Earned Value Management Formulas Flashcards
EV [Earned Value]
also
BCWP [Budgeted Cost of Work Performed]
EV = % Complete * BAC
CV [Cost Variance]
CV = EV - AC
Positive Value ⇒ Good
SV [Schedule Variance]
SV = EV - PV
Positive Value ⇒ Good
CPI [Cost Performance Index]
CPI = EV / AC
Value > 1 ⇒ Good
SPI [Schedule Performance Index]
SPI = EV / PV
Value > 1 ⇒ Good
EAC (1) [Estimate at Completion]
EAC (1) = BAC / CPI
Bigger Value ⇒ Good
EAC (2) [Estimate at Completion]
EAC (2) = BAC + AC - EV
Bigger Value ⇒ Good
EAC (3) [Estimate at Completion]
EAC (3) = new_estimate + AC
Bigger Value ⇒ Good
EAC (4) [Estimate at Completion]
EAC (4) = AC + (BAC - EV) / (CPI * SPI)
Bigger Value ⇒ Good
ETC [Estimate to Completion]
ETC = EAC - AC
Smaller Value ⇒ Good
VAC [Variance at Completion]
VAC = BAC - EAC
Positive Value ⇒ Good
TCPI [To-Complete Performance Index]
TCPI = (BAC - EV) / (BAC - AC)
Value < 1 ⇒ Good