Estimating Flashcards
What is direct cost?
Anything that has a discrete physical cost associated with the project
What is indirect cost?
Anything that does not have a discrete physical cost associated with the project
What are the 6 levels estimates?
1) Conceptual Estimate project (feasibility studies)
2) Estimate to Evaluate Alternate Design
3) Owner’s Engineer’s Estimate
4) Contractor’s Bid Estimate
5) Alternative Construction Methods Estimate
6) Change Orders or Claim Estimate
What is conceptual estimate?
owner’s general scope of the project
↳ used for a broad estimate of the project
What is estimate to evaluate alternate designs?
Estimates based on past projects with similar scopes
↳ uses unit prices and rough quantifications of units
What is owner’s engineer’s estimate?
- The estimate is given after the design is 80 -90% completed
- Based on quantity takeoff
- Relays on past bid abstracts
- Will likely not consider construction methods
What is contractor’s bid estimate?
- Most detailed out of all the estimates
- Based on the contractor’s Quantity takeoff (QTO)
- Will consider construction methods
- based on contractor’s detailed cost record
What is alternative construction methods estimate?
- identify a cheaper way of getting the job done
- the goal is to maximize profit
What is change orders or claim estimate?
Estimate for change orders
What are the 7 cost categories?
- Labour (L)
- Permanent Materials (PM)
- Expendable Materials (EM)
- Subcontracts (S)
- Equipment Operating Expense (EOE)
- Repair and Service Labor (RL)
- Rental (R)
- Operated and Maintained (O&M rental)
What level of risk does labour have and why?
Highest risk cost element
- Direct labour is the most volatile
- Highly productivity-related
- The most difficult cost to estimate and control during project performance
What level of risk does permanent material have and why?
Low Risk
- Not productivity related
- Can be accurately determined and is therefore not volatile
What level of risk does expendable material have and why?
Less risk than direct labour but still potentially high risk
- Not particularly productivity-related but can be very difficult to determine accurately and are thus always volatile to some extent
- In some projects can be highly volatile
What level of risk does subcontracts have and why?
Low Risk if covered by performance bond
- Highly productivity-related from subcontractor’s point of view
- But, not productivity-related from prime contractor’s point of view provided that the subcontractor’s quote entered in the prime contractor’s bid estimate is secured by a 100% performance bond
What level of risk does equipment operating expense have and why?
Not necessarily risky but can be if operating under harsh conditions
Highly related to the kind of work being performed and can be fairly volatile on equipment intensive jobs