Ladders and scaffolding
a stairway must be provided to each new floor before work starts on that level true or false ?
true
temporary access ramps must be at least _____ wide with a max slope of ________
20in and 1:5
max spacing of cleats on a sloped ramp is
400mm
walkways must be a minimum of ______ wide
500mm
temporary stairs require hand rails when
there are more than 4 risers
using part 4 of the O.H.S the top rails must be able to
withstand a point load of 125lbs in any direction, span no more than 8ft, or 10 ft for scaffold, and be between 40 - 44” above the travel and work surfaces
what’s the minimum width of a wooden scaffold plank?
235mm or 9 1/4”
what’s the minimum height of a guardrail
40in
above what height does a scaffold require a guardrail
10ft
what’s the max that a scaffold plan can project beyond its support
12”
what’s the max span for a wooden guardrail?
up to 8ft for 2x4 and up to 10 ft for 2x6
what’s the max slope, vertical to horizontal, that’s allowed for a work platform
1:5
what’s the max gap allowed under a toeboard
1/2 “
what’s the min width allowed for a scaffold work platform?
2 plank widths
what’s the min amount that a scaffold plank may project beyond its supports
150mm or 6in
what’s the max spacing allowed for supports or scaffold planks of the scaffold is to be used by a bricklayer?
7ft or 2100mm
the type of nail used in the construction of wooden scaffold is
duplex
best length of nail to use if the ledge is 19mm is
2 1/4
best location for the 38x140mm bearer may have in light duty work is
5ft or 1500mm