Eric's ip exam Flashcards
Which precaution is taken when removing insulation from piping?
a.
Wet it down with water.
b.
Wrap it in plastic.
c.
Cover surface area for falling debris.
d.
Positively identify the material.
What is applied to a strap wrench to prevent it from slipping?
a.
Pumice
b.
Resin
c.
Sandpaper
d.
Wax
What is the minimum length of 2 inch by 10 inch wooden planks required for a 2.4 meter (8 feet) long scaffold platform?
a.
2.4 meters (8 feet)
b.
2.7 meters (9 feet)
c.
2.6 meters (8 feet 6 inches)
d.
2.9 meters (9 feet 6 inches)
Which hand signal is indicated in the following image?
a.
Lower the boom slowly.
b.
Lower the load slowly.
c.
Raise the boom slowly.
d.
Raise the load slowly.
Given the following information:
Labor requirements are being estimated for the installation if the piping for in-floor heating
The floor space measures 9 meters by 10 meters (25 feet by 30 feet)
15 square meters (125 square feet) per hour can be completed per person.
How long will it take two tradespersons to complete this job?
a.
6 hours
b.
3 hours
c.
2 hours
d.
8 hours
How is pipe for a medical gas system stored?
a.
With capped ends and separated from other materials
b.
With piping capped and placed in a climate controlled space away from any temperature fluctuations
c.
Placed in an area that is out of direct sunlight.
d.
With caps removed and all pipes wrapped using heavy polyethylene
Which two tees are required for this piping installation?
a.
1 - 200mm x 150mm x 150mm
1 - 200mm x 200mm x 100mm
b.
1 - 200mm x 200mm x 150mm
1 - 200mm x 100mm x 100mm
c.
1 - 200mm x 200mm x 150mm
1 - 200mm x 150mm x 100mm
d.
1 - 200mm x 200mm x 150mm
1 - 200mm x 200mm x 100mm
Refer to the following image to answer the question.
What is the distance of dimension “A” from the finished floor to the center of the drain?
a.
533mm (21 inches)
b.
545mm (21 1/2 inches)
c.
558mm (22 inches)
d.
629mm (23 1/2 inches)
Refer to the Plan view image below to answer the question.
X = 18.3meters (60 feet)
Y = 2.5 meters (8 feet)
Z = 2.13 meters (7 feet)
What is the minimum number of hangers required inside the room for the horizontal 4 inch steel pipe when there is support at each end of the pipe as it goes through the wall? (not including ends)
a.
7
b.
8
c.
10
d.
9
Refer to the image provided to answer the question.
Which length of copper tube is required to bend the expansion loop from point A to point B if the gain is 6mm (1/4 inch) per bend?
a.
1246mm (49 inches)
b.
1295mm (51 inches)
c.
1219mm (48 inches)
d.
1270mm (50 inches)
What is the procedure used to assemble a compression joint on copper tubing?
a.
Cut, slide nut and ferrule over tubing, ream, push tubing completely into socket, then tighten nut.
b.
Cut, bevel, slide nut and ferrule over tubing, push tubing completely into socket, then tighten nut
c.
Cut, ream, slide nut and ferrule over tubing, push tubing completely in socket, then tighten nut.
d.
Cut, ream, slide nut over tubing, push tubing completely into socket, then tighten nut.
What is the procedure for brazing a copper tube or tubing joint?
a.
Remove oxidization from pipe and fittings, heat to a minimum or 540 degrees C (1000 degrees F), then apply brazing rod.
b.
Remove oxidization from pipe and fittings, heat to a minimum or 260 degrees C (500 degrees F), then apply brazing rod.
c.
Remove oxidization from pipe and fittings, heat to a minimum or 260 degrees C (500 degrees F), then apply solder.
d.
Remove oxidization from pipe and fittings, heat to a minimum or 540 degrees C (1000 degrees F), then apply solder.
What is the procedure to join PEX pipe using an expanding tool after the pipe has been cut square?
a.
Slide fitting into pipe, push ring over pipe, then expand pipe while secure.
b.
Slide ring over pipe, expand pipe with tool while turning head, then insert fitting.
c.
Expand ring with tool, insert fitting while turning pipe, then crimp.
d.
Expand pipe with tool, push ring over pipe, then insert fitting.
A large diameter, new hub and spigot gasket plastic pipe is being installed. Which steps are required?
a.
Align pipe sections, lubricate both ends, then pull piping sections together.
b.
Align pipe sections, pull piping sections together, then silicone the joints.
c.
Align pipe sections, apply silicone to hub end, then pull piping sections together.
d.
Align pipe sections, lubricate hub end, then twist piping sections together.
How is a tight or loose thread corrected?
a.
By applying additional cutting oil.
b.
By adjusting the dies.
c.
By re-reaming the pipe.
d.
By applying teflon tape
Refer to the image below to answer the question.
What is installed between the flanges?
a.
Slip on Flange
b.
Socket Weld Flange
c.
Spectacle Blind
d.
Companion Flange
What is the change in direction in a cast iron 1/8 bend?
a.
45 degrees
b.
90 degrees
c.
60 degrees
d.
