Exam 2 Flashcards
Smaller batch sizes yields
Shorter leadtime, smaller WIP, fewer defects, greater scheduling flexibility
BUT —> requires more handling and changeovers
To achieve the benefits of small batch production you must reduce change over/set up time
Quick change methodologies
- RETAD: rapid exchange of tools and dies
- SMED: Single minute exchange of dies
- OTED: One touch exchange of dies
Most set up tasks fall into three categories
1) transfer and cleanup
2) remove and install
3) adjustment
The four steps of the SMED procedure
1) Study existing set up/change over methods
2) Convert as many internal steps to external steps as possible
3) Improve all steps
4) Abolish the set up
Step 1 of SMED: study existing method
• distinguish internal from external tasks
– internal tasks: must be done while machine is stopped
– external tasks: can be done while the machine is running
– unnecessary tasks: can be eliminated
• use kaizen team approach, review data, take notes
Step 2 of SMED: Convert internal to external
Convert any activity that can be done safely while the machine is running to external set up steps
Step 3 of SMED: Improve or shorten internal steps
• Shortening internal steps has immediate impact on reducing downtime
• improve every task in the set up procedure
• both internal and external time shortened
• the ultimate goal: it is so short that it no longer matters
-set up time should be less than or equal to tech time
Step 4 of SMED: Abolish the set up
1) redesign products/parts to eliminate changeover
2) use machines that can produce more than one kind of part at the same time
3) use less versatile multiple machines; dedicate each machine to one kind of product/part
Kanban
A Japanese word for card
– the card is an authorization for the next container of material to be produced
– a sequence of kanban PULL material through the process
– there are different sorts of signals, but they all are still kanban
Push system versus pull system
• push system: schedules are created by MRP system
– problem: schedules are often invalid or obsolete because they ignore interruptions and inventory builds up
• Pull system: worker at station 2 producer ONLY to satisfy demand from downstream, worker withdrawals needed material from station 1 only as needed
– worker at station 1 produces only to satisfy demand from station 2, withdrawals needed material from upstream as needed
Buffer stock
Enables station 2 to meet demand quickly and not have to wait on station 1
– the quantity remaining in buffer stock signals when station 1 should produce more
Guidelines for assembly area operators
- apply to all parts of kanban system
– list all the parts in the kanban system
– the MRP work order system applies to all other parts
– take only one container per part number from the kanban storage rack whenever you run out
– before taking a full container of parts, return empty to rack
Re-Order point equation
ROP = LT(D) + SS
ROP: re-order point
LT: lead time
D: demand
SS: saftey stock
Hospital system operating rules
– For users withdrawing containers: take only one item per part number from the kanban storage rack
– for providers: check daily for items remaining, when number of items remaining reaches designated minimum, replenish with required number of full containers
Two-Bin system
Start with two full bins of each kind of item
– when one bin is emptied, place an order for another bin to replenish it
– by the time the order arrives, the second bin should almost be empty
More rules for kanban operations
– A card is attached to every container
– each operation produces/replenish is only the quantity specified on the card
– only non-defective items are sent downstream
– the production process is “smoothed” to achieve level production
Steps for continuous improvement
1) Slowly decrease the number of containers until an interruption occurs
2) Identify source of the interruption
3) Slightly increase the number, eliminate cause of interruption
4) Return to step one
Equation for the number of containers in a buffer (k)
k= (replenishment quantity + safety quantity) / container quantity
Pull will not work when
In general, whenever demand or lead time or variable
– demand is unstable/highly variable
– production process is not level
– too many defectives
– long set ups and frequent breakdowns
Necessary conditions for pull production
- production on demand only
- strive for inventory reduction everywhere
– preventative maintenance program
– quality at the source
– quick set ups
– linked, somewhat synchronous operations
– somewhat level final production schedules
– cooperative effort and teamwork
– local control and visual management
More equations
Reorder point = LT * D
K = (LT*D) / Q or K = (LT*D*(1+x)) / Q or K = (LT+S)*D / Q
Process layout
Advantages
Disadvantages
• process layout: facility is arranged by department, function, or specialty
•Advantages:
-high flexibility can make many products,
-lower equipment costs (low Fixed Costs)
-higher work motivation, greater work variety, great employee involvement
-good for low volume, high variety output
• disadvantages:
– higher labor expenses and less efficient processes & equipment (high Variable Costs)
– higher inventory&material handling costs
- difficulty in scheduling and coordinating operations
Product layout
Advantages
Disadvantages
• product layout: arranged according to steps in a process, usually to make one product
• Advantages:
– low unit cost to the highway efficient equipment, booking processing, lower rates
– operations are easy to schedule and control
– little inventory, good for high-volume, low or no variety output
• Disadvantages:
– little or no flexibility, can only make one product
– labor problems: little work variety, boredom, low worker motivation
– higher equipment costs
– task interdependencies: when one task stops, all stop