Discharge and breach Flashcards
What are the 4 methods of discharge?
- Performance
- Agreement
- Breach of a condition (or serious breach of an in-nominate term)
- Frustration
what is a breach of contract?
- A failure without lawful excuse to perform a contractual obligation allows for the rightful termination of the contract
- In addition damages can be claimed
Breach can take 3 different forms, what are they?
- Defective performance
- Non-performance
- Incapacitating oneself from performing
Is breach of contract strict liability?
- Yes it is not usually needed to prove fault to establish existence of a breach
Does every breach of contract give right to termination fo the contract?
- No, although damages can be claimed in each situation to receive any loss
What determines whether there is a right to terminate a contract?
- Depends upon the nature of the term that was breached (whether or not it is a condition)
- Also depends on the consequences of the breach
White and carter Ltd v McGregor 1961
- Recognises that the innocent party may ignore a breach in order to continue with performance and claim the contract price
An example of a failure to perform that does not mean a breach of contract
- Buying theatre tickets and then not picking them up or going to the performance ( The purchaser had not agreed to go to the performance but instead to pay for the tickets)
An example of a lawful excuse?
- defective goods being delivered and therefore the buyer refusing the pay
Where does a contract become discharged through performance?
-where both parties have fully performed their contractual obligations.
what is a discharge through full performance?
- Where there is an existence of an entire contract
Moore & Co v. Landauer & Co [1921]
- S contracted to sell to B just over 3000 tins of fruit
- Contract stated that tins were to be packed in cases of 30 tins each
- About half were delivered in cases of 24 tins each
- No suggestion this actually caused any significant hardship to B
- Nonetheless, clear breach
- The de minimis exception DID NOT apply
Arcos Ltd. v. EA Ronaasen [1933]
- Contract for sale of staves of wood 1/2 an inch thick
- Seller delivered wood 9/16 of an inch thick
- Court held seller was in breach of contract
- Shows that the exception to the de minimis rule is extremely narrow and can not be used in this case
Shipton Anderson v. Weil Bros [1912]
- S and B contracted for 4500 tons of wheat, 10% more or less
- S delivered excess of 55lbs
- Strictly, S in breach, even though he did not seek payment of the additional 4 schillings representing the contract price for the extra 55lbs
- However, court applied the maxim de minimis the discrepancy was SO TRIFLING that it was not regarded as a breach
Union Eagle v Golden Achievement [1997] (Time of performance)
- Union Eagle were supposed to pay a deposit for a flat and time was said to be ‘of the essence’.
- clause 12 said failure to complete meant the deposit was forfeit and the agreement rescinded.
- They were 10 minutes late.
- certainty was needed in the business world, particularly in a volatile market. Accordingly, the contract’s terms should be strictly enforced, and Union Eagle lost its 10% deposit.
What is performance of a contract?
- Doing that which is required by a contract.
- The effect of successful performance is to discharge the person bound to do the act from any future contractual liability.
What is an entire obligation?
- Where the person has an entire obligation to complete the contract before they are entitled to any payment
- No payment is necessary even 3/4 through
What is a severable obligation?
- A severable contract is a contract that is composed of several separate contracts between the same parties, so that failing (breaching) one part of such a ‘severable’ contract does not breach the whole contract.
Cutter v Powell (1795)
- The claimant’s husband agreed by contract to act as a second mate on the ship on a voyage to Jamaica.
- He was to be paid on completion
- Six weeks into the voyage the claimant’s husband died. The claimant sought to claim a sum to represent the six weeks work undertaken.
- wife’s action failed. Payment was on condition that he worked till the end and as he did not he was entitled to nothing
- He had an ENTIRE obligation
- However he could not be held liable as he had a lawful excuse as to why he did not fully perform
Ritchie v Atkinson (1808)
- A and B contracted for B to deliver a certain quantity of cargo to A, at £X per ton carried
- B delivered less than contractually required
- Court held B was entitled to payment, at the contractual rate of £X per ton, for the quantity delivered
- Fact that payment was calculated at price per ton evinced intention that obligation was to be severable
What is substantial performance?
- when [B] fully performs his contract in the sense that he supplies all that he agreed to supply but what he supplies is subject to defects of so minor a character that he can be said to have substantially performed his promise’
Hoenig v Isaacs [1952]
- A contracted w/B for B to refurbish A’s flat for £750
- B substantially completed the work, w/some, minor defects
- These could have been remedied for about £55
- CA held that the obligation was an entire one
- Nonetheless, their Lordships held B was entitled to full payment less the value by which the work was diminished by reason of the breach
- Case of substantial performance
Hochster v De La Tour (1853)
- In April 1852, B employed A as a courier to work for him for 3 months from 1st June
- On 11th May, B told A that A’s services would no longer be required
- On 22nd May, A sued B for damages
- B accepted he was in breach but claimed A should not be able to sue until B had committed a “performance” breach (i.e., 1st June or after)
- Court held A could bring action any time after anticipatory breach committed, even before contract performance was due
- And he was entitled to damages from the time of the breach
- Therefore anticipatory breach
What is affirmation of a contract?
- Where a party wishes to keep a contract alive
- if it can be shown that a person has no legitimate interest, financial or otherwise, in performing the contract rather than claiming damages, he ought not to be allowed to saddle the other party with an additional burden with no benefit to himself’