Discharge Flashcards

You may prefer our related Brainscape-certified flashcards:
1
Q

What is discharge

A

where a contract ends

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Discharge by performance

A

Strict rule that performance must be complete and exact

Cutters v Powell

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Cutters v Powell

A

C died near the end of voyage, widow sued for proportion of his fee. However, she was entitled to NOTHING as he had agreed to work the entire voyage and hadn’t done so.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

How has the harsh rule on discharge by performance been moderated

A
  • divisible contracts
  • substantial performance
  • prevention of full performance
  • acceptance of part performance
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Divisible contracts

A

Where contract can be seen as being separate parts, then non-completion of one part is not a breach of the whole contract.
Richie v Atkinson = ship owner agreed to pay per ton, C carried out only half of the cargo but was still entitled to payment for the amount of tons he had worked

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Substantial performance

A

if party has done substantially what was required than the doctrine will apply. Where it does apply there must be payment of the amount appropriate to what has been done.
DOES NOT apply where the contract is considered to be an entire contract where all obligations are seen as one and cannot be broken down (Cutter v Powel)
Dakin v Lee= work was completed to a low standard however the fact that it was poor execution doesn’t mean it hadn’t been done so the builder was entitled to be paid for the price subject to deduction

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is quantum merit

A

‘as much as It is worth’
applies to substantial performance whereby the claimant is to be paid for the work that has been done
Hoenig v Isaacs

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Prevention of full performance

A

if one party prevents another form carrying out the contract then the innocent can claim to be paid on a quantum merit = Planche v Colburn

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Planche v Colburn

A

publisher hired author to write book, publisher decided to abandon the series, author was prevented from performance through no fault of his own therefore he was entitled some payment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Acceptance of part-performance

A

If one party agreed to the other they do not need to complete the entire contract then they must be paid on a quantum merit basis. However the consent must be in the form of specific acknowledgement that the defaulting party is entitled to payment for what they have done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Sumpter v Hedges

A

D ran out of money to finish building so C had to do it. D argued C doing the work was acceptance of part-performance. However C had no choice but to accept part-performance and so the builder was not entitled to be paid for the work he had done.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

The effect of a term as to time for performance of a contract

A

The courts regard time as a condition if
- the [arties have expressly stated that time is of the essence of the contract
- when time for completion of the contract is critical
- one party has failed to [erform on time and the other has invited a new date for contract completion
IF NONE PRESENT THEN TIME IS TREATED AS A WARRANTEE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Discharge by frustration

A

If the party is prevented from carrying out the contract due to unforeseen intervening events then they would not be liable for breach of contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Taylor v Cladwell

A

Music hall burned down through no ones fault therefore he could no longer rent out the hall. The contract was frustrated and therefore he was not expected to compensate damages due to the discharge of the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is force majeure clause

A

Often seen in commercial contracts. Excludes liability for the parties for delay in performance or non-performance if there are extraordinary events.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Impossibility of performance

A

Frustration also applies where the subject matter becomes unavailable through no fault of the contracting parties.
Jackson v Union marine insurance - Long delay frustrated the contract

17
Q

Service impossibility of performance

A

Unavailability of the party performing the service
Robinson v Davidson = pianist made contract to perform, she became ill and was unable to attend. Her illness was a frustrating event

18
Q

The contract becoming illegal to perform

A

DM and D v James= the court said that a contract to import certain goods could be frustrated if importing goods of any kind becomes illegal after formation of the contract

19
Q

Radical change in circumstance - illegal performance

A

Krell v Henry = C paid for hotel to watch Prince coronation however Prince became ill and the event didn’t happen = contract was frustrated even though the hotel room could still be used
Herne v Hutton = C rented boat to watch the fleet and the kings coronation, the contract wasnt frustrated because he could still see the fleet

20
Q

When can frustration NOT apply

A
  • self induced frustration
  • contract becoming less profitable
  • the event being foreseeable risk or one that was mentioned in the contact
21
Q

Self induced frustration case

A

Maritime v Ocean trawlers = frustrating even was within the company’s control as it could have been allocated a licence to the hired boat.

22
Q

The contract has become less profitable

A

NOT a reason to rise frustration of contract as see n in Davis v Fareham

23
Q

The event being foreseeable or being mentioned in the contract

A

Amalgamated investment v John walker = building become a listed building not allowing redevelopment however that is why D Brought the building. Resulting in a huge decrease in value. Rejects frustration as listing is a risk associated with old buildings which the developers should have known.
pre-contract enquires shows they were aware

24
Q

Remedies for frustration

A
  • deposits are recoverable but money due is not
  • discretionary compensation to pay for work that has already been done
  • quantum merit
  • may order compensation to be paid for any valuable benefit one party may acquire under frustrated contract
25
Q

Discharge by breach

A

Where a party fails to perform his obligations under a contract, they might be sued for breach.
V will always be entitled to claim for damages.
Breach can be total failure to perform or failure to perform in accordance with the terms of the contract that could be seen as part-performance

26
Q

What are the circumstances giving rise to breach of contract

A
  • renunciation by a party of his liabilities under it
  • impossibility created by his own act
  • total or partial failure of performance
27
Q

What is anticipatory breach

A

When a party gives notice in advance to the other party that they will not be performing the contract.
Innocent party can choose to either sue straight or wait for the time agreed for performance and sue

28
Q

Hochster v de la tour

A

C was fired and could so sue immediately.

29
Q

Remedies for breach

A

anticipatory breach= claim for damages immediately, However V must take reaonsbale steps to mitigate the loss, can also repudiate
Actual breach = damages are assess in accordance to the detriment at the time performance was supposed to be done
breach of condition = damages and/or repudiation
breach of warranty = limited damages