and by laws applicable to the design and where necessary review the same with the authorities having jurisdiction in order that the client may apply for and obtain the consents, approvals, licences and permits necessary for the Project;
8. in British Columbia, provide and coordinate letters of assurance as applicable; and
9. review and obtain client approval before proceeding to next phase.

A

RAIC Document 6, Schedule of Architect’s Services
Basic services: 1-2, 5-9 Additional services: 3,4

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
62
Q

In the Construction Procurement phase, which of the following services are considered basic, which are additional?
1. Pre-Qualification of Bidders;
2. assist and advise the client in obtaining bids or negotiated proposals; 3. Issuing Bid Documents;
4. prepare and coordinate addenda as applicable;
5. analyze bids or negotiated proposals;
6. assist and advise in awarding and preparing contracts for construction;
7. review and obtain client approval before proceeding to next phase; 8. Preparation of Construction Contract(s)

A

RAIC Document 6, Schedule of Architect’s Services
Basic services: 2, 5-8 Additional services: 1,3,8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
63
Q

In the Construction/Contract Administration phase, which of the following services are considered basic, which are additional?
1. forward all instructions from the client to the contractor;
2. carry out and coordinate as applicable the General Review / Field Review of the Work;
3. keep the client informed of the progress and quality of the Work, and report to the client defects and deficiencies in the Work;
4. Full time on-site Project Representation;
5. require special inspection or testing of work, whether or not such work has been fabricated, installed or completed;
6. Review of contractor’s As-built Drawings;
7. prepare change orders and change directives for the client’s approval;
8. furnish supplemental instructions to the contractor;
9. receive from the contractor and forward to the client for the client’s review the written warranties and related documents;
10. prior to the end of the period of one year following the date of Substantial Performance of the Work, review any defects or deficiencies which have been observed and reported during that period;
11. issue certificates for payment;
12. issue a certificate of final payment;

A

RAIC Document 6, Schedule of Architect’s Services
Basic services: 1-3, 5, 7-12 Additional services: 4,6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
64
Q

In the Design Development phase, which of the following services are considered basic, which are additional?
1. coordinate services of consultants as applicable,
2. design development documents consisting of:
a. Site plan b.Plans
c. Elevations d. Sections
e. Project Brief
3. Promotional Presentations
4. prepare and submit to the client for approval a revised Construction Cost estimate;
5. continue to review applicable statutes, regulations, codes and by laws as the design of the Project is developed;
6. assist the client to obtain approval of authorities having jurisdiction, if applicable;
7. review and obtain client approval before proceeding to next phase.

A

RAIC Document 6, Schedule of Architect’s Services
Basic services: 1-2, 5-7 Additional services: 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
65
Q

In the Pre-design phase, which of the following services are considered basic, which are additional?
* Statement of Requirements or Building Program
* Financial feasibility study
* Site evaluation study
* Verifying accuracy of drawings furnished by client * Site Photographs
* Geotechnical or Soil Report
* Establish a Construction Budget
* Toxic and Hazardous Materials Report

A

RAIC Document 6, Schedule of Architect’s Services
All of pre-design services fall outside the basic services of an architect under the traditional project delivery method of design-bid-build which includes only the five phases - SD, DD, CD, BN, and CA.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
66
Q

In the Schematic Design phase, which of the following services are considered basic, which are additional?
1. coordinate services of consultants as applicable,
2. review and comment on the client’s Construction Budget in relation to the Client’s program of requirements;
3. Enhanced Building Envelope Services (in British Columbia)
4. Preparation of Presentation Models, Perspectives or Videos
5. review applicable statutes, regulations, codes and by laws and where necessary review the same with the authorities having jurisdiction;
6. assist the client to obtain approval of authorities having jurisdiction, if applicable;
7. Submissions for zoning changes
8. design documents to illustrate the scale and character of the Project
a. Site plan
b. Spatial relationship diagrams
c. Principal floor plans
d. Building sections
e. Elevations
f. Outline specifications
9. prepare and submit to the client a statement of probable Construction Cost based on current area or volume unit costs 10. Variances

A
  1. Variances
    RAIC Document 6, Schedule of Architect’s Services
    Basic services: 1,2,5,6,8a-f,9 Additional services: 3,4,7,10
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
67
Q

In what phase of a project should outline specifications be prepared?

A

CHOP 2.3.6, Design Development Tasks Design Development

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
68
Q

Is an architect required for all Part 3 buildings under the BC Building Code?

A

AIBC Bulletin 31
Yes. In addition to the requirements of the Act, all projects must also satisfy the current BC Building Code and local building bylaws. Under these building codes, architects are required to be engaged for design and field review and to provide corresponding assurances on all Part 3 buildings (of any occupancy or size) and any Part 9 buildings with common egress systems and firewalls. It is important to understand that the Part 3/Part 9 distinction is immaterial under
the Act.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
69
Q

Is it considered professional misconduct to participate in an invited competition?

A

RAIC Architectural Competitions, Creating a Competition Budget - Awards and Payments
Depends on the provincial association and how the architects are compensated. In BC it is against AIBC Bylaws to compete in Invited (non-endorsed) competitions where all architects are not equally remunerated. (I wasn’t able to determine with 100% certainty that it is acceptable for architects to participate in invited competitions if all the architects are compensated equally and fairly. I think it is ok but it may vary from province to province and depend on their bylaws)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
70
Q

List the following criteria for access route design:
1. Minimum width of a lane to be considered a street.
2. Maximum and minimum distance between building face and curb of street. 3. Maximum slope.

A

NBC
1. 6m 3.2.5.6.(1)(a)
2. 15m & 3m 3.2.5.5.(1)
3. 1:12.5 over minimum distance of 15m 3.2.5.6.(1)(d)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
71
Q

List the four main elements required in an Alternative Solution report.

A

NBC Division C, 2.3.1.1.
1. Explanation of the required measure that is not to be provided.
2. Analysis of the objectives and functions.
3. Proposed alternative measures.
4. Building code analysis and technical argument on why the alternative measures will be as good as the accepted solution.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
72
Q

List the rules related to writing a good specification.

A

CHOP 2.3.8 p.11
Be brief and clear
use imperative style
address instructions to the contractor
avoid repetition, specifying anything which is not to be enforced, “or equal” phrases, “scope” or “scope of work” paragraphs, weasel paragraphs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Name four methods of compensation for architectural services.

A

CHOP 2.1.10, The Architect’s Fee - Methods of Compensation
Compensation is usually by one of the following methods:
* Percentage (of the construction cost)
* Time basis (per diem or hourly rates)
* Lump sum (or fixed fee)
* Any combination of the above

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
73
Q

Name the five key factors to determine construction requirements for a building.

