Division 6 Flashcards

1
Q

Name two differences between a negotiated bid and a competitive bid

A

A negotiated bid is a privately funded project and invites only one contractor. A competitively bid project can be publicly or privately funded and involves multiple contractors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Why would an owner hire a construction manager as adviser (cma)?

A

This person is hired to assist in project delivery by providing cost estimating, scheduling, and construction contract management services to the owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

List three typical prequalifications an owner may require to restrict the number of contractors to bid on the project

A

Bonding capacity, project experience, and references are examples of this. Other examples include size of firm and experience of personnel

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which project delivery limits the role and responsibilities of the architect during the pre construction phase?

A

Integrated project delivery, or IPD, limits this project team member’s activities in preconstruction.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Who is responsible for cost control in design-build delivery?

A

The contractor is responsible for this but the architect may be responsible for the tracking and controlling of the cost of the architect’s design services.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Which document, placed in a public publication, is used to notify prospective bidders?

A

An advertisement for bid is used in this situation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Who must approve a proposed substitution, and if approved, what is done with the proposal?

A

This kind of proposal must be reviewed by the architect. If approved, it becomes an addendum to be included in the bid documents.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Who is the only party who guarantees by contract all construction cost?

A

The general contractor is the only party who guarantees this.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

At a public bid opening, which two items are announced by the architect after each bid is opened?

A

The two items announced at this time are the written amount of the bid and whether the bidder has submitted the required supporting documentation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What type of insurance protects employees from medical costs and lost income due to work-related injuries?

A

Workers’ compensation applies to these injuries

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

In relation to contract documents, what is an addendum and who prepares it?

A

This document authorizes a revision to the original contract documents before the construction contract has been signed by the owner. It is prepared by the architect.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

According to the AIA document B101, what form of dispute resolution must be tried first before the owner and architect can go to arbitration?

A

The owner and architect may not resort to this until mediation has been tried.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What other construction delivery method is most similar to the construction manager as constructor with regard to the many roles and responsibilities of the architect?

A

With regard to the many roles and responsibilities of the architect, this delivery method is similar to design-bid-build

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

During agency review, what is the architect’s role in an integrated project delivery project?

A

The architect’s role in this phase is limited to working with the permitting authority to show code compliance related to the building information model

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the purpose of the architect’s site observation?

A

This is to observe the progress and quality of the work and keep the owner informed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who determines the number and frequency of the architect’s site observation visits?

A

The architect determines this during the construction administration phase at intervals appropriate to the stage of construction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is the architect not responsible for during the construction of the project?

A

This team member is not required to perform exhaustive or continuous on-site inspections, or to be involved with means or methods of construction, or site safety

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Who pays for additional field testing if the work does not conform with the contract documents?

A

The contractor must pay for this if the work is deficient

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

During construction, why must the architect speak directly to the general contractor and not to the subcontractors?

A

The architect is an agent of the owner and does not have a contractual relationship with this entity

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are two situations in which completed work May have to be uncovered?

A

This may occur if work was covered contrary to the architect’s request or when no specific request was made by the architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Which document defines the lines of communication among the parties during construction administration?

A

AIA document A201, controls this during construction administration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Through whom must the owner and general contractor communicate during construction administration?

A

These two parties must communicate through the architect unless stated otherwise in their agreement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Who will pay for work to be uncovered when the work was covered contrary to the architect’s request?

A

The contractor will pay to uncover work when this situation arises

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

If uncovered work is determines to meet the project requirements, and the architect had not previously requested that it remain uncovered, who pays to uncover and replace the work?

A

The owner will pay to uncover and replace the work in this situation

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Q

Which document requires that certain portions of the work be subject to special inspections?

A

The international building code (IBC) requires special inspection of structural systems, prefabricated items, and certain materials

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
26
Q

Who must evaluate and approve the statement of special inspections?

A

The building official must review this document before special inspections can be incorporated into the project.

27
Q

In which two forms of communication may field reports be distributed?

A

Hard copies and electronic formats may be used to distribute this document after a site observation

28
Q

Who is responsible for organizing a preconstruction conference, and which parties are required to attend?

A

This meeting is organized by the architect and should be attended by the architect, owner, contractor’s personnel (project manager, account executive and superintendent), major subcontractors, and members of the design team (structural, mechanical, electrical, civil and plumbing engineers, and so on, as required).

29
Q

How is “contract time” defined?

A

This period starts at the date established in the agreement and ends at substantial completion

30
Q

Which party has the sole responsibility for the means of construction and the building technique?

A

According to the AIA document A201, these issues are the sole responsibility of the contractor.

31
Q

What two parties should each receive a copy of an architect’s field reports?

A

A copy of each of these architect’s reports must be provided to the owner and contractor

32
Q

What should an architect do if he or she finds an unsafe condition in the project site?

A

If an architect observes such a condition on the project site, he or she must immediately notify the owner and contractor

33
Q

In AIA document A201, what term is given to the architect’s visit to the site?

