estimating Flashcards

1
Q

what are the owners estimates and when are they performed

A
  1. conceptual estimate - before bid
  2. alternative design estimate - before bid
  3. owners engineers estimate - before bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

what are the contractors estimates?

A
  1. contractors bid estimate - before bid
  2. alternative construction methods - post bid
  3. changes/claims estimate - post bid
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

conceptual estimate

A

purpose: takeoff to get an initial idea, decide whether to proceed /w/ project
- feasability study
- hires A/E to provide order of magnitude estimate of cost
- they only know the general scope, very rough cost
- bldg - sq ft, road - km

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

alternative design estimate

A

purpose: exploring alternative options to find the most feasable
- A/E - $ based on previous experience
- rely on bid abstracts for cost info
- QTO
- at the end of the process the owner decides on an option

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

owners engineers estimate

A

purpose: a more accurate estimate developed by the owners engineer, cost against which to evaluate bids
- QTO
- past experience and bid abstracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

contractors bid estimate

A

purpose: to put forward a bid
- QTO (detailed)
- based on in-house cost data base (records)
- consider cnstrctn methods
- determines whether they make money, so it must be accurate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

alternative cnstrctn methods

A

purpose: consider alternative construction methods to complete the project in order to maximize profit
- has been awarded job
- now, detailed review of how job is priced
- is there a better way to do the work? better cnstrcn method? - maximize profit
- the innovative contractor can save money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

changes/claims estimate

A
  • estimate the cost for additional work outside the scope of the original contract
  • when a change order or claim is filed, the contractor has to determine how much he should charge
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

direct cost

A

any cost that can be associate with a discreet, physical part of a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

indirect cost

A

any cost that cannot be associated with a discreet, physical part of a construction project

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

bid formats - schedule of bid items bid vs lump sum bid

A
  • includes the cost of bid items, and can also include lump sum
  • lump sum includes lump sum only
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

what are the 7 horizontal categories of cost, and why are there 7 categories

A
  • Labour (L)
  • Permanent Materials (PM)
  • expendable materials (EM)
  • subcontractors (s)
  • equipment operating expense (EOE)
  • repair and service labor (RL)
  • rental, depreciation, write-off (R)

to seperate based on risk. by seeing amounts in each category, the contractor can get a handle on how risky the project is

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

why are PM and EM broken up

A

to have a high risk and low risk material category

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

PM

A

any material falling within the neat lines of a DWG

Low Risk
- Not productivity related
- Can be accurately determined and is therefore not volatile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EM

A

any material falling outside of the neat lines on dwgs, plus temporary structures ie flasework, formwork, erosion ctrl

Less risk than direct labor but still potentially High Risk

 Not particularly productivity related but can be very difficult to determine accurately, so always risky
 In some projects can be highly volatile

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

subs

A
  • coverered by performance bond, low risk
17
Q

EOE

A
  • FOG (fuel, oil, grease)
  • tires
  • small repair parts
  • 3rd party overhaul

Highly related to kind of work being performed and can be fairly volatile on equipment intensive jobs

18
Q

RL

A

Shares risk attributes of direct Labor but normally will not be as high a cost

19
Q

R

A

Highly dependent on the type of construction project and
on the contractor’s business philosophy and equipment policy
 In-house rental
 Third party rental
 Operated and Maintained (O&M rental)

 With the exception of O&M rental this cost element is not
particularly volatile

 O&M rental, however is highly productivity related and is just as volatile as direct labor

20
Q

L

A

Highest Risk Cost Element
 Highly productivity related

21
Q

risk ranking from high risk to low risk

A
  • L, RL, O&M
  • EM
  • EOE, R
  • S, PM
22
Q

soft subs

A
  • if a sub has not bonded you are taking on the risk
  • a sub you know has a good rep, but no bond and also the lowest bid
  • confident work will get done, but still want to cover the risk
  • difference to next highest bidder
23
Q

productivity hedge

A

incase of an over estimation of productivity

24
Q

event

A

cover the possibility of a specific event like a strike

25
Q

7 vertical categories of cost

A

direct costs
indirect costs
escalation (labour, material, equipment) - accounting for costs increasing over time
interest - from financing, eg new equipment.
contingency - for unnexpected costs
markup
bond - bond premium, payed to surety. bond costs money

26
Q

5 categories of indirect cost and 2 examples for each

A

salaried payroll - supervisors
time related overhead - rental of office trailer
non-time related overhead (a one time expense) - office furniture
insuarance and taxes - insurance and taxes
construction plant in and out - installing utilities

27
Q

labour premium

A

(hrs paid-hrs worked)/hrs worked

28
Q

overtime

A

a/b/c

a = rate on weekdays, applies only to hrs in excess of normal shift
b = rate on saturdays, applies to PAID shift hrs plus time over wrkd hours
c = rate on sundays and holidays, applies to PAID shift hrs plus time over wrkd hours

any hours on weekend are overtime