A

AIBC Building Code 1 Course 1. Building area
2. Building height
3. Number of streets facing 4. Major occupancy
5. Sprinklered or non-sprinklered

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
74
Q

Name the following contract form: CCDC 2

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 2 - Stipulated Price Contract
Standard prime contract between Owner and prime Contractor to perform the required work for a single, pre-determined fixed price or lump sum, regardless of the Contractor’s actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
75
Q

Name the following contract form: CCDC 3

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 3 - Cost Plus Contract
Standard prime contract between Owner and prime Contractor to perform the required work on an actual- cost basis, plus a percentage or fixed fee which is applied to actual costs.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
76
Q

Name the following contract form: CCDC 4

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 4 - Unit Price Contract
Standard prime contract between Owner and prime Contractor to perform the required work for a pre- determined, fixed amount for each specified unit of work performed. The total price is determined by multiplying the unit price by the actual, measured quantity of work performed for each specified unit.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
77
Q

Name the following contract form: CCDC 14

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 14 - Design-Build Stipulated Price Contract Standard prime contract between Owner and Design- Builder where the Design-Builder performs Design Services and Construction under one agreement, for a single, pre-determined stipulated or fixed price.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
78
Q

Name the following contract form: CCDC 15

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 15 - Design Services Contract between Design- Builder and Consultant
Standard contract between Design-Builder and Consultant to perform the design services required under a design-build contract between Owner and Design-Builder.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
79
Q

Name the following contract forms: CCDC 5A & 5B

A

http://www.ccdc.org/documents/index.html#CCDC5A
CCDC 5A - Construction Management Contract - For Services
Standard contract between Owner and Construction Manager for which the Work is to be performed by Trade Contractors. The Construction Manager acts as a limited agent of the Owner providing advisory services and administering and overseeing the contracts between the Owner and Trade Contractors.
CCDC 5B - Construction Management Contract - For Services and Construction
Standard contract between Owner and Construction Manager to provide advisory services during the pre-construction phase and perform the required Work during the construction phase. At the outset, the Work is performed on an actual-cost basis, plus a percentage or fixed fee which is applied to actual costs. The parties may agree to exercise the following options: Guaranteed Maximum Price (GMP), GMP Plus Percentage Cost Savings, and conversion into a Stipulated Price Contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
80
Q

Name the following contract forms: CCDC 9A & 9B

A

ht t p://www.ccdc.or g /docum ent s /index .ht m l#CCDC5 A
CCDC 9A - Statutory Declaration of Progress Payment Distribution by Contractor
A sworn statement for use by the Contractor as a condition of receiving payment for either the second and subsequent applications for progress payment or the release of holdback funds.
CCDC 9B - Statutory Declaration of Progress Payment Distribution by Subcontractor
A sworn statement for use by the Subcontractor as a condition of receiving payment for either the second and subsequent applications for progress payment or the release of holdback funds.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
81
Q

Name the following document: CCDC 20

A

CCDC 20 - A Guide to the Use of CCDC 2 - 2008 Stipulated Price Contract
A guide document designed to assist users of CCDC 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
82
Q

Name the following document: CCDC 22

A

CCDC 22 - A Guide to Construction Surety Bonds A guide document explaining the surety bonding process and the purpose and function of the CCDC standard bond forms (i.e. CCDC 220, 221 and 222).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
83
Q

Name the following document: CCDC 23

A

CCDC 23 - A Guide to Calling Bids and Awarding Construction Contracts
A guide document outlining the process of soliciting and evaluating construction bids, and awarding the construction contract. Includes a sample bid form.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
84
Q

Name the following document: CCDC 40

A

CCDC 40 - Rules for Mediation and Arbitration of Construction Disputes
Standard rules for mediation and arbitration of CCDC 2 construction disputes to be used in conjunction with the dispute resolution procedures of CCDC 2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
85
Q

Name the following document: CCDC 43

A

CCDC 43 - A Guide to the Use of CCDC 3 - 1998 Cost Plus Contract
A guide document designed to assist users of CCDC 3.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
86
Q

Under Document Nine, if the consultant fails to provide services properly or fails to comply with the requirement of this contract, the architect may terminate this contract after how long?

A

Document Nine, General Conditions 3.2.2 Seven days.

87
Q

Under RAIC Document Six, how much shall an architect be compensated if a project is terminated during the Schematic Design, Design Development, or Construction Documents Phase?

A

RAIC Document Six, GC 8.12
Termination expenses are computed as a percentage of the total fee earned to the time of termination for the Architect’s services and Additional Services, as follows:
20% if termination occurs during the SD phase
10% if termination occurs during the DD phase
5% if termination occurs during a phase subsequent to the design development phase

88
Q

Under the conditions of RAIC Document Six, how long is it before an architect can stop rendering services?

A

Fifty-two days. If any invoice submitted by the architect remains unpaid by the client for 45 days or more from the date the invoice was submitted, then the architect may give 7 days written notice to the client that the architect will suspend services.
If within seven days of delivery of the notice to suspend services, the client still has not paid the architect’s invoice, or the architect and the client have not agreed in writing on terms of payment of the invoice, the architect may suspend services on the project. Note that this differs slightly from GC 3.8.1 in Document Seven which states 60 days.

89
Q

Under the RAIC’s Guidelines for Architectural Competitions what is considered appropriate compensation for first prize of a competition? For other prizes?

A

RAIC Architectural Competitions, Awards and Payments
An amount equal to the fee for professional services to undertake that portion of the design.
Other prizes should total approximately twice the fee or twice the first prize money, therefore, if there are only two other competing practices, then they will also receive the same amount as the winner, however, if there are more competitors and the sponsor wishes to go 5 deep for prizing, then they will get less.

90
Q

Under the Standard Form Client-Architect Agreements, can a client sue an architect for more than the amount of insurance carried by the architect?

A

No. One of the general conditions in Document Six states that “the Client agrees that any and all claims, whether in contract or tort, which the Client has or hereafter may have against the Architect…shall be limited to the amount as mutually agreed to by the Client and by the Architect, and as described in the Architect’s Certificate of Insurance”

91
Q

Under what circumstances can a bid be deemed non-compliant?

A

The envelope is not sealed
Bidder not reviewed all the addenda
Not accompanied by bid bond or bid security Not properly signed or sealed
Surety bonding requirements not submitted

92
Q

Under what circumstances can the owner award a contract to someone other than the lowest bidder assuming all bids are compliant?

A

It is contrary to industry “best practice” to award a contract to someone other than the lowest bidder. Standard “privilege” clauses that state that the lowest or any bid will not necessarily be accepted are not advised and may not hold up to a legal challenge even though the current law of competitive bidding does not necessarily obligate the Owner to award to the lowest compliant bidder.

93
Q

Under what conditions can the architect suspend services?

A
  1. If an invoice remains unpaid for 45 days from the date the invoice was submitted, the architect can give 7 days written notice to the client that they will suspend services. OR
  2. If construction proceeds without a a building permit and building permit officials being dispatched to site.
  3. If the client takes action which violates applicable building codes or regulations. (RAIC Document 6, GC8.1-GC8.3)
94
Q

Under what conditions must a crawl space be considered a basement?

A

NBC 3.2.2.9.(1)
1. If it exceeds 1.8m in clear height, 2. Is used for any occupancy,
3. Contains flue pipes, or
4. Used as a plenum in combustible construction

95
Q

Under what law is Document Six governed?

A

Document Six, GC 9.1
The contract is governed by the law of the province or territory of Canada which is the principal place of business of the architect.

96
Q

What 3 things can proper building orientation and perimeter design help reduce?

A
  1. Energy use
  2. Amount of mechanical equipment
  3. Levels of artificial lighting. (Sustainable Design Fundamentals for Buildings, 2001 Edition)
97
Q

what are 3 advantages of water heating distribution systems?

