Exam 3 Flashcards
What is Material Requirement Planning?
a logical, easily understood approach to the problem of managing the parts, components and materials needed to produce end items
what are the two question in MRP
1.) how much of each part is needed
2.) when to order the part
What drives the MRP system
Dependent Demand
What are the data sources needed for an MRP program
1.) Master production schedule
2.) Bill of material file
3.) Inventory records file
What is Master Production Schedule
Aggregate plan shows overall quantities to produce
shows quantities of each type, with information about the production time frame
What is the Bill of Material
“need 3 of product B to make 1 of product A”
What is the Inventory Status Record
tells you information describing the item and information about part availability
“thing we did in class with figuring out gross requirement”
What is the gross requirment (MRP)
total required for an item
What is the projected available balance (MRP)
inventory of an item expected at the end of a period
what is scheduled receipts (MRP)
orders that have already been released and scheduled to arrive in this time period
what are net requirements (MRP)
amount needed when the previous period’s projected available balance plus scheduled receipts is not sufficient to cover the gross requirements
what are planned order receipts (MRP)
quantity that is planned to be released and will arrive in this time period
What to do if Safety Stock is needed
reduce the projected available balance for the first period ONLY by the safety stock amount
Term: Available to Promise
- Identifies the difference between the number of units currently
included in the master schedule and the actual customer orders - Stock currently held in inventory may be assigned to a customer order
(allocated) or may be available for future customer orders (available to
promise)
What is the MRP Process
- start with level 0 items (independent demand)
- calculate the net requirement and if it is below 1 plan order receipts
- calculate the projected available balance and move it to next week
- continue to level 1 item (dependent demand)
what should you do if Net requirement is less than 1
plan order receipts
Lot sizes
the part quantities issued in the planned order receipts and planned order releases section of MRP
Lot for Lot
produces exactly what is needed
-minimizes carrying costs
Economic Order Quantity (EOQ)
calculate reorder quantity based on EOQ
what are the EOQ cautions
not designed for a system for discrete time periods
do not always cover the entire number of periods
What is Least Total Cost
pick product that has holding cost and setup costs closest to eachother
sustainability
the ability to meet current resource needs without compromising the ability of the future generations to meet their needs
shareholders
individuals or companies that legally own one or more shares of stock in the company
stakeholders
individuals or organizations who are directly or indirectly influenced by the actions of the firm