Estimating Methods Flashcards
What are the two methods of single rate estimating?
Functional unit of accommodation
Floor area
Explain functional unit of accommodation
The number of units is counted ( e.g the number of occupants or main furniture objects ) this number is then multiplied by the cost per unit. This data will then provide a total estimated cost.
What is the formula for functional unit of accommodation?
Number of units x cost range ( per unit ) = total cost
Name 3 advantages of functional unit of accommodation
Any 3 of the following:
Quick and simple
Can be done without drawings and specifications
No take-off needed
Useful for buildings where standard size units occupy it
Name 3 disadvantages of functional unit of accommodation
Unreliable
Large deviation from accurate value
It is not based on drawings or specifications
What is floor area estimating?
The floor area of the proposed building is measured at each floor level. This method is ideal for early budgeting purposes
What is the formula for floor area estimating?
Floor area x cost range = total cost
Name 3 advantages of floor area estimating
Any 3 from the following:
Quick method
Easy to employ, as rules for calculations are simpler
Directly relates to accommodation
Allows comparison of different designs
Meaningful to both client and architect as it uses m2
Allows comparison between buildings that differ in shape and size
Name 1 disadvantage of floor area estimating
Fails to take account of any variation in the plan, shape or stored height
What are the 3 methods of multiple rate estimating?
Elemental cost planning
Approximate estimating
Bill of quantities
What is elemental cost planning estimating? Including the 2 methods
The proposed building is split into a series of elements. E.g foundations, walls, roof etc. the two methods are;
Approximate quantity of each element, unit rate
Using the total cost of a similar building, and applying it to the measure of the new building
What procurement method is elemental cost planning usually used for?
Design and build
Name 3 advantages of elemental cost planning estimating
Easy to understand
More accurate
Good for cost planning
Name 1 disadvantage of elemental cost planning estimating
More work and effort is required in preparing this method
Name 3 ways of selecting and using cost data
Any 3 from the following:
Using own historical data
National historical data
Price books (SPONS & BCIS)
Specialist sub-contractors, quotes etc
Building magazines
Websites