A
  1. compact, easily hidden
  2. can be combined with domestic hot water systems
  3. good for radiant floor heating.
98
Q

What are 3 different methods of construction estimation?

A
  1. Composite unit rates (broken into specification sections)
    Uses very simplified historic data as a basis for calculating cost. Only reliable if the historic data is comparable.
  2. Gross building costs or area calculation (least accurate)
    Cost per m2 or per ft2. Architects should limit the use of this basic information by using it only as a general guide at the pre-design stage.
  3. Elemental building costs (most comprehensive)
    Quantity surveyors often use this method as the standard format for presenting cost information. It divides the building into major elements such as structure, exterior closure; and then applies relevant cost information from similar projects.
99
Q

what are 4 advantages of electric heating systems?

A
  1. most compact
  2. quick response to temperature changes 3. easily zoned
  3. low initial cost
100
Q

what are 5 examples of additional services not covered under RAIC document 6?

A
  1. feasibility studies
  2. business cases
  3. functional programming 4. submissions to authorities 5. life cycle cost studies
101
Q

What are 5 implied duties of the owner to treat all bidders fairly and equally in a bidding process?

A
  1. All bidders must receive the same information.
  2. All information relevant to the bid must be disclosed.
  3. The owner may not change any of the terms of the bid after bid closing.
  4. Any preferences must be disclosed (I.E. Local Builders preferred).
  5. Only compliant bids may be considered. (CCDC 23)
102
Q

What are four levels of Alternative Dispute Resolution?

A

CHOP 2.1.9 - Risks Related to Management of the Practice
In the event of a dispute, the architect may occasionally be requested to participate in some form of ADR.
Four levels of ADR, increasing in severity are:
1. Partnering - a method of dispute avoidance or prevention
2. Negotiation - both parties attempt to resolve the matter with some compromises
3. Mediation - a neutral person is appointed to act as mediator; mediator does not have to be an expert or provide any decisions, only there to facilitate and assist the two parties at arriving at a compromise
4. Arbitration - two or more parties submit a dispute to an independent and impartial arbitrator or arbitration panel, mutually agreed upon by the parties in dispute. The arbitrator makes a final and binding resolution in a judicial manner. An arbitrator must have knowledge of the law and standard legal proceedings.

103
Q

What are four types of specifications?

A
  1. Outline or Preliminary Specifications
    * Prepared during the design stage;
    * Describes the project components in general terms - appearance, texture, and other criteria - which affect the image and function of the project.
  2. Master Specifications
    * Comprehensive text base, containing descriptions of every procedure, product or method likely to be encountered;
    * Editing made easy because most of the required text in included in the master document and one only has to delete the unwanted text.
  3. Model Specifications
    * Assembled to suit specific and similar kinds of projects, such as certain building types; * Only the specifications for site work will differ significantly
  4. Project Specifications
    * One-of-a-kind specifications developed for a specific project.
104
Q

What are letters of assurance?

A

(not mentioned in NBC)
Letters of Assurance are legal accountability documents that are required under the BC Building Code (and presumably other provincial building codes??), intended to clearly identify the responsibilities of key players in a construction project.

105
Q

What are privilege clauses and why are they not recommended in bidding contracts?

A

CHOP 2.3.9, Privilege Clauses
The use of privilege clauses is no longer appropriate in bidding documents because owners are expected not to provide an unfair advantage to one bidder. A typical privilege clause would read as follows:
“The lowest or any tender shall not necessarily be accepted.”
Architects should review Section 2.0, Principles of the Law of Competitive Bidding of CCDC 23, A Guide to Calling Bids and Awarding Construction Contracts.

106
Q

What are some solar strategies that are common among most Canadian buildings?

A
  1. Orient buildings to take advantage of winter solar gain.
  2. Provide year round shading to western exposures. 3. Provide summer shading for southern exposures. 4. Incorporate shading using the landscape or integrated with the building.
  3. Orient buildings to allow for the addition of solar panels and other ‘plug-in’ elements. (Sustainable Design Fundamentals for Buildings, 2001 Edition)
107
Q

What are Supplemental Instructions?

A

CHOP 2.3.10, Documentation
Instructions issued by the architect (sometimes with the assistance of consultants) to clarify or interpret the contract documents. Can also be issued to provide direction to the contractor concerning a problem which may have resulted during the course of construction.

108
Q

What are the “3 E’s” in an architect’s “Pathway to the Profession?”

A

CHOP 1.1.4, Introduction
Education - CACB Accredited Professional Degree, CACB Certification of Education, Grandfathering of education, or RAIC Syllabus Program
Experience - complete IAP
Examination - pass EXAC or ARE

109
Q

What are the 4 soil classification systems, according to the ASTM Unified Soil Classification System?

A

Gravels, Sands, Silts, and Clays. * Organic material is a soil type, but is a really bad idea to use underneath a building. (Building Construction Illustrated, 1.04)

110
Q

What are the 5 phases of an architectural project?

A

CHOP 2.1.10 - The Architect’s Traditional Services Schematic Design
Design Development
Construction Documents
Bidding and Negotiation (Construction Procurement) Construction Phase (Contract Administration)

111
Q

What are the 6 areas of development addressed in the LEED Green Building Rating System?

A
  1. Sustainable Sites
  2. Water Efficiency
  3. Energy and Atmosphere
  4. Materials and Resources
  5. Indoor Environmental Quality
  6. Innovation & Design Process (Building Construction Illustrated, 1.04)
112
Q

What are the different construction cost class estimates?

A

CHOP 2.3.3, p.3 & 19
Class A (5-10%): Based on 100% complete tender documents; done at the end of the Construction Documents phase; contingency can be drastically reduced compared to Class C or D.
Class B (10-15%): Design Development; based on 66% complete design
Class C (15-20%): Schematic Design, based on 33% complete design
Class D (20-30%): Functional Program; based on concept sketch design, a rough order of magnitude

113
Q

What are the fire safety requirements for basements extending more than one storey below ground in a Part 3 building?

A

NBC 3.2.2.15.(2)
a) Sprinklered throughout
b) Floor assembly below the ground level shall be constructed as a fire separation with a fire-resistance rating not less than
i) 3 hours if the basements are used as Group E or Group F, Division 1 or 2 occupancies and
ii) 2 hours for all other occupancies
c) All loadbearing walls, columns and arches shall have a fire- resistance rating not less than that required for the construction that they support.

114
Q

What are the firefighting access route requirements for buildings greater than 600m2 or more than 3 storeys in height?

A

NBC 3.2.5.4.(1) & 3.2.5.5.(1)
Fire department access routes are required to be within 3m to 15m of a building face.

115
Q

What are the five main components or parts of Document Six?

A

Guide to the Canadian Standard Form of Contract for Architectural Services - Document Six, p.2
1. Cover and Table of Contents
2. Agreement Form
3. Definitions
4. General Conditions
5. Schedules of Architect’s Services and Client Responsibilities

116
Q

What are the three contracts used for Client-Architect Agreements?

A

RAIC Document Six - Canadian Standard Form of Contract Between Client and Architect (a complete, long form contract that includes a checklist for scope of services; recommended for larger or more complex projects)
RAIC Document Seven - Canadian Standard Form of Agreement Between Client and Architect - Abbreviated Version (a shortened version of Document Six; includes an abbreviated version of the scope of services checklist; suitable for small to medium-sized projects)
RAIC Document Eight - Short Form Agreement Between Client and Architect (a one-page document used as an interim agreement or “binder” in order to start work while a full agreement is being prepared)

117
Q

What are the three locations the architect may be required to make and record observations as part of a field review?