22 1/2 degrees
What is the procedure for cutting the pipe when inserting an MJ wye into a cast iron stack?
a.
Measure the length of the pipe, select tube cutter, then cut pipe 1/4 to 1/2 longer than the wye.
b.
Measure the length of the wye, select snap cutter, then cut pipe 1/4 to 1/2 inch longer than the wye.
c.
Measure the length of the pipe, select grinder, then cut the pipe 1/2 to 1 inch shorter that the wye.
d.
Measure the length of the wye, select hacksaw, then cut pipe to the same length as the wye.
Which type of coupling is used when joining two field-cut lengths of glass pipe together?
a.
Fusion to fusion
b.
Bead to bead
c.
Plain to plain.
d.
Bead to plain
What is the size of a storm building sewer (slope of 1:100) that has drainage from a 27 meter by 22 meter flat roof with rainfall intensity or 25mm per 15 minutes?
a.
4 inch
b.
8 inch
c.
6 inch
d.
5 inch
An air conditioning fixture has a continuous flow of 5 liters per second. What is the hydraulic load?
a.
167.3FU
b.
3600FU
c.
158.5FU
d.
126.8FU
The total length of a sanitary building sewer is 100 feet and the total fall is 2 feet 1 inch . What is the grade of the sewer per foot?
a.
1/4 inch per foot
b.
1/8 inch per foot
c.
1/2 inch per foot
d.
3/8 inch per foot
Which type of support is used for a nominally horizontal pipe installed underground on a base that is not firm and continuous?
a.
Hangers supported by a structural slab.
b.
Sand.
c.
Wood blocking.
d.
Hangers supported by wood blocking under a slab.
What is the minimum size for the inlet pipe connected to a septic tank?
a.
6 inch
b.
2 inch
c.
3 inch
d.
4 inch
Which test is used to determine the suitability of the soil for a treatment field?
a.
Permeation
b.
Saturation
c.
Percolation
d.
Siphon
What is the volume of effluent in an effluent chamber if the width is 0.9 meters (3 feet), the working depth is 1.8 meters (6 feet) and the length is 1.8 meters (6 feet)?
a.
2.92 cubic meters (108 cubic feet)
b.
3.24 cubic meters (36 cubic feet)
c.
1.62 cubic meters (18 cubic feet)
d.
4.50 cubic meters (15 cubic feet)
For a septic field. What is the primary purpose of the washed gravel?
a.
To provide air space allowing aerobic bacterial action to take place.
b.
To provide support for weeping lateral.
c.
To allow ground water to dissipate before contacting effluent
d.
To keep lateral dry after effluent flushing.
What is the minimum size vent required for a sewage sump with a 6 inch inlet?
a.
5 inch
b.
2 inch
c.
3 inch
d.
4 inch
Refer to the image to answer the question.
What is the minimum size and type of vent required?
a.
1 1/4 inch individual and continuous
b.
1 1/4 inch continuous vent
c.
1 1/2 inch continuous vent
d.
1 1/2 inch individual and continuous
What is the maximum number of liters allowed on a 4-inch combined building sewer at 2% grade?
a.
180L
b.
390L
c.
10800L
d.
5970L
What is the minimum size of a floor drain that is permitted to be in a private residence?
a.
2 inch
b.
4 inch
c.
3 inch
d.
1 1/2 inch
Refer to the image to answer the question.
What is the minimum size of the wye?
a.
4 inch x 4 inch x 3 inch
b.
4 inch x 3 inch x 4 inch
c.
3 inch x 3 inch x 3 inch
d.
4 inch x 4 inch x 4 inch
What is the minimum size storm building drain for a continuous discharge of 5 L/s at a grade of 1:50?
a.
4 inch
b.
6 inch
c.
5 inch
d.
3 inch
Item X is found in a twelve story building. What is the size and name of item X?
a.
3 inch offset relief vent
b.
3 inch yoke vent
c.
2 inch yoke vent
d.
2 inch offset relief vent
What’s the minimum trap-arm length of a shower drain with a flow rate of 15 LPM?
a.
18 inch
b.
6 inch
c.
4 inch
d.
2 inch
When may a floor drain be connected to a storm drainage system?
a.
If the building drain is not in the area.
b.
If the floor drain receives only clear water waste.
c.
If the building is not served by a building drain.
d.
If the floor drains are in the boiler room.
What is the maximum temperature of effluent allowed to discharge into the drainage system?
a.
39 C
b.
49 C
c.
99 C
d.
75 C
Where is a clean-out located to serve a running trap?
a.
Both downstream and upstream of every running trap.
b.
Upstream side and directly over every running trap.
c.
The nearest stack upstream of the running trap.
d.
Downstream side and directly over every running trap.
What is the rod reading at point A?
a.
1.66 feet
b.
0.66 feet
c.
6.065 feet
d.
6.61 feet
Find the depth of the pipe invert at dimension X from the figure.
a.
1.90 m
b.
1.95 m
c.
2.4 m
d.
2.0 m
What is the number of flow control roof drains required for a 45 meter by 90 meter roof?
a.
5
b.
4
c.
6
d.
3