Earned Value Management Formulas Flashcards

1
Q

(AC)

A

Actual Cost- What the project has spent so far.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

(BAC)

A

Budget at Completion- What the project budget is.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

(CPI)

A

Cost Performance Index- shows the overall cost efficiency of a project.

Equation: CPI= EV/AC

If > 1 under budget
If < 1 over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

(CV)

A

Cost Variance- the difference between EV and AC.

Equation: EV-AC=CV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

(EAC)

A

Estimate at Completion standard formula-
Forecasts final project costs based on current performance.

Equation: EAC=BAC/CPI

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

(EV)

A

Earned Value- What the project is worth.

Equation: Percentage Completed * BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

(PV)

A

Planned Value - What the project should be worth.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

(SPI)

A

Schedule Performance Index- shows overall schedule adherence.

Equation: SPI=EV/PV

If > 1 ahead of schedule
If < 1 behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

(SV)

A

Schedule Variance- the difference between EV and PV.

Equation: EV-PV=SV

\+ = ahead of schedule
- = behind schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

(VAC)

A

Variance at Completion- projection of being over or under budget based on current performance.

Equation: BAC-EAC=VAC

If + = under budget
If - = over budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

EAC CPI and SPI affect remainder of project

A

Forecasts final project costs based on current performance.

Equation: AC +[BAC-EV/(CPI*SPI)]

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

EAC future work at planned cost formula

A

Forecast final project cost based on current performance.

Equation: AC + BAC - EV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC initial cost estimates flawed

A

Forecasts final project costs based on current performance.

Equation: AC + estimate for remainder of project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Estimate to Completion

A

Predict how much more the remainder of the project will cost.

Equation: ETC= EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

TCPI utilizing BAC

A

Predicts likelihood of reaching BAC

Equation: (BAC-EV)/(BAC-AC)

If >1 harder to complete and meet BAC
If <1 easier to complete and meet BAC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

TCPI utilizing EAC

A

Predicts likelihood of reaching EAC.

Equation: (BAC-EV)/(EAC-AC)

If >1 harder to complete and meet EAC
If < 1 easier to complete and meet EAC