EVM Flashcards
BAC
Original budget of the project
PV
PV = Planned % Complete x BAC
Planned Value
Amount of money worth of work that should have been done on the project
What did you PLAN
EV
EV = Actual % Complete x BAC
Earned Value
Amount of money worth of work you actually did on the project
What have you EARNED
AC
Actual Cost
Actual Cost
Amount of money you already spent on the project
CV
CV = EV - AC
Cost Variance
What’s EARNED - Current COST
CPI
CPI = EV / AC
Cost Performance Index
EARNED [ACTUAL% * BAC] / ACTUAL
SV
SV = EV - PV
Schedule Variance
SCHEDULE = EARNED - PLANNED
SPI
SPI = EV / PV
Schedule Performance Index
SCHEDULE = EARNED / PLANNED
EAC
EAC = BAC / CPI
Estimate At Completion
FINAL COST EST. = BUDGET / RATE OF SPENDING (CPI)
ETC
ETC = EAC - AC
Estimate To Completion
COST REMAINING = FINAL EST. - CURRENT EST.
VAC
VAC = BAC - EAC
Variance At Completion
TCPI
TCPI = (BAC - EV) /
(BAC - AC)
To-Complete Performance Index [Total CPI]
What is the non-EVM equation:
PERT
Beta
Not EVM
PERT = (O + 4 * R + P) / 6
Optimistic
What is the non-EVM equation:
PERT
Standard Deviation
Not EVM
PERT = (Pessimistic - Optimistic) / 6
What is the non-EVM equation:
PERT
Triangular Distribution
Not EVM
PERT = (O + R + P)/3
What is the non-EVM equation:
Cycle Time
[Agile]
Cycle time = (work in progress) / (througput)
What is the non-EVM equation:
Communication Channels
[Agile]
N(N-1)/2