A

CHOP 2.3.11, Conducting a Field Review - Field Locations
* the construction site;
* the “extended” site;
* the plant or location of off-site fabrication.

118
Q

What are the three main environmental control materials in an assembly that separates a conditioned space from an unconditioned space?

A

NBC 9.25.1.1.
Thermal insulation, air barrier, and vapour barrier. The code states that all three must be present and that the assembly is constructed in such a way that the properties and relative position of all materials conform to Subsection 9.25.5.

119
Q

What are the three types of occupancy that can be granted near project completion?

A

CHOP 2.3.12, Take-over Procedures - Occupancy
1. Unconditional Occupancy - everything has been completed; no outstanding issues or deficiencies
2. Conditional Occupancy - occurs when a building or portion thereof, may be considered safe but is incomplete with respect to the scope of work shown on the construction documents submitted for the building permit.
3. Phased (or Partial) Occupancy - occurs when a discrete, or stand-alone, portion of a building is complete with respect to the scope of work shown (for that portion) on the construction documents submitted for the building permit, or with respect to the permit conditions or substantial building code compliance.

120
Q

What are the two broad categories of things an architect should review when performing field review services?

A

CHOP 2.3.11, Appendix B
1. Matters required by the Building Code:
These services are a regulatory requirement and they must be performed.
2. Contractual Matters or “good practice”:
These are matters related to workmanship, appearance, accuracy, etc. and they go beyond the review required for code-related matters.

121
Q

What are the two categories of architectural competitions?

A

RAIC Architectural Competitions, Competition Categories & CHOP 2.1.3, Competitions
Endorsed includes a professional advisor, abides by a jury’s decision, is endorsed by the appropriate provincial or territorial association of architects or the RAIC, and leads to a commission for the winning architect.
Non-endorsed is neither endorsed by the RAIC nor by the appropriate provincial or territorial association of architects. It may or may not have a professional advisor or use a jury for decision-making. It may or may not lead to a commission for the winning architect.

122
Q

What are the two contracts in the bidding process, and who are they between?

A

Contract A, the contract between the owner and each bidder, known as the Bidding Contract.
When the bid is selected, it leads to Contract B, the Construction Contract. (CCDC 23)

123
Q

What are the two main filing systems every architectural practice should maintain?

A

CHOP 2.1.5, Filing and Retrieval Systems - Filing systems
An architectural practice will require at least two type of filing systems:
1. Filing of information relating to the management of the practice
2. Filing of information relating to the management of the project

124
Q

What are three advantages of air heat distribution?

A

1.quick response
2.can also perform ventilation, cooling, humidity control and filtering.
3. no equipment in rooms

125
Q

What are three methods of writing specifications?

A

CHOP 2.3.8, Methods of Specifying
1. Proprietary Method
* Proprietary specifications identify products by their trade names and important characteristics.
2. Prescriptive Method
* A generic description of what is required, using no product, trade or manufacturers’ names, or any reference to manuals or standards.
3. Performance Method
* Performance specifications describe the desired end result of how the materials and systems will perform in the completed building.

126
Q

What are three ways a general contractor can be selected for a construction project?

A
  1. Open competitive bids (sometimes called public tender);
  2. Invited competitive bids (sometimes called invited tender);
  3. Direct selection
127
Q

What are two possible legal procedures affecting the construction of buildings?

A

Injunction - sought when a public body applies to the court for an order restraining a private individual or other body from violating an applicable law. It is often applied to stop an individual or company from constructing a building contrary to regulations, codes or bylaws. A typical example is a “stop work order.”
Mandamus - an order directing a public body to exercise a public duty, such as the issuance of a building permit. If a municipality refuses to issue a building permit and forces the client to apply to the court for a mandamus, the architect must be sure that all building plans and specifications comply fully with municipal bylaws and building codes.

128
Q

What buildings require the services of an architect?

A

Group A (Part 3) - Public Assembly:
– any one-storey building with an unsupported span exceeding 9 m or gross area exceeding 275 m2; – any building of more than one storey with gross area exceeding 235 m2; and
– all schools, any size
Group B - (Part 3) - Hospital, Sanatorium, or Home for the Aged, Institutional: – any building (excluding veterinary hospital) with a
capacity exceeding 12 beds
– any building with gross area exceeding 470 m2
Group C - Residential, Hotel or similar occupancy: – any building containing 5 or more dwelling units – any building containing 11 or more guest rooms
Group D & E - Commercial:
– any building with gross area exceeding 470 m2
Group F (F1: Part 3) - Industrial:
– any building with gross area exceeding 470 m2

129
Q

What do the bidding documents consist of? (6 items)

A
  • Bidding Requirements * Contract Forms
  • Contract Conditions
  • Specifications
  • Drawings
  • Addendum
130
Q

What do the construction documents consist of? (7 items)

A
  • Bidding Requirements * Contract Forms
  • Contract Conditions
  • Specifications
  • Drawings
  • Addendum
  • Contract Modifications
131
Q

What do the contract documents consist of? (6 items)

A

CHOP 2.3.8, p.1
* Contract Forms
* Contract Conditions
* Specifications
* Drawings
* Addendum
* Contract Modifications

132
Q

What does LEED stand for, and who developed it?

A

Leadership in Energy and Environmental Design, developed by the U.S. Green Building Council (Building Construction Illustrated, 1.04)

133
Q

What does the Certificate of Payment signify?

A

The issuance of the Certificate of Payment constitutes a representation by the architect to the client that based on the architect’s field reviews and review of the contractor’s schedule of values and application for payment, that the work has progressed to the value indicated. (RAIC Document 6, GC4)

134
Q

What does the Project Manual consist of? (4 items)

A

CHOP 2.3.8, p.1
* Bidding Requirements * Contract Forms
* Contract Conditions
* Specifications

135
Q

What Factors influence construction cost? (12 answers… If you dare!)

A

CHOP 2.3.3, Factors Affecting Cost
1. Type of project
2. Overhead
3.Profit
4. Market Conditions 5. Difficult Access
6. Fast schedule
7. Escalation/Inflation
8.Tax
9. Season and Weather
10. Change in functional program 11. Contingency
12. Regulations

136
Q

What five elements make up the Code of Ethics and Professional Conduct for architects?

A

CHOP 1.1.3, Code of Ethics and Professional Conduct
* competence
* conflict of interest
* full disclosure
* compliance with laws * professional conduct

137
Q

What is a bid bond?

A

CHOP 2.3.9, Bid Bond
The bid bond submitted by the contractor (bidder) guarantees that if the bid is accepted within the time period stated, the contractor will enter into a formal contract with the owner. If the contractor fails to enter into a contract, the surety will guarantee - up to the amount of the bid bond - to pay the difference in money between the amount of the contractor’s bid and the amount for which the owner legally contacts with another contractor for the project. Bid bonds are usually between 5% and 10% of the estimated construction cost; on very large projects, 2.5% is considered and appropriate amount.

138
Q

What is a bond?