A

This is called a site observation or site visit

34
Q

Name two differences between a change order and a construction change directive

A

A change order must be approved by the owner, architect, and contractor, and all three parties must agree on the change in cost. The second procedure must mommy be approved by the owner and architect, and without all parties agreeing on the change in cost

35
Q

Which party produces a request for information (RFI)?

A

The contractor, owner, or architect can use this document to request additional information during the construction phase

36
Q

When is the contractor allowed to submit a request for payment of a construction cost directive to the owner on the application for payment?

A

This item can be submitted to the owner for payment upon agreement of the additional cost of the work by the contractor and owner, and completion of the work

37
Q

During the construction phase of the project, the contractor is required to make submittals to the architect. Name four types of submittals.

A

Four types of these are shop drawings, samples, product data, and documents related to sustainability issues

38
Q

Which document is used to record minor changes in the work?

A

This administrative action is recorded by the architect using AIA document G710, architect’s supplemental instructions

39
Q

If the work does not conform with the contract documents, who has the authority to reject the work?

A

The architect has the authority to take this action if work is not in compliance with the contract requirements

40
Q

The architect’s review of the shop drawings does not relieve the constructor of what?

A

The review of this by the architect does not relieve the contractor of conformance with the contract documents

41
Q

During the construction phase, who may make a claim on the project?

A

The owner or the contractor may take this action if they seek an adjustment to the time or payment of money or other relief from the terms of the contract

42
Q

In a shop drawing review, what are the similarities and differences between the “revise and resubmit” and “rejected” designations assigned by the architect?

A

Neither submittals complies either the contract documents as submitted. In the first, the contractor may provide additional information or make corrections and return the submittal to the architect for review. In the second, an item is unsuitable for use in the project and may not be resubmitted to the architect for review.

43
Q

Describe the difference in roles between a mediator and an arbitrator.

A

In mediation, this person facilitates a discuss for the parties to reach their own settlement. In arbitration, this person allows the parties to submit their evidence and hear witness testimony before making a decision or ruling on the matter.

44
Q

What is normally withheld from a progress payment until work is completed?

A

Retainage is normally withheld from this kind of payment.

45
Q

Which party pays for additional nonconformance field testing?

A

This is the only type of field testing paid for by the contractor

46
Q

What information must be included on every progress payment application?

A

This application must include the value of the work completed to date and the value of any stored material.

47
Q

Who pays for work rejected by the architect?

A

Under these circumstances, the additional work must be paid for by the contractor

48
Q

What fee method should be used when the owner has identified a specific set of services?

A

When the owner has done this, the architect can accurately estimate a stipulated sun contract

49
Q

If the owner fails to substantially perform according to contract, what must an architect do to terminate the contract?

A

To take this action in regard to a contract with an owner, an architect must give the owner seven days written notice.

50
Q

What is a change order?

A

This document is prepared by the architect and authorizes a revision to the original contract documents after the construction contract has been signed by the owner

51
Q

When are shop drawings usually prepared?

A

These drawings, schedules, or diagrams are usually prepared after the subcontractor or material supplier has signed a contract with the general contractor

52
Q

What is a mechanic’s lien?

A

This is a claim against a property made by a contractor, material supplier, or architect for unpaid debt of the property owner

53
Q

What type of drawings must the architect keep a log of?

A

Shop drawings require this type of record keeping

54
Q

What is the advantage to the owner of using a construction change directive?

A

This document gives the owner a way to order changes in the work before agreeing to an adjustment to the cost and/or time with the contractor

55
Q

When does the contractors warranty period start?

A

This begins when the project has reached substantial completion

56
Q

What post-construction activity is a prerequisite for LEED certification?

A

Commissioning of the energy systems is a prerequisite for this

57
Q

What activity must take place if the architect determines the project is not substantially complete after a site inspection?

A

The architect must notify the contractor of the work that must be completed to achieve this

58
Q

Why would an architect provide a post-occupancy evaluation free of charge to the owner?

A

This activity provides valuable information to the architect after the owner has occupied the building. It is a good marketing effort by the architect and maintains contact with the owner for potential future work

59
Q

What action may the owner take upon the acceptance of substantial completion by the parties?

A

When this is reached, the owner may move in or utilize the work for its intended purpose

60
Q

For a large, complex building project, who usually hires the commissioning agent?

A

This person is hired by the owner to coordinate the efforts of this post-construction activity

61
Q

What is the next activity after the contractor has completed the punch list?

A

After the contractor has completed this, the next step is for the architect to make an inspection to determine whether the project is substantially complete

62
Q

If a construction claim is made by the contractor, what actions may be taken by the initial decision maker?

A

If the contractor takes this action, the initial decision maker may do any of the following:
Request supporting data
Suggest a solution
Accept the contractor’s assertion
Reject the contractor’s assertion
Notify the parties that a determination cannot be made

63
Q

At the closeout of a project, the contractor typically submits five items to the owner. What are they?

A
The five items typically submitted at this time are:
Warranties and operating manuals
Final payment documents
Record (as-built) drawings
Certificate of occupancy
Extra materials