Discharge of Contracts Flashcards
What are the ways in which a contract may be discharged?
(a) Performance;
(b) Expiry;
(c) Agreement;
(d) Breach; or
(e) Frustration.
What is discharge by expiry?
A contract will expire when it is completed according to its own terms. Contract expiration is often by date ie the parties incorporate a term in the contract which stipulates when the contract comes to an end. For example, the contract provides that the contract will expire 12 months after
the commencement date. A contract can also expire based on the occurrence of an event. For example, a contract may include a term that the supplier is to deliver goods to the buyer within a given time frame and upon delivery the contract comes to an end.
What is discharge by performance?
The entire obligations rule: A contractual obligation is discharged by a complete performance of the obligation. The promisee is entitled to the benefit of complete performance exactly according to the promisor’s ‘undertaking’. A promisor who only performs part of their obligation is not discharged from that obligation
What are the four exceptions to the entire obligations rule?
- acceptance of partial performance
- substantial performance
- divisible obligations
- wrongful prevention of performance
What constitutes acceptance of partial performance?
Where one party has given only partial performance of the contractual obligations, it is possible that the innocent party, rather than reject the work done, might accept that part of the performance. However, it should be noted that such an acceptance of partial performance is at the discretion of the innocent party. If the innocent party voluntarily accepts partial performance,
then the party in default will be entitled to payment on a quantum meruit basis.
Quantum meruit (meaning as much as is deserved) is a remedy whereby the claimant may be able to claim a
reasonable sum so that the defendant is not unjustly enriched. The court will assess the value of a quantum meruit award on an objective basis using the information available to it, for example the usual market price for goods or services.
In Sumpter v Hedges (1898) 1 QB 673 Sumpter had agreed to build two houses with stables on Hedges’ land, in return for a fixed price. After completing work worth around half of the contract price, Sumpter told Hedges that he did not have enough money to finish the job, so Hedges did it
for himself.
In Sumpter v Hedges, because the work had been done on the innocent party’s land, the court felt that the innocent party had no choice but to complete the work. He was in possession of what he could not fail to keep. This was not voluntary acceptance of partial performance as the innocent party did not have the option to take or not to take the benefit of the work done. If the court had found otherwise, however, the builder would have been entitled to a quantum meruit to compensate him for the value of the work done. In the event, he was entitled to compensation for the value of the materials which he had left on site which had not been incorporated into the
building which the innocent party used to complete the work. This was because the innocent party had the choice as to whether or not to use these, as they could have been returned.
What constitutes substantial performance?
Where a contract has been substantially performed, it may be possible for the party who rendered such substantial performance to obtain the contract price subject to a deduction to reflect the cost of remedying the ‘defect’ (ie the aspect which has not been performed). When
considering such a plea, the court considers the nature and extent of the defect, which is done by measuring the cost of remedying the defect against the contract price. If the defect is too serious, the party who rendered the defective performance will not be entitled to recover any money.
However, if substantial performance is found to have been rendered, then the party will be entitled to the contract price subject to a deduction.
In defining what is ‘substantial performance’, the court takes a similar approach to when deciding whether has been a repudiatory breach of contract: the question is whether the defect goes ‘to
the root of the contract’.
What are divisible obligations?
Some contracts are clearly intended to be divided into parts, eg the payment of a salary under a fixed contract of employment. If this is the case, then the performing party is entitled to payment
for each part which is performed. However, the question as to whether a contract is divisible or entire depends upon the intention of the parties.
What constitutes wrongful prevention of performance?
Where one party performs part of the agreed obligation, and is then prevented from completing the rest by some fault of the other party, they will be entitled to payment despite not having completed the rest of the obligation (Planche v Colborn (1831) 131 ER 305). The innocent party has
two options:
(a) To sue for damages for breach of contract; or
(b) To claim a quantum meruit.
What is tender of performance?
In an action for breach of contract for failing to perform an obligation, it is a good defence for the defendant to show that they ‘tendered performance’. In order for a plea of tender to be successful, the promisor must show that they unconditionally offered to perform their obligations in accordance with the terms of the contract, but that the promisee refused to accept such performance. For instance, if the seller delivered goods but the purchaser refused to accept delivery, the seller would be relieved of liability for failing to deliver. In relation to payment of a debt, a plea of tender does not discharge the debt. However, it would prevent the creditor from claiming interest or damages on that debt subsequent to the tender of performance.
What constitutes discharge by agreement?
On the basis that something may be destroyed in the same manner by which it was created, a contractual obligation may be discharged by agreement. This may occur in one of two ways:
(a) By a subsequent binding contract between the parties; or
(b) Alternatively, by operation of a term of the original contract.
How may discharge by subsequent binding contract occur?
For instance, where both parties have obligations which remain unperformed, the contract may be discharged by mutual waiver. This is a new contract by which each party agrees to waive their rights under the old contract in consideration for being released from their obligations under the
old contract.
This type of arrangement is very common in commercial situations where parties wish to end an existing contract and achieve commercial certainty. They will often agree the terms of a termination agreement to release and settle any liabilities under the original contract so that they can be sure that they will have no further liabilities or obligations arising from it in the future.
For this discharge to be effective, two elements must be present, sometimes called ‘accord and satisfaction’: there must be agreement that the obligation will be released (‘accord’), and there must be consideration for the promise to release a party from the obligation (‘satisfaction’).
How might difficulties regarding considerations be resolved when discharging a contract?
One way of resolving this issue is that the party to whom the obligation is owed may release the other party by a subsequent agreement under deed. This avoids the need for consideration altogether, because a gratuitous promise (one without any consideration) is enforceable if made
in a contract in the form of a deed.
Alternatively, the party to whom the obligation is owed may provide consideration by agreeing with the other party to accept something different in place of the former obligation, for example the accelerated payment of a sum payable in instalments.
Where there has been accord and satisfaction, the former obligation is discharged. The essential point is that, unless there is a new consideration, there can be no satisfaction, ie there can be no
discharge of the previous agreement and no formation of an agreement on new terms.
Can discharge by the operation of a term in the contract occur?
There is no reason why a contract should not contain a term providing for the discharge of obligations arising from the contract. Such a term may be either a condition precedent or a condition subsequent.
What is a condition precedent?
A condition precedent is a condition which must be satisfied before any rights come into existence. Where the coming into existence of a contract is subject to the occurrence of a specific event, the contract is said to be subject to a condition precedent. The contract is suspended until
the condition is satisfied. Where a condition precedent is not fulfilled, there is no true discharge because the rights and obligations under the contract were contingent upon an event which did
not occur, ie the rights and obligations never came into existence in the first place.
What is a condition subsequent?
A condition subsequent is a term providing for the termination of the contract and the discharge of obligations outstanding under the contract, in the event of a specified occurrence.