A

CHOP 2.3.9, Bonds
A bond is an instrument which permits a contractor to provide an owner with a guarantee from a bonding company, known as a surety. The guarantee ensures that the contractor satisfactorily performs his/her obligations under a contract. A bond is not an insurance policy but instead a three-party undertaking whereby the surety agrees to indemnify the owner against loss arising from the failure of the contractor to perform obligations under contract.
For construction contracts, three bonds are of particular importance: * Bid bond;
* Performance bond;
* Labour and material payment bond

139
Q

What is a Certificate of Substantial Performance?

A

CHOP 2.3.10, p. 7 & 9
A certificate issued under the appropriate lien legislation attesting that the contract between the owner and the contractor is substantially complete.

140
Q

What is a Change Directive?

A

CHOP 2.3.10, Documentation
If the contractor’s price cannot quickly be agreed to, the architect may issue a Change Directive if the proposed changes are within the general scope of work described in the contract documents. A Change Directive avoids delays and permits work to proceed while negotiations continue over the price of the proposed change.

141
Q

What is a Change Order

A

CHOP 2.3.10, Documentation
Change Orders cover adjustments to the scope of work that require a change or changes to the contract price or contract time. The Change Order is the final form which indicates the agreement between the client/owner and the contractor on specific additions, deletions or revisions to the contract documents.

142
Q

What is a Fire Compartment?

A

NBC Division A, 1.4.1.2.
An enclosed space in a building that is separated from all other parts of the building by enclosing construction providing a fire separation having a required fire-resistance rating.

143
Q

What is a Fire-protection rating?

A

NBC Division A, 1.4.1.2.
The time in minutes or hours that a closure will withstand the passage of flame when exposed to fire under specified conditions of test and performance criteria, or as otherwise prescribed in the Code.

144
Q

What is a Fire-resistant rating?

A

NBC Division A, 1.4.1.2.
The time in minutes or hours that a material or assembly of materials will withstand the passage of flame and the transmission of heat when exposed to fire under specified conditions of test and performance criteria, or as determined by extension or interpretation of information derived therefrom as prescribed in the Code.

145
Q
A
146
Q

What is a labour and material payment bond?

A

CHOP 2.3.9, Labour and Material Payment Bond
A labour and material payment bond guarantees that claimants (sub-contractors, sub-trades, and suppliers who have direct contracts with the contractor) will be paid for labour and materials provided to the contractor for use on the project identified in the bond.

147
Q

What is a Letter of Acceptance? (used in the Construction Procurement Phase)

A

CHOP 2.3.9, Contract Award - Letter of Acceptance
The award of contract is usually accomplished by issuing a Letter of Acceptance from the client. This letter allows the contractor to start work immediately while a formal contract is drafted and executed.

148
Q

What is a Letter of Assurance?

A

CHOP 2.3.10, p. 8 & 2.3.12, p. 3
An official document provided by the architect or registered professional to the Authority Having Jurisdiction that the building has been constructed in substantial compliance with the building code, applicable regulations, and the construction documents accepted for building permit purposes. The LOA may be required before an Occupancy Permit is issued. Not all provinces require LOA’s. In BC, the standard forms of LOA’s must always be used as provided in the BC Building Code.

149
Q

What is a lien?

A

CHOP 2.3.10, p. 9
A legal claim on real property to satisfy a debt owned to the lien claimant by the property owner. This claim can carry the right to sell the property upon default.

150
Q

What is a performance bond?

A

CHOP 2.3.9, Performance Bond
The function of a performance bond is to indemnify the owner up to the amount of the bond in the event of default (bankruptcy or insolvency) on the part of the contractor. Frequently, the amount of a performance bond is based on a percentage of the contract amount, such as 50% or 100% of the contract amount.
A performance bond will not cover payment of labour and material claims.

151
Q

What is a Request for Information (RFI)?

A

CHOP 2.3.10, Documentation
The RFI is a procedure for the contractor to request clarifications when the intent of the contract documents is unclear, incorrect, or information is missing.

152
Q

What is a Schedule of Values?

A

CHOP 2.3.10, p. 7
A schedule submitted by the contractor at the start of a project, typically sub-divided by divisions, major sub-trades or quantifiable elements related to the construction. The work performed by the general contractor’s own forces, as well as the costs for mobilization, supervision, overhead, and profit, are usually indicated. The value of sub-trade contracts and sub-trade breakdowns assists in determining the appropriate Certificates for Payment and the progressive release of holdback monies for lien purposes.

153
Q

What is a shop drawing?

A

CHOP 2.3.10, p. 9
A drawing, diagram, schedule or data prepared on behalf of the contractor to indicate precise details of the construction materials, products or installation. Usually prepared by the “shop” or trade or manufacturer, supplier or fabricator responsible for the particular product.

154
Q

What is a statute of limitations?

A

CHOP 2.1.9 - Risks Related to Management of the Practice
Every province and territory has a different statute of limitations. These statutes of limitations usually provide a time limit when a claim can be made. These laws indicate the number of years after which no legal proceeding may be undertaken following a date when the damage (or negligent act) was discovered or ought to have been discovered. However, no time limitation applies to recognition of damage (or negligence) in the life of a building. In other words, professional responsibility and potential liability for each and every project remains with the architect for life.

155
Q

What is a Statutory Declaration and how is it used in a typical project?

A

CHOP 2.3.10, p.4 & CCDC 2, 5.5.1
At the end of construction, the contract documents generally require the contractor and/or sub-contractors to submit Statutory Declarations for review by the architect (these documents are CCDC 9A and 9B). Statutory Declarations are applications for the release of holdback. After the receipt of an application for payment from the Contractor the Consultant will issue a certificate for payment of the holdback amount.

156
Q

What is a Statutory Holdback?

A

CHOP 2.3.10, p. 7 & 9
A percentage of the monetary amount payable under a (construction) contract, which is held as security for a certain period of time. The percentage and period of time are based on the provincial lien legislation.

157
Q

What is Architecture 2030 and the 2030 Challenge?

A

Architecture 2030 is an environmental advocacy group whose mission is “to provide information and innovative solutions in the field of architecture and planning”. The 2030 challenge calls for all new buildings and developments to use half the fossil fuel energy they would typically consume, and all buildings to be carbon neutral by 2030. (Building Construction Illustrated, 1.04)

158
Q

What is Functional Programming (or design brief)? Is it part of an architect’s basic services?

A

CHOP 2.3.4, p.3 & 8
Functional Programming can be described as the decision-making process that clearly defines the problem and scope of work for design. The functional program describes the requirements which a building must satisfy in order to support and enhance human activities. Architectural fees for functional programming are not part of “basic services.”

159
Q

What is MasterFormat?

A

CHOP 2.3.8, MasterFormat
MasterFormatTM is a system of numbers and titles for organizing construction information into a regular standard order or sequence. It is organized in the well-known “49 Division” Specification Format, using a six-digit section numbering system. Each section is, in turn, organized according to a three-part format for articles titled: General, Products and Execution.

160
Q

What is one key difference between endorsed and non-endorsed architectural competitions when choosing a winner?

A

RAIC Architectural Competitions, Stakeholders/Participants
In an endorsed competition, the sponsor (client) abides by the jury’s decision when announcing the winner. In a non-endorsed competition, there may or may not be a jury, and even if there is, the sponsor is not required to use the jury’s decision to choose the winner; the sponsor retains the final decision.

