Discharge by performance, agreement, breach and/or frustration Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

Ways in which a contract might be discharged

A

(a) Performance
(b) Agreement
(c) Breach
(d) Frustration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discharge by performance - the entire obligations rule

A

The promisee is entitled to the benefit of complete performance exactly according to the promisor’s undertaking. A promisor who only performs part of their obligation is not discharged from that obligation.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Exceptions to the entire obligations rule

A

(a) Acceptance of partial performance
(b) Substantial performance
(c) Divisible obligations
(d) Wrongful prevention of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Acceptance of partial performance

A
  • Possible that the innocent party might accept part of the performance.
  • If the innocent party voluntarily accepts partial performance, then the party in default will be entitled to payment on a quantum meirut basis (‘as much as he deserves’)
  • the court will assess a quantum meirut award on an objective basis
  • Sumpter v Hedges: there had not been voluntary acceptance of patrial performance because the court felt that the innocent party had no choice but to complete the work.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Substantial performance

A

Where a contract has been substantially performed, it may be possible for the party who rendered such substantial performance to obtain the contract price subject to a deduction to reflect the cost of remedying the ‘defect.’

  • The court considers the nature and extent of the defect, by measuring the cost of remedying the defect against the contract price.
  • If the defect is too serious, the party who rendered the defective performance will not be entitled to recover money.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Divisible obligations

A
  • Some contracts are clearly intended to be divided into parts, e.g. a fixed contract of employment
  • If this is the case, then the performing party is entitled to payment for each part when it is performed
  • The question as to whether a contract is divisible or entire depends upon the intention of the parties
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Wrongful prevention of performance

A

Where one party performs part of the agreed obligation, and is then prevented from completing the rest by some fault of the other party, he will be entitled to payment (Planche v Colborn)

The innocent party has two options:

(1) sue for damages for breach of contract
(2) claim a quantum meirut

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Defences to allegations of a failure to perform

A
  • Tender of performance: The promisor must show that he unconditionally offered to perform his obligations in accordance with the terms of the contract, but the promisee refused to accept such performance e.g. if the seller delivered goods but the purchaser refused to accept delivery
  • Performance by a third party: It is possible that the service can be provided by a third party, but this is not always the case. Robson v Drummond: a person had agreed to keep a carriage in repair for five years by the court but was not entitled to delegate performance as this was seen as a contract of personal service. British Waggon v Lea: permissible for a contract to let out railway wagons and to keep them in repair to be performed by someone else. It did not matter to the hirer who kept the wagons in repair.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Two ways to discharge by agreement

A

(a) By a subsequent binding contract between the parties;

(b) By operation of a term of the original contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Discharge by subsequent binding contract

A

Where both parties have obligations which remain unperformed, the contract may be discharged by mutual waiver. This is a new contract by which each party agrees to waive their rights under the old contract in consideration for being released from their obligations under the old contract. (Wilson)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Elements required for discharge by subsequent binding contract

A

(1) Accord (agreement to release obligation)
(2) Satisfaction (consideration for the promise)

This can raise difficulties where one party has performed his obligations but something remains to be done by the other. This may be resolved by releasing the other party by subsequent agreement under deed instead, or offering something different as consideration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Discharge by operation of a term in the contract

A

Such a term may be either a condition precedent or a condition subsequent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Condition precedent

A
  • A condition which must be satisfied before any rights come into existence.
  • Where until a specific event occurs, the remaining rights and obligations in the contract are not binding.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Condition subsequent

A

A term providing for the termination of the contract an discharge of outstanding obligations in the event of something specific happening (Head v Tattersall)

e.g. when a particular date occurs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Discharge for breach

A
  • Usual remedy for breach of contract is an award of compensatory damages
  • In certain circumstances, the innocent party may treat the contract as terminated for repudiatory breach. This is where one party has breached a term which is either a condition or innominate term to be treated as a condition (Bettini v Gye)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Party’s choice

A

Generally, where there has been a repudiatory breach, a party has a choice as to whether to terminate or affirm. The choice is not entirely unrestricted.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Anticipatory breach

A
  • Where a party indicates he will not perform his contractual obligations in advance of the date for performance.
  • A party who, by words or conduct, leads a reasonable person to conclude that he does not intend to perform his part of the contract is said to have ‘renounced’ the contract.
  • The innocent party has an immediate right to accept the renunciation and treat the contract as terminated.
  • Hochster v De la Tour: An indication that a party will only not perform his contractual obligations in a minor regard will not give rise to the right to terminate. If a party wants to rely on an anticipatory breach to terminate, then it will need to demonstrate that had the breach occurred at the time the performance was due, it would have been repudiatory.
18
Q

