EVM Flashcards

1
Q

BAC

A

Original budget of the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PV

A

PV = Planned % Complete x BAC

Planned Value

Amount of money worth of work that should have been done on the project
What did you PLAN

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

EV

A

EV = Actual % Complete x BAC

Earned Value

Amount of money worth of work you actually did on the project
What have you EARNED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

AC

A

Actual Cost

Actual Cost

Amount of money you already spent on the project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A

CV = EV - AC

Cost Variance

What’s EARNED - Current COST

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

CPI

A

CPI = EV / AC

Cost Performance Index

EARNED [ACTUAL% * BAC] / ACTUAL

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

SV

A

SV = EV - PV

Schedule Variance

SCHEDULE = EARNED - PLANNED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

SPI

A

SPI = EV / PV

Schedule Performance Index

SCHEDULE = EARNED / PLANNED

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

EAC

A

EAC = BAC / CPI

Estimate At Completion

FINAL COST EST. = BUDGET / RATE OF SPENDING (CPI)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

ETC

A

ETC = EAC - AC

Estimate To Completion

COST REMAINING = FINAL EST. - CURRENT EST.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

VAC

A

VAC = BAC - EAC

Variance At Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

TCPI

A

TCPI = (BAC - EV) /
(BAC - AC)

To-Complete Performance Index [Total CPI]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the non-EVM equation:

PERT

Beta

Not EVM

A

PERT = (O + 4 * R + P) / 6

Optimistic

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is the non-EVM equation:

PERT

Standard Deviation

Not EVM

A

PERT = (Pessimistic - Optimistic) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the non-EVM equation:

PERT

Triangular Distribution

Not EVM

A

PERT = (O + R + P)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the non-EVM equation:

Cycle Time

[Agile]

A

Cycle time = (work in progress) / (througput)

17
Q

What is the non-EVM equation:

Communication Channels

[Agile]