Exam 1 - Definitions Flashcards

1
Q

A task or process to be accomplished in a set period of time, working towards longer project goal.

A

Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Ordered link between two activities representing the order of execution.

A

Activity Relationship

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Four types of activity relationship;

A

FS - Finish to Start (MOST COMMON)
SS - Start to Start
FF - Finish to Finish
SF - Start to Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Activity that is on critical path.

A

Critical Activity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

It is sequence of network activities which add up to longest overall duration, determine shortest time possible to complete project.

A

Critical Path

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

First step in CPM scheduling algorithm calculates each activity’s early start and early finish start.

A

Forward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Calculated earliest date for activities on the network, find latest start and finish dates/float.

A

Backward Pass

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

An algorithm for scheduling a set of project activities. It is commonly used in conjunction with the program evaluation and review technique.

A

Critical Path Analysis

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A chart where activities are presented by bars. Bars length = Activity duration

A

Bar Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Project modeling technique for scheduling a set of project activities. Developed in 1950’s and aims to build a model of project that contains;

  • list of activities
  • time (duration) that each activity will take to complete.
  • logical and points such as milestones
A

Critical Path Method (CPM )Scheduling

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Time based activity chart in which a series of horizontal lines shows amount of work done or production completed in certain periods of time in relation to what was planned

A

Gantt Chart

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Earliest time an activity can start within target

A

Early Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Earliest time an activity can finish within target

A

Early Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Latest possible activity must finish

A

Late Finish

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Latest possible activity must start

A

Late Start

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Amount of time an activity in a project network can be delayed wihtout causing delay to project.

A

Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Difference between the finish date of the last activity on critical path

A

Total Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Amount of time that spans from competition of one previously scheduled activity and extends to point which next scheduled activity is set to begin.

A

Free Float

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

An activity that determines start date and finish date of a following activity

A

Predecessor

20
Q

Task whose start/end date is controlled by the predecessor

A

Successor

21
Q

Schedule delay, successor activity will be delayed with respect to predecessor activity.

A

Lag

22
Q

Example; A lag or delay such as putting 5 days for concrete because cannot stand or work on concrete for 5 days after pour.

A

Positive Lag

23
Q

Drag an item back

A

Negative Lag

24
Q

Logic error where activity attempts to start prior to a preceding activity.

A

Loop

25
Q

Project activity without a predecessor or successor activity

A

Open Ends

26
Q

Set of dates and cost frozen at start of project and used for performance evaluation as project progresses.

A

Base Line

27
Q

Percentage value between 0 and 100 that indicates partial completeness of an activity, project, etc.

A

Percent Complete

28
Q

Tracking overall progress of with plan, for costs, man hours, materials, etc. Can use monthly.

A

S - Curve

29
Q

Restriction on an activity’s start or finish date in scheduling software used to impose deadlines or delay activities.

A

Date Constraint

30
Q

Event to mark specific point in time along a project timeline. These points signal anchors and also, start and end date milestones do not impact project duration.

A

Milestone

31
Q

Labor can be directly related/allocated to the output of a productive account. Indirect is not related to output. Labor employed directly by owner or main contractor.

A

Direct Labor

32
Q

Costs that are not directly accountable to an activity or work package, costs can be fixed or variable. Costs which are not directly related to production.

A

Indirects

33
Q

Bar chart, estimated or actual manpower, costs expanded.

A

Histogram

34
Q

4 Types of Schedules

A

1) Master
2) Milestones
3) Look Ahead Schedules
4) Weekly Schedule

35
Q

Subset of a project is ……

A

Work Package

36
Q

United States federal law that establishes the requirement for paying the local prevailing wages on public works projects for laborers and mechanics

A

Davis Bacon Act

37
Q

We know equipment will come in and work around it, does NOT control schedule.

A

Material Driven

38
Q

Schedule locked in and material needed, build our whole entire schedule around that piece of equipment that is constrained and be delivered in a month or so….

A

Material Constrain

39
Q

Not part of manpower loaded schedule

A

Indirect Costs

40
Q

Essentially tracking overall cost at job through the schedule. Typically involves the simultaneous development of a project estimate, using various estimating tools, and a projectschedule using the critical path methodology.

A

Cost Loaded Schedule

41
Q

Tracking all direct manpower utilized on the job site. MANPOWER DISTRIBUTION OVER TIME.

A

Manpower Loaded Schedule

42
Q

Indirect costs and ______ _______ are basically the same thing.

A

General Conditions

43
Q

Three Major thing for schedule?

A

Material, Equipment, Labor

44
Q

Examples of indirect craft labor?

A
  • water distribution
  • trash - clean up
  • fire watch
  • equipment spotters
  • crossing guards
45
Q

What determines size of crew?

A
  • Man-hours allotted tasks
  • Duration
  • Work area sized and amount of work
  • Historical Info
46
Q

What is the right crew mix?

A
  • Duration of activity can play big factor
  • Workforce experience level
  • Higher the skill level then higher quality
47
Q

typically include supplementary wage and nonwage payments or benefits you receive from your employer

A

Fringes