The effect of terminating a contract for repudiatory breach

A
  • Where a contract is terminated for a repudiatory breach this puts an end to all primary obligations of both parties remaining unperformed.
  • The innocent party can claim damages arising from the breach but also the loss of the contract
  • available only in exceptional cases: the Hong Kong Fir test, the breach should ‘deprive the injured party substantially of the whole benefit of the contract.’
  • any rights and obligations which have accrued before termination remain enforceable.
19
Q

The risk of wrongful termination

A
  • Termination of a commercial contract for repudiatory breach involves a high degree of risk
  • If a court later finds out it was a breach of warranty and the party had no right to terminate, it will be that party who is actually now in repudiatory breach
20
Q

The right of election

A

Where there has been a repudiatory breach, the contract is terminated only if the aggrieved party makes the election to treat the breach as repudiating the contract. The innocent party must make its decision to terminate the contract known to the party in default (Vitol v Norelf)

When a party makes a choice whether to affirm or terminate, he will only be bound by the choice if he was aware of all the facts giving rise to the right to elect, and of the fact that the right to elect existed (Peyman v Lanjani)

The innocent party is allowed a period of time in which to decide.

21
Q

Benefits of affirmation

A
  • the contract survives and the rights of the innocent party are preserved
  • might be a simpler choice if it relates to a major project rather than finding a new contractor
  • the values of a damage claim is uncertain so might be financially wiser
  • where a party has indicated an intention not to perform its obligations, the innocent party can still affirm, perform its own obligations and claim the sum due under the contract (although damages would of course only be for breach and not for the loss of the contract as a whole) (White v McGregor)
22
Q

How a contract is affirmed

A
  • must be evidence of a clear and unequivocal commitment to continuing with the contract (Yukong v Rendsburg)
23
Q

Limits on affirmation

A

A claimant would not be entitled to affirm and would be confined to a claim in damages if:

(a) The co-operation of the breaching party is required for continued performance of the contract;
(b) The innocent party has no ‘legitimate interest, financial or otherwise’ in affirming the contract

In relation to (a), if the innocent party requires co-operation of the breaching party, this will also prevent the innocent party claiming the contract price.

24
Q

When will the innocent party not have legitimate interest in affirming the contract?

A
  • only in extreme cases where:
  • (a) the burden is on the contract breaker to show that the innocent party has no legitimate interest in performing the contract rather than claiming damages;
  • (b) This burden is not discharged by merely showing that the benefit to the other party is small in comparison to the loss to the contract breaker;
  • (c) applies only in extreme cases, where damages would be an adequate remedy and where an election to keep the contract alive would be unreasonable
25
Q

Discharge by frustration

A

‘Frustration occurs whenever the law recognises that, without default of either party, a contractual obligation has become incapable of being performed because the circumstances in which the performance is called for would render it a thing radically different from that which was undertaken by the contract.’ (Davis Contractors v Fareham)

26
Q

Things that are not a frustrating event

A

(a) If it is caused by the default of a party
(b) If it is provided for in the contract
(c) If it is merely an increase in expense or onerousness
(d) If it is something which the parties could reasonably have contemplated.

27
Q

What happens when a contract is frustrated?

A

If a contract is frustrated, it is brought to an end automatically. Frustration may be raised as a defence to an action for breach of contract.

28
Q

What might render performance radically different

A

(a) Performance being impossible
(b) Performance being illegal or prevented by government intervention
(c) The common purpose of the contract being frustrated.

29
Q

Performance is impossible - examples

A

Taylor v Caldwell: contract to use a music hall for a series of concerts. Before the first concert, the Hall was destroyed by fire. No provision was made for this risk in the contract. Destruction was without the fault of either party, and the concerts could not be given as intended.

Condor v The Barron Knights: the drummer in a music group was taken ill. The contract was frustrated because the drummer was not capable of performing the contract in the way intended.

30
Q

Difficulties establishing whether performance is impossible

A

Tamplin SS Co v Anglo-Mexican Petroleum: the court had to decide whether the requisitioning of a ship for the purposes of war in Feb 1915 frustrated a 5 year charterparty which was to last until Dec 1917. The court held that it did not, on the basis that war would soon be over and a considerable proportion of the charterparty would remain.

