EVM Formulas Flashcards
1
Q
Cost Variance
A
CV = EV - AC
Negative values indicate over budget
2
Q
Cost Performance Index
A
CPI = EV / AC
This value should be 1 and over for projects under budget.
3
Q
Schedule Variance
A
SV = EV - PV
Negative values indicate behind schedule
4
Q
Schedule Performance Index
A
SPI = EV / PV
This value should be 1 and over for a project to be ahead of the schedule.
5
Q
TCPI
A
TCPI = (BAC – EV) / (BAC-AV)
6
Q
Estimate At Completion
A
EAC = BAC / CPI
7
Q
Estimate To Complete
A
ETC = EAC - AC
8
Q
Variance At Completion
A
VAC = BAC - EAC
9
Q
Planned Value
A
PV= Planned % Complete x BAC
10
Q
Earned Value
A
EV= Actual % Complete x BAC