161
Q

What is RAIC Document Six?

A

CHOP 2.1.10 - Client-Architect Agreements Canadian Standard Form of Contract for Architectural Services Between Client and Architect. It is the accepted national standard contract used by architects.

162
Q

What is SectionFormat?

A

The Three Part SectionFormat’s primary purpose is to provide a uniform approach for organizing articles and paragraphs within the project specification sections to produce a consistent appearance and completeness. The architect should use both the MasterFormat system in combination with the Three Part SectionFormat as a guide in writing specifications sections for every project except for simple outline specifications or minor projects.
The three parts of the SectionFormat are:
Part 1, General:
This part covers those subjects which:
* Relate to the work in general;
* Provide a general description of the system, where applicable;
* Identify references to standards;
* Define the administrative and technical requirements specific to a particular section.
Part 2, Products:
This part defines the acceptable equipment, materials, fixtures, mixes, and fabrications, that is, “product” items to be incorporated into the work.
Part 3, Execution:
This part describes the manner in which items covered by Part 2 are to be incorporated into the work.

163
Q

What is Sound Transmission Class (STC) and how does it relate to actual sound transmission? For example, if you have a wall assembly with an STC rating of 33 and one with 63, which one is quieter and by how much?

A

NBC A-9.10.3.1.A. & Wikipedia
Sound Transmission Class (or STC) is an integer rating of how well a building partition attenuates airborne sound. STC is roughly the decibel reduction in noise a partition can provide, abbreviated ‘dB’. The dB scale is a logarithmic one and the human ear perceives a 10dB reduction in sound as roughly halving the volume - a 40 dB noise subjectively seems half as loud as a 50 dB one. Similarly, a wall with an STC of 63 is perceived by the human ear to be 88% quieter or allow 1/8 as much perceived sound through than a wall with an STC of 33. From 33 to 43 sound is halved (1/2), from 43 to 53 it’s halved again (1/4), from 53 to 63 it’s halved yet again (1/8).

164
Q

What is Substantial Performance of the work?

A

CCDC 2, Definitions
Substantial Performance of the Work shall have been reached when the work is ready for use or is being used for the purpose intended, and is so certified by the consultant.

165
Q

What is the ‘Minimum RSI Ratio’ and how does it affect the construction of building envelope assemblies?

A

NBC 9.25.4.3. & A-9.25.5.1. & Figure A-9.25.5.2.
Minimum RSI Ratio is the minimum amount of insulation outboard of a plane of low air and vapour permeance (such as 1/2” plywood) compared to the amount of insulation inboard of this plane. Areas with higher heating degree days require higher RSI Ratios, or more insulation on the outboard side of this plane, to ensure the dew point lies outside this plane and prevents moisture from condensing inside the wall cavity with nowhere to escape.

166
Q

What is the architect required to do under the Schedule of Architect’s Services in Document Six prior to the end of the period of one year following the date of Substantial Performance of the Work?

A

Document Six, Schedule of Architect’s Services, 5.21
The architect must review any defects or deficiencies which have been observed and reported during that period and notify the contractor in writing of those items requiring attention by the contractor to complete the work in accordance with the contract.

167
Q

What is the difference between a Field Inspection and a Field Review?

A

CHOP 2.3.11, p. 1
An inspection is a “close examination” of construction - this level of service is beyond the architect’s responsibilities.

168
Q

What is the difference between Construction Cost, Construction Budget, and Project Budget?

A

Document Six, Definitions & CHOP 2.3.3, Definitions
Construction Cost is the contract price(s) of all Project elements designed or specified by, or on behalf of, or as a result of, the coordination by the Architect, including cash allowances, building permit fees, changes, construction management fees or other fees for the coordination and procurement of construction services, and all applicable taxes, including the full amount of value-added taxes, whether recoverable or not.
Construction Budget is the client’s combined estimate of the construction cost, construction contingencies and GST or HST, or if there is no client’s combined estimate, an amount agreed to by the client and the architect. In essence, this number is an estimate provided at the early stages of a project whereas the construction cost is better defined.
Project Budget is the client’s estimated total expenditure for the entire project. It includes, but is not limited to, the construction budget, professional fees, costs of land, rights of way, and all other costs to the client for the project.

169
Q

What is the difference between cost planning and cost control? Whose responsibility is it to define and monitor these?

A

CHOP 2.3.3, Introduction - The Role of the Architect in Cost Planning and Control
Cost planning (or the preparation of construction cost estimates) is done in the predesign and design stages, whereas cost control (or the monitoring of construction costs) is done at the later stages. The architect is responsible for defining and monitoring these although they may depend on other consultants such as quantity surveyors or firms that specialize in cost estimation to aid in determining the amounts.

170
Q

What is the difference between Supplemental and General Conditions in CCDC 2?

A

Supplemental Conditions are amendments or modifications to the General Conditions portion of the CCDC 2 document

171
Q

What is the Final Certificate for Payment and when is it issued?

A

CHOP 2.3.12, Take-over Procedures
Once the architect is satisfied that all deficiencies have been corrected and that all work under the contract has been completed, the contractor can apply for payment for the outstanding amount so that the architect can issue the Final Certificate for Payment.

172
Q

What is the fire resistance rating required for a roof-top enclosure for elevator machinery or for a service room?

A

NBC 3.2.2.14.(1) & (2)
No fire resistance rating required if not more than 1 storey. If more than one storey the rooms shall be constructed in accordance with the type of construction required by Articles 3.2.2.20. to 3.2.2.88.

173
Q

What is the first thing an architect should do if they have been asked by a client to appear as a witness in a case arising out of a project in which they have provided professional services?

A

CHOP 2.1.10 Appendix A - The Architect as Expert Witness
The architect should contact their professional errors and omissions insurer to inform the insurer and to obtain guidance.

174
Q

What is the formula used by the payment certifier to determine if a certificate of completion or substantial performance can be issued?

A

This depends on provincial or territorial lien legislation. In BC, in order to qualify for substantial performance, the extent of work remaining must be evaluated by the payment certifier (usually the architect) as being capable of completion or correction at a cost of not more than 3% of the first $500,000 of the contract plus 2% of its second $500,000 plus 1% of the balance. As well, for purposes of the statute, an improvement is completed if it or a substantial part of it is ready for use or is being used for the purpose intended. (Lien Act, AIBC)

175
Q

What is the latest an architect should issue an addendum before bid closing?

A

CHOP 2.3.9, Addenda
The last opportunity for issuing an addendum should be no later than four working days before bid closing. If this is not possible, consideration should be given to extending the bid period.

176
Q

What is the main role of the Canadian Architectural Certification Board (CACB)?

A

CHOP 1.1.4, Education
* certify the academic qualifications of candidates;
* accredit programs offered by Canadian university schools of architecture.

177
Q

What is the maximum height difference you can have without a guard in a Part 9 building?

A

NBC 9.8.8.1. (3)
2 risers or 400mm (16”)

178
Q

What is the maximum number of steps allowed without a hand rail?

A

NBC 9.8.7.1. (3)
For occupancies other than single dwelling units: All steps must have a handrail
For single dwelling units: Interior - 2 risers Exterior - 3 risers

179
Q

What is the maximum number of storeys you can build with combustible construction?

