EVM Formulas Flashcards

1
Q

Cost Variance

A

CV = EV - AC

Negative values indicate over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost Performance Index

A

CPI = EV / AC

This value should be 1 and over for projects under budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Variance

A

SV = EV - PV

Negative values indicate behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Performance Index

A

SPI = EV / PV

This value should be 1 and over for a project to be ahead of the schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

TCPI

A

TCPI = (BAC – EV) / (BAC-AV)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Estimate At Completion

A

EAC = BAC / CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate To Complete

A

ETC = EAC - AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Variance At Completion

A

VAC = BAC - EAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planned Value

A

PV= Planned % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Earned Value

A

EV= Actual % Complete x BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly