Equipment Identification Flashcards

1
Q

There are ? steps that are common to the installation of all substation equipment.

A

7

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The minimum separation between bare live conductors in a substation (phase-to-phase) for 69 kilovolts is ? .

A

31”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The minimum clearance for 115 kilovolts from a live conductor to the substation lattice structure is ? .

A

42”

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Sulfur hexafluoride (SF6) gas is a common arc quenching medium used in new substation ? .

A

Circuit Breakers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

SF6 gas ? and will displace the air at the bottom of a confined space.

A

is heavier than air

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Substation breakers are often defined by their ? and their type of operating mechanism.

A

insulating medium

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Substation circuit breakers can be operated by ? or ? controls.

A

AC/DC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In new substations of 500 kilovolts, individual single-phase transformers are used because 3-phase transformers at these voltages are extremely large and expensive.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Disconnects in a substation cannot be used as grounding devices.

A

False

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Post insulators found in modern substations are normally porcelain or polymeric.

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Step regulators normally provide 5% or ? regulation.

A

10%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The purpose of installing capacitors in a substation is to reduce ? .

A

line losses

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

After switching a substation capacitor, wait at least ? minutes before applying a ground.

A

5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

The reactor used to counter phase-to-ground capacitance is connected phase-to-ground and is called a(n) ? reactor.

A

Shunt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

The most common type of battery used for direct current power in a substation is the ? cell.

A

lead-acid

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In substation metering, a VT and a PT are two different types of instrument transformers.

A

false

17
Q

A substation ? is used on primary high voltage lines and buses to produce a lower voltage that is an exact fractional representation of the primary voltage.

A

coupling capacitor

18
Q

The most common type of substation is called a(n) ? -insulated substation.

A

air

19
Q

An electrical line inside a substation yard made out of an aluminum-alloy pipe is called a ? .

A

bus

20
Q

A(n) ? is used in a substation to filter out high-frequency communication signals on the power conductors.

A

wave trap

21
Q

A thermography (infrared) survey of a substation will point out any connections, splices, and switch components that are hot.

A

True