A

NBC 3.2.2.50.(2)
Four.

180
Q

What is the maximum percentage of floor area that an open vs. enclosed mezzanine can be?

A

NBC 3.2.1.1.(3) & (4)
Open mezzanine: <40% (visual obstructions taller than 1070mm not permitted)
Closed mezzanine: <10% (completely closed to ceiling or have visual obstructions taller than 1070mm)

181
Q

What is the minimum number of risers allowed in an interior run of stairs?

A

NBC 3.4.6.2. (1)
Every flight of interior stairs shall have not less than 3 risers.

182
Q

What is the period of irrevocability?

A

CHOP 2.3.9, Bid Period and Bid Closing The time during which a bid call is open; usually the period provided for in the bid bond. Based on the conditions of the “bid contract,” bidders are unable to withdraw their bids during the period of irrevocability.

183
Q

What is the purpose of field reviews?

A

CHOP 2.3.11, Purpose of Field Review
Field reviews are based on a systematic, random sampling of the work. The architect’s duty during field review is to carry out sufficient periodic site visits at appropriate intervals during the various stages of construction to determine if the work is in general conformity with the contract documents. In addition, the architect reports on the progress of the work and observations made on site. In most agreements, such as RAIC Document Six, the architect is not required to make exhaustive inspections or continuous on-site review; nor is the architect responsible for the construction methods or procedures or for construction safety.

184
Q

What is the purpose of progressive release of holdbacks?

A

This allows the release of holdbacks to subcontractors or suppliers in advance of the substantial performance of the work.

185
Q

What is the purpose of specifications?

A

CHOP 2.3.8, Specifications and Drawings
* complement and permit simplification of the drawings;
* limit the role of the drawings to address form, shape, dimension, and location;
* describe requirements for quality and workmanship which the drawings may not be able to address;
* address compatibility of materials.

186
Q

What is the purpose of the Intern Architect Program (IAP)?

A

CHOP 1.1.4, Experience
* meet generally recognized standards of practical skill
* practice architecture in a way that protects and health and safety of the public

187
Q

What is the purpose or function of the working drawings?

A

CHOP 2.3.7 - Construction Documents - Drawings As part of the construction contract, the working drawings take on a legal significance for which architects must assume responsibility. The purpose of the drawings is to address form, shape, dimensions, and location.

188
Q

What is the recommended minimum amount of time an architect should retain files on a project?

A

CHOP 2.1.5, p. 3
Project records should be retained until after expiry of the limitation period for pursuing a claim for professional negligence. The time period contained in the statutes of limitations varies from province to province (see 2.1.9 CH-30)

189
Q

What must an architect ensure if they allow an employee to work from home or out of office to produce documents that the architect must then seal with their stamp? Is this requirement altered if the employee is a registered architect?

A

CHOP 2.1.7, Managing Human Resources - Work from Home
The architect must determine whether the off-site work can be under the “care and control” or “direct supervision” (also called “responsible control”) of the registered member in order to apply the architects’ seal, as required under provincial or territorial Architects Acts. This applies whether or not the employee happens to be a registered architect so long as they are not the person providing the seal. If the employee is a registered architect and has been entrusted by the principal architect to administer their own seal for the project documents then the principal may not be required to have direct supervision if the company’s liability insurance includes liability coverage for employees as well as owners. It is recommended that all architects be familiar with the terms of their practice’s liability insurance to determine who is able to seal documents and under what circumstances direct supervision is required.

190
Q

What must the architect do at the end of each phase (SD, DD, CD) to ensure the project stays on budget?

A

Document Six, Schedule of Architect’s Services
Update and revise the construction cost estimate. As the project becomes more and more detailed, this estimate should become more and more accurate. The architect’s fee, if percentage-based and calculated under the F2 Fee classification as described in the Guide to Document 6, should be adjusted accordingly at the end of each phase. The architect’s final fee is then set at the end of the bidding phase when the winning bid is chosen - this is the final construction cost.

191
Q

What problem may arise if a practice were to allow employees to perform part or all of their work from home, through e-mail or other forms of communication?

A

CHOP 2.1.7, Managing Human Resources
The architect must determine whether the off-site work can be under the “care and control” or “direct supervision” (also called “responsible control”) of the registered member in order to apply the architects’ seal, as required under provincial or territorial Architects Acts.

192
Q

What resources are available to an architect to produce a project cost estimate?

A

CHOP 2.3.3, Techniques
There are various types of cost consultants and/or resources available to the architect to produce a reliable estimate if they do not have the expertise or resources to produce one in-house.
Quantity Surveyors - provide professional service at hourly rates, or at a fixed or percentage fee of the construction budget.
Construction Managers and other Development/Construction Experts - Other sources of expertise directly from the construction industry include construction managers, contractors, design-builders, and developers.
Construction Price Index - data usually published by government agencies and private companies. These publications are useful only as a guide to show trends; usually some months out-of-date; often presented in graph form for ease of
co mmunica tio n.
Publications - available from government agencies, private interest groups, private companies, and quantity surveyors. The information comes in printed or electronic form, and the cost varies considerably depending on the amount of detail, completeness, and ease of use. Data from government agencies are more useful for identifying trends and differences in national, regional, and local costs than for calculating the cost of a specific building.

193
Q

What role do sub-consultants play in performing field reviews and determining percentage of work completed?

A

CHOP 2.3.11, Field Review Services of Consultants
The architect is usually the prime or “managing and coordinating” consultant, and is responsible for coordinating the field functions of the engineering and other consultants. All consultants should be required to submit field review reports in a format similar to that used by the architect, and the architect will distribute the reports as required. In addition, the architect relies on the consultants to determine the value or percentage of work completed by each respective discipline in order to prepare Certificates for Payment.

194
Q

What should an architect do if they are summoned to testify by a party other than the client?

A

CHOP 2.1.10 Appendix A - The Architect as Expert Witness
The architect must contact his professional errors and omissions insurer to inform the insurer and to obtain guidance.
The architect is under no legal obligation to speak to a party or a lawyer representing a party other than their client. However, if summoned, the architect will be under a legal obligation to appear in court or before the relevant tribunal.
Regardless of who has asked the architect to testify (be it the client or another party), the architect should remember to testify in a manner which is complete and even-handed. The architect’s role is not to promote the client’s case.

195
Q

What should an architect look for when they review a bid submitted by a general contractor? (8 things)

A

CHOP 2.3.9, Analysis of Bids
* the completeness of each bid;
* the bid amount and the amount of valueadded taxes such as GST, HST or QST;
* the proposed construction start date and schedule;
* inclusion of all addenda;
* sub-contractors listed, including follow-up of the references;
* manufacturers and suppliers listed with follow-up as required;
* alternatives;
* unit prices.

196
Q

What should the architect do if only one bid is submitted during a call for bids?

A

CHOP 2.3.9, Bid Period and Bid Closing
If only one bid is submitted, the architect should advise the client to consider returning the bid unopened, or negotiating with the sole bidder.

197
Q

What should the architect do if the fees for a particular project are not commensurate with the professional services required?