However, amount of time left is only one consideration in establishing frustration. Factors to be considered too: the terms of the contract, its content, the parties’ knowledge, expectations, contemplations as to risk at the time of the contract

31
Q

Performance is illegal/prevented by government intervention

A
  1. Change in the law = e.g. where war breaks out, and to continue performance would be trading with the enemy (Fibrosa Spolka v Fairbairn)
  2. Government intervention = e.g. contractors required by government order to stop work and sell the plant (Dick Kerr v Met Water Board)
32
Q

Common purpose is frustrated

A

Krell v Henry: defendant hired a room to view the coronation procession. The processions did not take place on the days appointed. The contract was frustrated it was recognised by both parties that the foundation of the contract was to view the procession.

Herne Bay Steamboat v Hutton: steamboat company contracted to lend their steamboat to the defendant ‘for the purpose of viewing the Naval Review and for a day’s cruise around the fleet.’ Held that the defendant was not discharged from contractual obligations because (a) the object of hiring the vessel was the defendant’s alone and no concern to the plaintiff, and (b) the viewing of the Naval Review was not the foundation of the contract as they could have still cruised around the fleet.

33
Q

Merely an increase in expense/onerousness

A

Very rare for a contract to be held to have been frustrated by an event which leaves it possible to perform but simply makes it more onerous to one party.

34
Q

Caused by the default of a party

A

The party alleging self-induced frustration must prove that the other party is at fault.

35
Q

Which the parties could reasonably have contemplated

A
  • If you could have foreseen an event, but failed to make provision for it in your contract, the doctrine of frustration will be less likely to apply.
  • Flying Music Company v Theater Entertainment: the negative effect of civil unrest in Greece and the economic crisis could not amount to frustration because at the time the contract concluded there were already signs of unrest. The parties had the opportunity to deal with the risk in the contract.
  • Canary Wharf v European Medicines: key test is whether the event would have informed the manner in which the parties assessed the risk of entering into the contract. Highly theoretical risks which the parties would not have taken into account would not be relevant.
36
Q

Provided for in the contract

A
  • The doctrine of frustration cannot override express and unambiguous contractual provision for the frustrating event
  • Commercial contracts often contain a force majeure clause, which states what will happen should a set of circumstances materialise
  • Force majeure clauses often refer to acts of terrorism, war and acts of God.
37
Q

Consequences of frustration

A
  • common law set out consequences, but the common law was significantly altered by the Law Reform (Frustrated Contracts) Act 1943
  • The Act will govern most instances of frustrated contract but the common law remains important for 2 reasons:
  • (1) where the contract contains provisions dealing with the consequences of frustration, the Act will only apply to the extent that it is consistent with the contract - so it is possible for contracting parties to exclude the Act by prior agreement
  • (2) certain types of contract are not governed by the Act and so still subject to the common law
38
Q

Consequences of frustration at common law

A
  • The contract is terminated at the date of the frustrating event
  • Any rights which accrued before the frustrating event are enforceable (e.g. services performed but not yet paid for) but the parties are discharged from future obligations.
  • Issue arises where there has been an advance payment such that the customer has paid for services which have not yet been performed
39
Q

Issue with advance payments

A
  • where there has been a total failure of consideration, money already paid could be recovered and money due and payable need not be paid (Fibrosa Spolka)
40
Q

Consequences under statute - the Law Reform (Frustrated Contracts) Act 1943

A
  • does not apply to future obligations. If a frustrating event occurs, future obligations are automatically discharged by the common law. The Act deals with obligations arising prior to the frustrating event.
  • Section 1(2) - money paid can be recovered, even though the failure of consideration may only be partial. Money payable will cease to be payable
  • also gives the court discretionary power to order retention or recovery of money as it thinks JUST in all the circumstances to account for expenses incurred by the payee
  • the amount retained or recovered is capped and cannot exceed (i) the actual expenses incurred and (ii the amount paid or payable prior to the frustrating event.
  • s 1(3) - a party who has gained valuable benefit under the contract before the frustrating event may be required to pay a just sum for it.
  • ‘benefit’ means the end product of the claimant’s services, not the services themselves.
  • where the value of the benefit has been reduced to nil by the frustrating event, the provider of the ‘benefit’ has no claim.