Element 1 - Foundation in Health and Safety Flashcards
CDM 2015
What are a domestic clients duties under cdm 15 with 1 contractor?
The clients duties automatically transfer to the contractor.
What are a domestic clients duty with more than 1 contractor?
Principle contractor takes on clients duties.
If client does not select a pc then it falls to the contractor responsible for the construction phase.
Can also be transferred to the pd if there is s written agreement between the pd and client.
Commercial client duties with 1 contractor?
Provide pre construction information to designers and contractors.
Notify hse about project if required by completing a form 10.
Ensure construction phase plan prepared.
Arrangement for welfare facilities.
Arrangements for construction to be safely carried out.
Commercial client duties if more than 1 contractor
Appoint pc and pd ensuring they carry out their duties.
Ensure pd produces health and safety file.
Update, maintain and keep the health and safety file.
Principal designer duties
Plan, manage, monitor and coordinate pre construction phase.
Provide relevant information on planning, managing and monitoring to pc.
Prepare h and s file staring during pre construction phase.
Coordinate h and s during pre construction phase.
Principal contractor
Prepare construction phase plan
Provide pd with information for h and s file
Liaise with pd
Ensure coordination of contractors
Ensure suitable site induction given to every worker
What is in a h and s plan
Welfare facilities and 1st aid
Site rules
Fire and emg procedures
Site induction
Site security
Pre construction information - 5 points
Description of the project
Clients considerations and management requirements
Environmental restrictions and existing on site risks
Significant design and construction hazards
Health and safety file
Construction phase health and safety plan - 4 points
Description of the project
Management of the work
Arrangements for controlling significant site risks
Health and safety file
Health and safety file - 5 points
Description of work
Hazardous materials used
Marking of services
Drawing of the structure
Residual hazards