A

CHOP 2.1.9, Risks Related to Management of a Project - The Project: Design and Documentation: Professional Fees
If the fees for a particular project are not commensurate with the professional services required, the architect should attempt to renegotiate. The professional services must not be compromised even if the architect chooses to accept a commission that has fees below what they consider adequate to do a thorough job. Refer to RAIC document, A Guide to Determining Appropriate Fees for the Services of and Architect.

198
Q

What three items are excluded from the construction cost as defined in the Definitions of Document Six?

A

Document Six, Definitions
1. Compensation of the architect and the consultants
2, Other professional fees which are the responsibility of the client
3. Land cost and land development charges

199
Q

What tool can the architect use to minimize risk before releasing a set of documents and ensure they are complete and correct?

A

CHOP 2.1.9, Risks Related to Management of a Project - The Project: Design and Documentation: Checklists
One of the most important elements in the management of risk is a thorough and comprehensive checking process. This element may the singular most important one in mitigating the risk of incomplete, incorrect, non-comprehensive or uncoordinated documents. Many practices develop and use exhaustive checklists to ensure that the many items required to complete a set of drawings have been included.
A proper checking process is highly disciplined and should be followed rigorously. A simple method is to apply - without exception - the rule that the drawings and specifications are not to be sealed until after the checking process has been completed.

200
Q

What two documents define the nature and scope of the architect’s services during the construction phase?

A

CHOP 2.3.10, Purpose of Contract Administration
1. The construction contract (such as CCCDC 2)
2. The client-architect agreement (such as Canadian Standard Form of Contract Between Client and Architect: RAIC Document Six).

201
Q

What’s the relationship between Sound Transmission Class rating and an assembly’s structural make-up?

A

NBC A-9.10.3.1.
Acoustical ratings (or STC rating) for assemblies decrease with decreasing depth and decreasing separation of the structural members.

202
Q

When a contractor considers the work to be completed, they issue an application for final payment. What does the architect do next?

A

The architect reviews the work within 10 days, and if the architect agrees, will issue a certificate of final payment.

203
Q

When a project is nearing its end and the architect is ready to terminate their services why is it important for them to understand the lien legislation in their province or territory?

A

CHOP 2.3.10, p. 8
To be able to adequately prepare a Certificate of Substantial Performance which is based on this lien legislation.

204
Q

When an architect issues a Certificate for Payment to the owner, the architect guarantees that the contractor has done all of the work they are requesting payment for and that it has been done correctly and completely, true or false?

A

CCDC 2,GC 2.2.17
False. All certificates issued by the Consultant will be to the best of the Consultant’s knowledge, information and belief. By issuing any certificate, the Consultant does not guarantee the Work is correct or complete.

205
Q

When are most client-architect agreements terminated and what should the architect do just before the termination of the agreement?

A

CHOP 2.1.9, Risks Related to Management of a Project - The Project: Post-construction
Most client-architect agreements provide for the termination of the agreement one year following the date of substantial performance. The architect should provide a list of warranty items for correction by the contractor, following a final on-site review scheduled shortly before expiry of the warranty period.

206
Q

When are Parts 3,4,5 and 6 applied to buildngs?

A

NBC 1.3.3.2.(1)
Post-disaster buildings
Building used for major occupancies classified as Group A, assembly
Group B, care, treatment or detention
Group F, Division 1, high-hazard industrial Group C,D,E,and F2 & F3 exceeding 600 s.m. in building area or exceeding 3 storeys in building height

207
Q

When calculating a percentage-based fee, what should the architect use and what level of service does this fee include?

A

CHOP 2.1.10, The Architect’s Fee - Fee Calculation
Each provincial or territorial association of architects provides a schedule or tarrif of fees to be used by their member architects. In provincial or territorial fee guidelines, percentage fees usually include an outline of what they consider to be basic services plus the fees of structural, mechanical, and electrical engineers - the three common engineering disciplines.

208
Q

When drawings of different scales and different dates have conflicting information, which documents govern?

A

CHOP 2.3.7, Coordination of Drawings
CCDC 2 GC 1.1.7 indicates that “drawings of a larger scale shall govern over those of smaller scale of the same date” and that “later dated documents shall govern over earlier documents of the same type”.

209
Q

When reviewing and awarding construction contracts what should the architect do if the lowest bona fide bid exceeds the construction cost estimate by 15%?

A

CHOP 2.3.3 p.15 & RAIC Doc Six, General Conditions 3.4 1. Obtain approval from the client for an increase in the construction budget
2. Re-bid or negotiate
3. Modify the construction documents to reduce the construction cost (for no additional fee if the increased bid is not due to extraordinary market conditions or other factors not reasonably foreseeable by or under control of the architect).
4. Terminate the contract if the project is abandoned

210
Q

When reviewing bids, the architect may categorize them into two major types; what are they?

A

CHOP 2.3.9, Analysis of Bids - Bid Types 1. Compliant - meets all the bidding criteria
2. Non-compliant - any irregular bid that might be considered informal, non- responsive, incomplete, improperly qualified or conditional.

211
Q

Which of the following are considered to be an architect’s instruments of service?
Plans
Sketches
Drawings
Graphic representations Specifications Computer-generated designs Reports

A

RAIC Document 6, Definitions All of them.

212
Q

Which of the following buildings require an architect in
BC?
1. 1-storey movie theatre with a span of 8m and gross area of 200s.m. 2. Small, 100s.m. 2-classroom school
3. 2-storey, 400s.m. hospital with 10 beds
4. 3-storey, 550s.m. motel with 10 guest rooms
5. 4-storey, 500s.m. 5-unit townhouse
6. 1-storey, 450s.m. doughnut shop
7. 2-storey, 530s.m. warehouse, medium hazard
8. 1-storey 150s.m. biohazard facility
9. 2-storey, 590s.m. footprint, 6-unit townhouse
10. 3-storey, 1700s.m. gross (566 footprint) mansion

A

AIBC Bulletin 31 & NBC Div. A, 1.3.3.2.
1. No under the Architect’s Act (AA) but yes under the National Building Code (NBC)
2. Yes under AA and NBC
3. No under AA, yes under NBC
4. No under AA, ??? under NBC
5. Yes under AA and NBC
6. No under AA, no under NBC
7. Yes under AA, no under NBC
8. Yes under AA and NBC
9. Yes under AA, no under NBC (to be confirmed)
10. No under AA, no under NBC

213
Q

Which soils are most susceptible to frost action?

A

Silts and clays are the most susceptible to frost action, while sands and gravels are the least - the same is true about permeability - low permeable soils retain water, which expands when frozen.

214
Q

Why should some types of consultants such as geotechnical engineers, not be hired directly by architects?

A

CHOP 1.2.3, Types of Consultants
Geotechnical and environmental remediation engineers and certain other specialists (such as land surveyors) should be retained directly by the client because architectural professional liability insurance policies do not typically cover these services. Still, the architect should obtain form the client proof of professional liability insurance from all consultants that the client engages directly.
Most insurance underwriters will, however, cover architects for hiring the three “basic engineering consultants” - these are structural, mechanical, and electrical engineers. If the architect chooses to hire a consultant directly that is not considered a “basic consultant” then they should use RAIC Document 9 as it references Document 6 and subjects that consultant to the general conditions of the main contract between the client and architect. Document 9 is not a stand alone agreement and it is expected that the RAIC Document 6 be appended to it - ensures the consultants have a full understanding of the expected and required services (Agreements with Consultants)