Discharge Flashcards

1
Q

Discharge by performance

A

The general rule as set out in Cutter v Powell is that performance must be complete and exact

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are the 4 exceptions to Cutter v Powell

A

Divisible Contracts: If contract contains divisible elements, non-completion of one part doesn’t breach whole contract - Ritchie v atkinson
Substantial Performance: Party has done substantially what is required (quantum meruit payment) - Hoenig v Issacs
Prevention of full performance: one party prevents the other from carrying out the contract (innocent party has quantum meruit claim) - Planche v Colburne
Acceptance of Part Performance: One party has agreed to accept part performance and will pay quantum meruit. Requires specific acknowledgment made voluntarily and w/o undue pressure - Sumpter v Hedges

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Inclusion of specific time term for performance

A

Time is a warranty (Charles Rickards v Oppenheim) unless;
a. Expressly stated in contract that time is of the essence; or
b. In the circumstances, time is critical; or
c. A party has failed to complete on time, so a new time limit has been placed (new condition)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Discharge by breach - Repudiatory Breaches

A

Breach of any term allows for damages claim, but only breaches of condition or sufficiently serious innominate term allow for repudiation of contract.
Repudiatory Breach = Breach of condition, Sufficiently serious breach of innominate term, Refusal to perform
if repudiatory breach is established, innocent party can terminate contract and claim damages OR continue it and claim damages

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Discharge by breach - Non-Repudiatory Breaches

A

Non-repudiatory Breach = Renunciation of liabilities, Impossibility created by own act, Total or partial failure of performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Actual or Anticipatory breach?

A

Actual Breach = Breach which occurs at time of or during performance
Anticipatory Breach = Where party gives notice in advance that he will not be performing/ completing contract
-Can be express or implied if it led other party to reasonable conclusion
-Uncertainty or unlikelihood not allowed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Courses of action after anticipatory breach

A

(Hochester v de la Tour)
a. Sue immediately for breach of condition
-must take reasonable steps to mitigate loss
b. Wait for time of performance and sue for actual breach
-loss may increase, but carries risk of frustration

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Discharge by Frustration

A

= contract prevented by event outside of parties’ control (National Carriers v Panalpina)
1. Impossibility of performance
2. Radical change of circumstances so purpose cannot be achieved
3. Contract becomes illegal to perform

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When frustration doesn’t apply

A
  1. Self induced frustration/ within control of party - Maritime National Fish v Ocean Trawlers
  2. Contract becomes less profitable - Davis Contractors v Fareham
  3. Foreseeable risk - Amalgamated Investment v John Walker and sons
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Remedies for frustration

A

Common law = automatic termination at moment of frustration
= obligations up to frustration to be completed
Law Reform (Frustrated Contracts) Act 1943:
- s1(2) = money paid and payable before event are recoverable
= future payment obligations end
- s1(3) = party obtaining valuable benefit must pay its value as just
- s1(4) = payment of expenses and overheads as reasonable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Cutter v Powell

A

In entire contracts, partial performance does not entitle a party to payment unless the contract explicitly allows for it.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Ritchie v Atkinson

A

Contract can be considered divisible if it specifies payment per unit (e.g., per ton), allowing for payment for the portion of the contract that has been fulfilled, while also permitting the other party to claim damages for the unfulfilled portion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Hoenig v Isaacs

A

If a contractor substantially performs their obligations under the contract, they are entitled to payment of the contract price, minus any damages for defects or incomplete work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Planche v Colburne

A

A party who has been prevented from completing a contract due to the other party’s breach may recover damages on a quantum meruit basis for the work already done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Sumpter v Hedges

A

Concerned the concept of entire contracts and the recovery of payment for partial performance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Hochester v de la tour

A

a party can sue for anticipatory breach of contract as soon as the other party repudiates the contract, even before the date of performance.

17
Q

Maritime National Fish v Ocean Trawlers

A

Contract cannot be frustrated if the frustrating event is self-induced or foreseeable by the party seeking to rely on it.

18
Q

Davis Contractors v Fareham

A

Contract is not frustrated merely because its performance becomes more expensive due to unforeseen circumstances

19
Q

Amalgamated Investment v John Walker and sons

A

Court dismissed the appeal as they assumed the risk when making the contract