*DISCHARGE OF A CONTRACT BY PERFORMANCE AND BREACH* Flashcards
What is the doctrine of complete performance?
- where both parties complete the contract and do both of their obligatory duties ie complete performance
- Cutter v Powell demonstrates this doctrine
- performance of contractual obligations must be precise and exact
Exceptions to the doctrine of complete performance?
1) wrongful prevention of performance by other party
- e.g if person asking for service changes mind halfway through
- they would be in breach of contract so other party would bring a claim to recover damages
- would be able to recover their loss of profit
- or claim a quitus meruit which is a claim in restitution
2) voluntary acceptance of partial performance by other party
- Sumpter v Hedges
- could claim quitus meruit
- e.g driver drives goods halfway and other party agrees to pick up from there
- some damages should be recoverable for partial performance
3) substantial performance
- in order for this to apply the work must be finished but slightly defective
- then it is necessary to consider the nature and extent of the defects
- compare contracts price with amount needed to rectify the defects
- Hoenig v Isaacs
- Bolton v Mahadeva
4) divisible obligations
- this is where the parties have agreed payments for a distinct part or stage of work
- here each part or stage is treated like a separate contract
What must be present for discharge by agreement to be valid?
- where the parties to a contract may agree to release one another form outstanding obligations
- there must be offer, acceptance, consideration and contractual intention
What is a condition, warranty and innominate term?
Condition: major term
Warranty: minor term
Innominate term: neither condition or warranty
How do you determine whether something is a condition or warranty? What will be the appropriate remedy for the three different terms?
- court do objective test where they look at whether a reasonable person would think parties intended term to be a condition or warranty
- it will often say in contract whether it is a condition by using the word specifically however, in Schiller v Wickman Machine Tool Sales ltd the parties had described term as a condition but it wasn’t one in legal sense
- if it’s a condition then innocent party can terminate contract and recover damages
- its a warranty then innocent party cannot terminate contract but can sue for damages
- if its an innominate term it depends on whether the entire benefit of the contract has been stripped
Hong Kong Fir Shipping Co ltd v Kawasaki Kisen Kaisha Ltd
- a test which should be used to determine whether innocent party can terminate the contract was to ask if that event had occurred ie the breach of contract, had substantially deprived the whole contract
Advantages and disadvantages of classification of terms?
A:
- certainty, meaning both parties know what’s at stake
D:
- unfairness
- party may use breach of contract to terminate even if breach is minor
Are ss13 to 15 of the SGSA 1982 a condition/warranty or innominate term?
- because these are IMPLIED terms, they are treated as innominate
What is an action for an agreed sum?
- if one party shall pay a sum of money to the other and the time arises for them to pay but they refuse, then the payee can bring a claim for agreed sum
- this is called a debt action
- remoteness and mitigation need not be an issue its a straightforward payment
When can a party terminate a contract?
- if a condition is broken then could TERMINATE
- if warranty then sue for DAMAGES and not terminate
- if an innominate term is broken then can only terminate if the innocent party has been deprived of the whole benefit of contract
If a breach does entitle the party to terminate, what is the breach called?
Rescinded/ repudiatory
What is the effect of termination?
- the contract is at an end and future obligations will be
discharged. - this means that neither party need perform any future obligations under the
contract. - the innocent party can also sue for damages for any loss suffered.
- the decision to terminate must normally be communicated to the other party.
What is the effect of affirmation?
- contract is not over and both parties should continue to perform their obligations.
- if the innocent party does decide to affirm the contract, the innocent party should make it clear that it is treating the contract as continuing.
- the innocent party can still claim damages for loss suffered.
What is the special remedy for sale of goods contracts?
- if there is a breach of ss9-11 of CRA 2015 or s13 or 14 of SGA 1979, the buyer could be entitled to reject the goods
What is an anticipatory breach?
- if a party gives advance warning that they will not be complete in contract when they are meant to
- the other party can terminate and sue for damages immediately
- or they can continue with contract in hopes that other party will complete contractual obligations