Enterprise & Regulatory Reform Act 2013 Flashcards

1
Q

Under the act, what was Conservation Area Consent replaced by?

A

Planning Permission

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

When may a certificate of immunity from listing be obtained?

A

Anytime. Previously it was when a planning submission was submitted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a certificate of immunity from listing?

A

A guarantee a building will be immune from listing for 5 years. LPA are unable to serve a building preservation notice within this time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If there is a breach of planning requirements within a conservation area, what is the time limit on enforcement action?

A

No time limit

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are Heritage Partnership Agreements?

A

It is an agreement or management framework in which Listed Building Consent can be granted for specified works (excluding demolition), rather than a series of individual consents

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What are Building Consent Order?

A

Set up by the LPA or Secretary of State for Culture Media and Sport, under which works of a type described in the order (excl. demolition) will not require Listed Building Consent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a certificate of Lawfulness?

A

Confirms that works described in it do not affect the character of a listed building, and therefore do not require consent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How long is a Certificate of Lawfulness valid for?

A

10 years

How well did you know this?
1
Not at all
2
3
4
5
Perfectly