Discharge Of Contract - Discharge By Perfomance Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What does discharge of contract mean?

A

-The contract has been completed and come to an end

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the three ways that contracts can be discharged?

A
  1. By performance
  2. By frustration
  3. By breach (depending on term)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What does by performance mean?

A

-Both parties have done exactly what they promised
-eg one party has delivered and the other party has paid. If don’t deliver then don’t have to pay
-Courts: if performance incomplete then the contract had not been discharge

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Case for discharge by performance (MUST INCLUDE)

A

-Cutter v Powell
-Agreed to work as sailor on voyage to another country. In contract said lump sum when get back. Died near end of the voyage. Widow tried to sue for his proportion.
-Had not completed his part of the bargain so not discharged and didn’t have to pay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are the 5 exceptions to the performance rule?

A

-Divisible contracts
-Substantial performance
-Full performance prevented by D
-D accepted part-performance from C
-Late performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Divisible contracts explanation

A

Where contract seen as being separate parts non-completion of one part not a breach of whole. In Cutter v Powell, if $1 a day then divisible

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Case for divisible contracts

A

-Ritchie v Atkinson
-Ship owner agreed to carry cargo at agreed rate per ton, carried only part of the cargo.
-Entitled to be paid for the cargo he had carried at agreed price per ton
-liable in damages for breach of control for not carrying whole cargo

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Explain substantial performance

A

-If party done almost everything required under contract, substantial performance may apply
-where it does, must be payment of amount for what’s been done
-(only trivial details missing)
-Not apply to contracts where considered whole contract and all obligations single transaction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Case for substantial performance

A

-Dakin v Lee
-Builders agreed to repair for $1500. Performed completely but poorly. Cost $80
-Court said contract substantially/precisely performed. Fact it had been done badly didn’t mean it had not occurred
-Entitled to be paid the price with deduction for defective work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When is performance not substantial?

A

-If what has been done so far removes the whole benefit of the contract or causes further damage

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is the case for ‘removing whole purpose or causes further damage”?

A

Bolton v Mahadeva
-Builder agreed to install central heating system for $560. Installation defective and caused fumes, didn’t work. Repairs = $170
-Court said entitled to nothing as not substantial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Full performance prevented by D - explain

A

-If one party prevents other from carrying out his contract then the innocent party can claim to be paid on a quantum meruit basis (as much as its worth)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the case for full performance prevented by D?

A

-Planche v Colburn
-Publisher hired author to write 1 series of books. When publisher decided to abandon, author prevented from completing but not his fault
-Entitled to recover a fee for wasted work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Explain D accepted part performance by C

A

-if one party agreed other party need not complete
-contract must be paid on quantum meruit basis.
-party entitled to be paid for what completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the case for D accepted part performance by C

A

-Sumpter v Hedges
-Builder agreed to build two houses, completed half and ran out of money
-Customer completed the work, argued by completing half himself, C accepted part performance
-D had no choice, left half completed house, builder not entitled to be paid as insufficient
-Used materials left by the builder so awarded sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Explain late performance

A

-Delay to performance to be treated as a breach of condition if any points present. If none present default position is for delay to be treated as a breach of innominate term, effect of breach examined.
-Was there a deadline in the contract? How important was the deadline? To distinguish between condition and warranty.
-Delivery must happen within reasonable time, if doesn’t then can set deadline that is a condition

17
Q

Case for late performance

A

-Charles Rickards Ltd v Oppenheim

18
Q

Charles Rickards Ltd v Oppenheim

A

-Buyer of rolls Royce car chassis agreed for body built on by fixed date. Not completed
-Buyer pushed for delivery, said unless delivered in 4 weeks then would cancel. When completed rejected
-C entitled to cancel as time is of the essence

19
Q

Tender of performance explanation and case

A

-A formal offer to carry out an obligation specified in a contract or legally required
-Startup v MacDonald
-Contract stated that 10 tons of oil were to be delivered to the dft. Delivered oil at 8.30pm on Saturday 31st march. Defendant refused due to the hour
-C had tendered performance within the agreed contractual acceptance. Entitled to damages for non-acceptance