Domain: Contracts Flashcards
The A/E is responsible for:
* being generally familiar with the progress of the work
* determining if the work is being provided according to the contract documents
The A/E is responsible for observing what?
The quality and protecting the owner from defects in the work.
The A/E has the authority to ___.
* reject non-conforming work
* DOES NOT have the authority to STOP work of the contractor
Basic lines of communication in AIA general conditions include the following:
* owner-contract: through A/E
* to consultants: through A/E
* to subcontractors and suppliers: through contractor
* to separate contractor: through owner, const manager or coordinating contractor
What provides a forum in which matters pertinent to the timely completion of the work can be discussed?
progress meetings
Progress meetings involving the A/E and contractor typically occur when?
prior to submission of an application for payment (or when requested by a member of the project team)
Who would schedule a meeting to address internal management, organization, operation, coordination, and safety issues?
contractor
Who would schedule meetings to address coordination with separate contractors, select colors, or coordinate move-in plans?
Owner
Who would schedule meetings to address coordination between the contractor and the A/E?
a design-builder
Special meetings scheduled for a specific purpose usually (DO or DO NOT) require attendance of the entire team?
do NOT
The owner is obliged to provide information about what for the contractor to rely on?
* physical characteristics
* legal limits
* utility locations
The owner is responsible for what?
work performed by the owner or separate contractors that will affect the work of the contractor performing subsequent dependent work may be required to correct deficiencies reported by the contractor affected
When are contract modifications required?
whenever a change will modify the contract documents, whether or not the change will affect the time or cost.
When are change orders used to modify the contract documents?
when COST, TIME or BOTH are affected
What type of contract modification is issued when neither time nor cost are affected?
minor change in the work
If the A/E is in agreement with the proposed change, cost, and time revisions submitted by the contractor, what will be issued?
a change order
If the A/E is not in agreement with the contractor’s proposal, what will be issued?
a change DIRECTIVE
True or False:
Contract modifications are not required when an RFI does not affect cost or time.
True
What describes the conditions under which modifications to the contract documents will be allowed?
conditions of the contract and Division 01
When might contract document modifications be necessary?
* intent of the documents is not reasonably infer-able and corrections are required to eliminate errors, omissions, discrepancies or design deficiencies
* unknown conditions
* owners requirements change (additions/deletions)
* changes in the requirements after issued permit
* time period between bid proposal accepted and contract execution is too long
* interpretations of regulations by AHJs
* a spec’d product isn’t available anymore
* new product offers cost savings
* new info about a spec’d product becomes available
* adjustment in contract sum occurs (due to actual cost and specified allowance)
* estimated quantity of work for unit price is changed
Who can initiate a request for a contract modifications?
owner, contractor or A/E
What methods are available to request and make contract document modifications to the project?
* written requests for change
* minor changes
* change directives
* change orders
What is the difference between written requests for change, minor changes in the work, change directives, and change orders?
* Written requests for change are not a directive to make a change.
* Minor changes do not affect contract sum or time.
* Change Directives direct change to be made; contract sum or time adjusted at a later date in the form of a change order.
* Change Orders direct change to be made with contract sum or time adjustments stipulated.
What are examples of written requests for change?
* proposal request
* change order request
* request for subsitution
What are examples of minor changes in the work?
* AIA “Supplemental Instructions” (SI)
* EJCDC “Field Order”
* EJCDC “Written Interpretation or Clarifications”
What are examples of change directives?
* AIA “Construction Change Directive
* EJCDC “Work Change Directive”
Who usually prepares a proposal request?
A/E
What is a proposal request?
A written document that describes a proposed change to the project, and includes the reasons for the proposed change.
Usually completed by the A/E, and sent to the contractor for evaluation of how the proposed change will affect the contract sum and time.
Why does the contractor review a proposal request?
The proposal request is sent to the contractor for evaluation of how the proposed change will affect the contract sum and time.
The proposal request must include enough detail for the contractor to accurately estimate the cost and time impact of the proposed change on the project.
True or False:
A proposal request is a change order or a directive to make changes to the project.
False.
True or False:
A change order request may be used by the contractor.
True.
A contractor-initiated change order request should state the reasons for the proposed change along with itemized costs for what?
labor, materials, taxes, subcontracts, bonds, insurance, overhead, profit
Define “minor changes to the project” or “clarifications of the contract documents.”
Instructions or Clarifications not involving adjustment of the contract sum or time.
True or False:
The A/E’s supplemental instruction or field order requires the owner’s and contractor’s signature.
False.
* sum or time is not affected
True or False:
A minor change is initiated by the A/E as a written instruction or order directed to the contractor and is binding on the owner and contractor.
True.
Construction Change Directives and Work Change Directives direct the contractor to make a change to the project prior to what?
owner and contractor agreement upon the proposed changes in contract sum or time
Change directives are prepared by A/E and signed by _____.
A/E and owner
Once the cost or time is agreed upon, the change directive is ____.
incorporated into a change order.
If the proposed adjustment in the contract sum or time is subject to later acceptance or rejection, the contractor ____.
is directed to proceed with the change regardless.
A Change Order authorizes what?
an addition, deletion, or revision to the project in consideration of an adjustment in the contract sum, time, or both.
A principle of most standard general conditions is that _______ _______ has authority to execute a change order.
owner only